Vertical Elements Horizontal Elements

Description of Work Remarks / Status


(Col / RW) (Slab/Beam)
Beams Reinforcement fixing Completed.
Lower Ground Floor (Pour - 2) Completed 23 May, 2017 Slab Reinforcement Shifting to Slab in Progress.
Pouring of Concrete in current week.

Scaffolding for Slab is in Progress.


Lower Ground Floor (Pour - 3) 20 May, 2017 05 June,2017
Beam Bottoms and Sides is in progress.

Scaffolding for Slab is in Progress.


Ground Floor Pour - 1 18 May, 2017 02 June,2017
Beam Bottoms and Sides is in progress.

Ground Floor Pour - 2 10 June, 2017 22 June, 2017

Ground Floor Pour - 3 20 June, 2017

First Floor Pour - 1 12 June, 2017 Form Work for Slab/beams

Raft 06 No. of Raft( 350-400 CM Each) will be Placed.

Retaining Wall Retaining wall will be in progress


POUR 1 GROUND FLOOR
POUR 2 LOWER GROUND FLOOR
POUR 3 LOWER GROUND FLOOR