SINGLE STOREYED STEEL+RCC SCHOOL BUILDING

39‐Schools Reconstruction Project, Rakhine State, UNICEF MYANMAR
WEEKLY PROGRESS REPORT (42) Date: 14.12.2017
February'2017 March'2017 April'2017 May'2017 June'2017 July'2017 August'2017 September'2017 October'2017 Novemer'2017 December'2017 Overall
No. DESCRIPTION OF WORK
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 5 6 7 8 Progress %
III BATCH A, (LOT 3) Contractor Asia Myanmar Dragon Co., Ltd.
3.1 60'x24'x4'Plinth School Building, Ma‐Beit Taung (MB 11), Minbya Township 87.00%

3.1.0 Site Assessment Completed Finished


3.1.1 Foundation Excavation Completed 3.00%

3.1.2 Founadtion PCC Completed 3.00%

3.1.3 Short Column Up to G-Beam Completed 3.00%

3.1.4 Ground beam Completed 5.00%

3.1.5 Slab Form Work Completed 3.00%

3.1.6 Short Columns Completed 3.00%

3.1.7 Plinth Beam Completed 5.00%

3.1.8 Steel Structures Fabrication & Delivery Completed 8.00%


3.1.9 Steel Structures Erection (Portal Frame) Completed 4.00%

3.1.10 Roofing Completed 3.00%

3.1.11 Flooring Completed 5.00%

3.1.12 Brick Walling Completed 5.00%

3.1.13 Doors and Windows On going 2.50%

3.1.14 Plastering & Black Board Completed 3.00%


Thingyan Holidays

3.1.15 Hand Railing and Ramp On going 1.00%

3.1.16 Ceiling Completed 5.00%

3.1.17 Painting On going 3.25%

3.1.18 MEP On going 1.25%

3.1.19 Toilets/Septic Tanks On going 8.00%

3.1.20 Water Collection Tank On going 4.00%

3.1.21 Utility / Store On going   3.00%

3.1.22 Drainage On going 6.00%


Prepared by: Yi Yi Khin, CSC Ltd. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44