Status of Claims and Payments as on 31.01.

2018
S.  State Name of the Company /Concessionaire  Date of  Date of Confirmation /  Date of  Date of Sanction  Amount  Date of  Date of  Remarks
No. /Contractor receipt of  Validation of the BG Amount  Submission  of the Amount by  Sanctione Signing of  Release of 
Application  by NHAI of Bank  NHAI d (Rs. in Escrow  Amount to 
in Format 'A'  Guarantee  crore) Account  the Escrow 
from the  by the  Agreement  Account
Contractor Contractor by the 
Contractor
1 2 3 4 5 6 7 8 9 10
1 Gujarat IRB Ahmedabad Vadodara Super Express  08.12.2016 15.12.2016 08.12.2016 15.12.2016 21.17 15.12.2016 19.12.2016 Consequent upon Judgement dated 
Tollway Private Limited /Six laning of  06.02.2017 of Hon'ble High Court of 
Ahmedabad to Vadodara section of NH 8  Delhi in favor of NHAI by set aside the 
from Km. 6.400 to Km. 108.700 (length  AT award dated 08.01.2016, 
102.300) in the State of Gujarat and  Concessionaire has deposited Rs. 21.80 
improvement of Ahmedabad Vadodara  Cr. through RTGS in Canara bank.
Expressway from Km. 0.000 to 93.302 in 
the State of Gujarat (Length – 93.302 Km.) 
under NHDP Phase V on Design Build 
Finance Operate Transfer (DBFOT) Toll 
basis
2 Goa IRB GOA Tollway Private Limited /Design,  08.12.2016 15.12.2016 08.12.2016 15.12.2016 248.50 15.12.2016 16.12.2016
Engineering, Finance, Construction, 
Operation and Maintenance of Four laning 
of Goa/Karnataka border to Panaji‐Goa 
Section of NH‐4A from Km. 84+000 to Km. 
153+070 in the State of Goa under NHDP 
Phase III on Build, Operate and Transfer 
(BOT) Toll basis

3 Assam IL&FS Engineering and Construction  13.12.2016 Letter No.NHAI/11015/AS‐ Awaited


Company Ltd /Widening and  19/17/2005/EW‐I/76 dated 
strengthening of existing NH‐37 from 2  20.12.2016 issued to 
lanes to 4 lanes Km.230.500 to  Contractor
Km.205.000 of Dharamtul to Jagiroad in 
Assam on East‐West Corridor under Phase‐
II Programme of NHDP (Package No. EW‐II, 
AS‐19)
4 Uttar  Oriental Structure Engineers Pvt Ltd. KMC  14.12.2016 Letter No. Arbitration/UP/ ABP‐ Awaited
Pradesh /Request from Oriental Structural  2&3/2010/ 92652 dated 
Engineers Pvt Ltd – KMC Constructions Ltd  20.12.2016 issued to 
(JV) Allahabad Bypass Project (Package  Contractor
ABP‐3) (Award date: 27.04.2012)

5 Uttar  Oriental Structure Engineers Pvt Ltd. KMC  14.12.2016 Letter No. Arbitration/UP/ABP‐ 23.08.2017 09.10.2017 29.30 08.09.2017 10.10.2017 Letter No. Arbitration /UP/ABP‐2&3/ 
Pradesh /Request from Oriental Structural  2&3/2010/92655 dated  2010/103820 dated 02/08/2017 issued 
Engineers Pvt Ltd – KMC Constructions Ltd  20.12.2016 issued to  to Contractor
(JV) Allahabad Bypass Project (Package  Contractor
ABP‐3), (Award date: 07.11.2011)

6 Uttar  Oriental Structure Engineers Pvt Ltd. KMC  14.12.2016 Letter No. Arbitration/UP/ABP‐ 14.07.2017


Pradesh /Request from Oriental Structural  2&3/2010/92648 dated 
Engineers Pvt Ltd – KMC Constructions Ltd  20.12.2016 issued to 
(JV) Allahabad Bypass Project (Package  Contractor
ABP‐3) (Award date: 04.03.2016)

