1. TRACK LINK
1) REMOVAL
(1) Move track link until master pin is over Master pin
front idler in the position put wooden
block as shown.
(2) Loosen tension of the track link.
※ If track tension is not relieved when the
grease valve is loosened, move the
machine backwards and forwards.
※ Unscrew the grease nipple after release
the tension by pushing the poppet only
when necessarily required. Block
Grease leaking hole is not existing. So,
while unscrew the grease nipple, grease
is not leaking until the grease nipple is 130ZF8UC01
130ZF8UC04
2) INSTALL
(1) Carry out installation in the reverse order
to removal.
※ Adjust the tension of the track link.
90 ~ 110
130ZF8UC05
8-169
2. CARRIER ROLLER Frame
1) REMOVAL
(1) Loosen tension of the track link. Grease
valve
8-162(1)
130ZF8UC07
2) INSTALL
(1) Carry out installation in the reverse order
to removal.
8-170
3. TRACK ROLLER Frame
1) REMOVAL
Grease
(1) Loosen tension of the track link. valve
8-163(1)
140Z98UC05
8-163(3)
2) INSTALL
(1) Carry out installation in the reverse order
to removal.
8-171
4. IDLER AND RECOIL SPRING
1) REMOVAL
(1) Remove the track link.
For detail, see removal of track link.
130ZF8UC10
(2) Sling the recoil spring (1) and pull out idler
and recoil spring assembly from track
frame, using a pry.
·Weight : 215 kg (474 lb) 1
130ZF8UC11
2
3
130ZF8UC12
2) INSTALL
(1) Carry out installation in the reverse order
to removal.
※ Make sure that the boss on the end face
of the recoil cylinder rod is in the hole of
the track frame.
130ZF8UC13
8-172
3) DISASSEMBLY AND ASSEMBLY OF IDLER
(1) Structure
6 5
8
3
1 2
4
4
3
5
21078DA43
8-173
(2) Disassembly Press
① Remove plug and drain oil.
② Draw out the spring pin (7), using a
press.
7 8-166(1)
2
8-166(2)
4
8-166(3)
8-174
(3) Assembly
※ Before assembly, clean the parts.
※ Coat the sliding surfaces of all parts with 1 4 Press
oil.
① Cool up bushing (4) fully by some dry ice
and press it into shell (1).
Do not press it at the normal temperature,
or not knock in with a hammer even after
the cooling.
8-167(1)
5
7
8-167(2)
8-167(3)
8-167(4)
8-175
⑥ Install bracket (5) attached with seal (3).
8-168(1)
8-168(2)
8-168(3)
8-176
4) DISASSEMBLY AND ASSEMBLY OF RECOIL SPRING
(1) Structure
4 7, 8 6 5 3 2 14 1 9 10 11 12
13
130ZF8UC30
8-177
(2) Disassembly
Press
① Apply pressure on spring (3) with a
press.
※ The spring is under a large installed load.
This is dangerous, so be sure to set 4
properly. 7, 8
·Spring set load : 8497 kg (18733 lb) 6
② Remove bolt (7), spring washer (8) and 5
lock plate (6).
3
③ Remove lock nut (5).
Take enough notice so that the press
which pushes down the spring, should
not be slipped out in its operation.
④ Lighten the press load slowly and
remove bracket (4) and spring (3).
130ZF8UC31
13
130ZF8UC32
130ZF8UC33
8-178
(3) Assembly
Install dust seal (11), back up ring (10) 1 9 10 11
and rod seal (9) to body (1).
※ When installing dust seal (11) and rod
seal (9), take full care so as not to
damage the lip.
130ZF8UC33
(94.0±3.6 lbf·ft)
130ZF8UC34
130ZF8UC35
8-179
⑥ Lighten the press load and confirm the Press
set length of spring (3).
⑦ After the setting of spring (3), install lock
plate (6), spring washer (8) and bolt (7).
7, 8
6
5
3
405±1.5 m
130ZF8UC36
8-180