EOT Timeline
EOT Timeline
2/1/2018 2/28/2018
56 Days
Project
Completion
Date
Matters to consider
Only activity affected is the opening of the bridge- No other acitivities in delay due t
3/29/2018
Days
Engineer Instruction
Received/Approved
Drawings
Engineer Instruction
Received/Approved New Project Completion
Drawings Date