7 Uttar  Oriental Structure Engineers Pvt Ltd. KMC  14.12.2016 Letter No.Arbitration/UP/ABP‐ Awaited


Pradesh /Request from Oriental Structural  2&3/2010/92649 dated 
Engineers Pvt Ltd – KMCConstructions Ltd  20.12.2016 issued to 
(JV) Allahabad Bypass Project (Package  Contractor
ABP‐3) (Award date: 25.04.2011)

8 Uttar  Oriental Structure Engineers Pvt Ltd.  14.12.2016 NHAI/12018/ADB‐IV/UP‐3/  Awaited


Pradesh /Request from Oriental Structural  2005/92681 dated 20.12.2016 
Engineers Pvt Ltd Construction of New  issued to Contractor
Four Lane Jhansi Bypass from km 90.300 
to km 106.175 of NH‐25 in the state of 
Uttar Pradesh Package EW‐II (UP‐3)

9 Uttar  Oriental Structure Engineers Pvt Ltd.  14.12.2016 NHAI/12018/ADB‐IV/UP‐3/  Awaited


Pradesh /Request from Oriental Structural  2005/92683 dated 20.12.2016 
Engineers Pvt Ltd Construction of New  issued to Contractor
Four Lane Jhansi Bypass from km 90.300 
to km 106.175 of NH‐25 in the state of 
Uttar Pradesh Package EW‐II (UP‐3)

10 Uttar  Oriental Structure Engineers Pvt Ltd.  14.12.2016 NHAI/12018/ADB‐IV/UP‐3/  Awaited


Pradesh /Request from Oriental Structural  2005/92684 dated 20.12.2016 
Engineers Pvt Ltd Construction of New  issued to Contractor
Four Lane Jhansi Bypass from km 90.300 
to km 106.175 of NH‐25 in the state of 
Uttar Pradesh Package EW‐II (UP‐3)

11 Madhya  Oriental Structure Engineers Pvt Ltd.  14.12.2016 Letter No. NHAI/BOT/11012/  Awaited


Pradesh /Request from Oriental Structural  NH‐25/MP‐UP‐1/2016/92678 
Engineers PvtLtd Rehabilitation and  dated 20.12.2016 issued to 
Upgrading of km 50.00 to km 90.300. of  Contractor
NH‐25 to 4/lane configuration in the state 
of Madhya Pradesh Package EW‐II/MP‐UP‐
I
12 Uttar  Oriental Structure Engineers Pvt Ltd.  14.12.2016 NHAI/12018/ADB‐IV/UP‐3/  Awaited
Pradesh /Request from Oriental Structural  2005/92682 dated 20.12.2016 
Engineers Pvt Ltd Four Laning of Mathura  issued to Contractor
Agra Section of NH‐2 from km 148.33 to 
km 177.00 in the State of UP (Contract 
Package‐1)
13 Jharkhand OSE Oriental Gammon (JV) /Four Laning  14.12.2016 Letter No. 11014/11/2001/  Awaited
and Strengthening of the Existing Two‐ DRB/GM(WB)/ 92636 dated. 
Lane Section between km 199.660 to km  20.12.2016 issued to 
250.500 on NH‐2 (Construction Package  Contractor
–IA ) Contract Agreement No. GTRP/1

14 BIhar OSE Oriental Gammon (JV) /Four Laning  14.12.2016 Letter No. 11016/7/2000/  Awaited


and Strengthening of NH‐2 from km 180 to  Tech/VA/JH/ 92688 dated 
km 240 in the State of Bihar ‐Contract  20.12.2016 issued to 
Package –VA (Contract No.TNHP‐07) Contractor

