Extension of Time Claim - Guard Rail

Period of Delay = 29/03/18-01/02/18 = 56 Days

2/1/2018 2/28/2018
56 Days

Contractor letter requesting


Engineer instruction by
01/02/18 in order to proceed Project
with works by agreed Completion
completion date of 23/02/18 Date

Prolongation Period = 01/05/18 -23


2/23/2018
68 Days

Project
Completion
Date

Matters to consider
Only activity affected is the opening of the bridge- No other acitivities in delay due t

Reasons for standing time due to Cathodic Protection not Handrail.


Previously mentioned no intention to claim for Cathodic Protection
/18-01/02/18 = 56 Days

3/29/2018
Days

Engineer Instruction
Received/Approved
Drawings

Prolongation Period = 01/05/18 -23/02/18 = 68 Days


3/29/2018 5/1/2018
68 Days

Engineer Instruction
Received/Approved New Project Completion
Drawings Date

f the bridge- No other acitivities in delay due to the instruction

odic Protection not Handrail.


claim for Cathodic Protection