LAPORAN PROGRESS PEMBANGUNAN

PERIODE : 22 DES 2016 – 22 JANUARI 2017 ( 1 BULAN)

N Periode Kegiatan Foto


o. Waktu
1 22 – 31 Bekisting column, wood
DES 2016 plank installment for
concrete pouring and
casting into the
intended shape

Bekisting Kolom,
Persiapan pemasangan
papan cor/ cetakan
sementara yang
digunakan untuk
menahan beton selama
beton dituang dan
dibentuk sesuai dengan
bentuk yang diinginkan
2 2 - 21 Concrete pouring on
JAN 2017 column cast.

Cor Tiang Kolom Beton

3 23 - 31 The finished concrete


JAN column.
2017
Lepas Bekisting Tiang
Kolom Beton
jadi
4 1 - 15 Iron placement (wire),
FEB 2017 bekisting and concrete
slab installment.

Pembesian, Bekisting
dan Cor Balok
5 16 - 21 Galvanite installment,
FEB 2017 waterproof foundation
on second floor.

Pemasangan BONDEX
6 21 - 25 Wire mesh installment.
FEB 2017
Pemasangan Wire Mesh
7 27 FEB - Concrete pouring on
28 upper deck.
MARET
2017 Cor Dak Atap
Due to this date to the end of march 2017, the process still continue on light brick (hebel), mortar
layering, plafond installment and last is flooring process. I can only advice you as such, that if you prefer
to go to Indonesia by 9 February, then we can choose the ceramic material, color and motive, paint color
for the interior and exterior so by march we can continue the progress on schedule. Among these thing,
maybe if you go to Indonesia, can you add the budget for the finishing process? because the budget for
this were already used for electronic appliances that we purchased on december 2016.