15 Jharkhand OSE Oriental Gammon (JV) /Four Laning  14.12.2016 Letter No.11014/11/2001/  Awaited


and Strengthening of the Existing Two‐ DRB/ GM(WB)/92641 dated 
Lane Section between km 199.660 to km  20.12.2016 issued to 
250.500 on NH‐2 (Construction Package  Concessioniare.
–IA ) Contract Agreement No. GTRP/1
16 Jharkhand OSE Oriental Gammon (JV) /Four Laning  14.12.2016 Letter No. 11014/11/2001  Awaited
and Strengthening of the Existing Two‐ /DRB/ GM(WB)/92645 dated 
Lane Section between km 199.660 to km  20.12.2016 issued to 
250.500 on NH‐2 (Construction Package  Concessionaire
–IA ) Contract Agreement No. GTRP/1

17 Jharkhand OSE Oriental Gammon (JV) /Four Laning  14.12.2016 Letter No. 11014/11/2001  Awaited


and Strengthening of the Existing Two‐ /DRB/ GM(WB)/92640 dated 
Lane Section between km 199.660 to km  20.12.2016 issued to 
250.500 on NH‐2 (Construction Package  Contractor
–IA ) Contract Agreement No. GTRP/1

18 Bihar SSANGYONG OSE Oriental (JV) /Four  14.12.2016 Letter No. NHAI/BH/DRB /IV‐ Awaited


Laning and Strengthening of NH‐2 from  D/PIU‐VNS/92680 dated 
km 140.00 to km 180.000 on NH‐2  20.12.2016 issued to 
–Construction Package–IVDin Bihar  Contractor
(Contract Agreement No.TNHP‐06)
19 Bihar SSANGYONG OSE Oriental (JV) /Four  14.12.2016 Letter No. NHAI/BH/ DRB/IV‐ Awaited
Laning and Strengtheningof NH‐2 from km  D/PIU‐VNS/92679 dated 
140.00 to km 180.000 on NH‐2  20.12.2016 issued to 
–Construction Package–IVD in Bihar  Conctractor
(Contract Agreement No.TNHP‐06)
20 Assam Gayatri –ECI (JV) /Widening and  14.12.2016 Letter No. NHAI/11015/As‐ Awaited
Strengthening of existing Two‐lane to Four  10/ARB/2015/ EW‐I/78 dated 
Lane from km 93.000 to km 60.000 (Bijni‐ 20.12.2016 issued to 
Assam/WB Border Section) on NH‐31‐C on  Contractor
East West Corridor in the State of Assam 
(Contract Package No.EW‐II (AS‐10)

21 Assam Gayatri –ECI (JV) /Four Laning of National  14.12.2016 Letter No.NHAI/11015 /AS‐ Awaited


Highway from Km.40.000 to Km 60.500 of  27/2007/EW‐I/77 dated 
Maibong to Lumding Section of NH‐54 in  20.12.2016 issued to 
Assam on East West Corridor under Phase‐ Contractor
II Programme of NHDP Contract Package 
EW‐II (AS‐27)

22 Assam Gayatri –ECI (JV) /Widening and  14.12.2016 Letter No. NHAI/11015/AS‐ Awaited


Strengthening of existing Two‐lane  10/ARB/2015/ EW‐I/79 dated 
carriageway from km 93.000 to km 60.000  20.12.2016 issued to 
(Bijni‐Assam/WB Border Section) on NH‐ Contractor
31‐C under East West Corridor in the State 
of Assam (Contract Package No.EW‐II (AS‐
10)
23 Tamilnadu AFCONS Infrastructure Limited (Shapoorji  14.12.2016 Letter No. NHAI/13012/4/98‐ 11.01.2017 16.01.2017 14.91 11.01.2017 17.01.2017
Palonji) /Widening of Four Lane and  PT /RC‐I/538 dated 19.12.2016 
Rehabilitation of Two Lane carriageway of  issued to Contractor
Poonamallee – Kancheepuram Section of 
NH‐4 (Km 13.8 to km 70.2 (Contract 
Package No.RC‐1)

24 Karnataka AFCONS Infrastructure Limited (Shapoorji  14.12.2016 Letter No NHAI/KNT/Afcon‐ 11.01.2017 16.01.2017 92.40 11.01.2017 17.01.2017


Palonji) /Four laning and Strengthening of  April/2005/92612 dated 
BG of Rs. 1,22,11,95,684 extended upto 
Km.340‐Km404 Haveri to Hubli Section of  19.12.2016 issued to  31.01.2019
NH‐4 in the State of Karnataka. concessionaire.

