Professional Documents
Culture Documents
hours, and Job B required 48 hours from now. The objective is to try and meet the due date of each job, but to start each job ju
taking into consideration the following:
In the first pass job A starts now, and job B starts immediately after that:
job A 32 24 0 32
job B 8 48 32 40
In the second pass each job stops when it is due, so job A would need to have started 8 hours ago:
job A 32 24 0 32 -8 24 1
job B 8 48 32 40 40 48
The third pass pushes job A later so that it starts at hour zero:
job A 32 24 0 32 -8 24 0 32
job B 8 48 32 40 40 48 40 48
job A 32 24 0 32 -8 24 0 32
job B 24 48 32 56 24 48 32 56
job A 16 24 0 16 8 24 8 24
job B 16 48 16 32 32 48 32 48
job A 8 24 0 8 8 16 8 16
job B 32 48 8 40 16 48 16 48
job A 16 24 0 16 -8 8 0 16
job B 40 48 16 56 8 48 16 56
=MIN(C34,F35) - pull stop is the earlier of the due time or the start of the next job
=MAX(D34,F34,I33) - push 2 start is the later of: the earliest start
the push start
the stop of the previous job
=H34+B34 - push 2 stop is the start plus hours
each job, but to start each job just in time. The logic works in 3 passes, and "shuffles" the jobs
Day 1 Day 2
8 16 24 32 40 48 56
1 1 1 1
1
1 1 1
1
1 1 1 1
1
1 1 1 1
1 1 1
1 1
1 1
1
1 1 1 1
1 1
1 1 1 1 1