Activities Description Predecessor Duration Man-Days


Men

A Site Clearing --- 4 6 24

B Excavation A 9 6 54

C Structural Works B 200 12 2400

D Rough Wall C 50 6 300

Rough Exterior
E C&D 20 6 120
Plumbing

F Electrical Works C 24 6 144

G Interior Plumbing C 24 6 144

Installation of Doors
H D 27 8 216
and Windows

I Wall Finishes E&G 50 8 400

J Exterior Painting I 45 8 360

K Floor Finishes I 30 10 300

L Interior Painting K 45 8 360

M Exterior Fixtures J 21 6 126

N Interior Fixtures L 28 6 168

Site Work
O N 17 6 102
Landscaping

AVERAGE MANDAYS: 5418

AVERAGE NUMBER OF MEN: 12.50