25 Karnataka AFCONS Infrastructure Limited (Shapoorji  14.12.2016 Letter No. NHAI/KNT/Afcon‐ 11.01.2017 16.01.2017 20.03 11.01.2017 17.01.2017


Palonji) /Six laning of Km. 527.000 to Km.  April/2015/92781 dated 
535.00 Km. 539.00 to KM. 556.00 of  22.12.2016 issued to  BG of Rs. 25,12,40,022 extended upto 
Hyderabad‐Bangalore section of Nh‐7 in  Contractor 31.01.2019
the State of Karnataka. ‐ Contract Package 
NS‐24/KN

26 Karnataka AFCONS Infrastructure Limited (Shapoorji  14.12.2016 Letter No. NHAI/KNT/Afcon‐ 11.01.2017 16.01.2017 3.09 11.01.2017 17.01.2017


Palonji) /Six laning of Km. 527.000 to Km.  April/2015/92783 dated 
535.00 Km. 539.00 to KM. 556.00 of  22.12.2016 issued to  BG of Rs. 3,88,03,865 extended upto 
Hyderabad‐Bangalore section of Nh‐7 in  Contractor 31.01.2019
the State of Karnataka. ‐ Contract Package 
NS‐24/KN

27 Karnataka AFCONS Infrastructure Limited (Shapoorji  14.12.2016 Letter No. NHAI/KNT/Afcon‐ 11.01.2017 16.01.2017 10.41 11.01.2017 17.01.2017


Palonji) /Six laning of Km. 527.000 to Km.  April/2015/92784 dated 
535.00 Km. 539.00 to KM. 556.00 of  22.12.2016 issued to  BG of Rs. 13,06,28,299 extended upto 
Hyderabad‐Bangalore section of Nh‐7 in  Contractor 31.01.2019
the State of Karnataka. ‐ Contract Package 
NS‐24/KN

28 Maharashtra JOG – SHIRKE (JV) /Four Laning of SH‐54  12.12.2016 Letter No.  BG in F/o  31.01.2017 24.79 19.01.2017 01.02.2017 BG Confirmation in the name of 
from 6.400 Km to 14.55 Km and  NHAI/Legal&Arbitration /  National  National Highways Authority of India on 
Construction of Four lane Major Bridge  Revival/2016/92689 dated  Highways  30.01.2017. Amended BG Confirmation 
across Panvel Creek (Belapur‐ 20.12.2016 issued to  Authority  in the name of Mumbai JNPT Port Road 
GawanPhata) in Maharashtra State  Contractor of India on  Company Limited on 09.03.2017
Package‐II. 19.01.2017 
& BG in F/o 
of Mumbai 
JNPT Port 
Road 
Company 
Limited on 
23.02.2017
29 West Bengal Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/12014/FQ  Case Closed Claim amount stands deposited with 
/Widening 4/6 Lanes and Strengthening of  /2003/ SC/Tech/CGM  the Supreme Court. Contractor not 
existing Two Lane Carriageway of NH‐6 in  /186/92685 dated 20.12.2016  eligible for 75% Payment against 
the State of West Bengal from Kolaghat to  issued to Contractor Arbitral Award. Letter No. 
Kharagpur (from km 72 to km 136)  NHAI/12014/FQ /2003/ SC/Tech/CGM 
Contract Package WB‐II) Claim No. 3,4&5. /186/105752 dated 12.09.2017 issued 
to Contractor
30 West Bengal Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/12014  Case Closed Claim amount stands deposited with 
/Widening 4/6 Lanes and Strengthening of  /FQ/2003/SC/  the Supreme Court. Contractor not 
existing Two Lane Carriageway of NH‐6 in  Tech/CGM/186/92675 dated  eligible for 75% Payment against 
the State of West Bengal from Kolaghat to  20.12.2016 issued to  Arbitral Award. Letter No. 
Kharagpur (from 72 km to km 136)  Contractor NHAI/12014/FQ /2003/ SC/Tech/CGM 
(Contract Package WB‐II) claim‐II /186/105755 dated 12.09.2017 issued 
to Contractor
31 West Bengal Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/12014/  Case Closed Proposal withdrawn by HCC vide Letter 
/Widening 4/6 Lanes and Strengthening of  FQ/2003/SC/  No. HCC/CONT/ARB/WBII/PA/288 
existing Two Lane Carriageway of NH‐6 in  Tech/CGM/186/92656 dated  dated 09.02.2017
the State of West Bengal from Kolaghat to  20.12.2016 issued to 
Kharagpur (from 72 km to km 136)  Concessioniare
(Contract Package WB‐II) Claim‐III
32 West Bengal Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/12014/  Case Closed NHAI PIU Kolkata relaesed the amount 
/Widening 4/6 Lanes and Strengthening of  FQ/2003/SC/  of Rs. 70,21,297/‐ on 13.02.2013. 
existing Two Lane Carriageway of NH‐6 in  Tech/CGM/186/92654 dated  Nothing is admissible to HCC against 
the State of West Bengal from Kolaghat to  20.12.2016 issued to  the AT award. Letter No. 
Kharagpur (from 72 km to km 136)  Contractor NHAI/12014/FQ /2003/SC/Tech/CGM 
(Contract Package WB‐II) Claim No. 2 /186/105750 issued to Contractor.

33 West Bengal Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/12014/  Case closed Claim amount stands deposited with 


/Widening 4/6 Lanes and Strengthening of  FQ/2003/SC/  the Supreme Court. Contractor not 
existing Two Lane Carriageway of NH‐6 in  Tech/CGM/186/92695 dated  eligible for 75% payment against 
the State of West Bengal from Kolaghat  20.12.2016 issued to  Arbitral Award.
toKaharagpur (from 72 km to km 136)  Contractor/Claim Rejected
(Contract Package WB‐II) Claim No.6

34 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/40020/2/‐III  20.11.2017 03.01.2018 206.54 22.12.2017 04.01.2018


Pradesh /Lucknow‐ Muzaffarpur National Highways  /Tech‐III/WB‐4/DRB/92660 
Projet‐4‐laning from Km 135.000 to Km  dated 20.12.2016 issued to 
64.700 of Ayodhya to Gorakhpur Section  Contractor
of NH‐28 in the Uttar Pradesh (Civil 
Construction package LMNHP‐EW‐II(WB)‐
4. Award dated:20.03.2015

35 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/40020/2/‐III/  17.03.2017 31.03.2017 87.79 23.03.2017 31.03.2017


Pradesh /Lucknow‐Muzaffarpur National Highways  Tech‐III/WB‐4/DRB/92662 
Projet‐4‐laning from Km 135.000 to Km  dated 20.12.2016 issued to 
64.700 of Ayodhya to Gorakhpur Section  Contractor
of NH‐28 in the Uttar Pradesh (Civil 
Construction package LMNHP‐EW‐II(WB)‐
4. Award dated:18.03.2016

36 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/40020/2/‐III/  24.02.2017 21.03.2017 50.22 14.03.2017 21.03.2017 Letter No. NHAI/40020/2/C‐III/ Tech‐
Pradesh /Lucknow‐Muzaffarpur National Highway  Tech‐III/WB‐4/DRB/92658  III/WB‐4/DRB/95581 dated 23.02.2017 
Project‐ 4 Laning from km 135+000 to km  dated 20.12.2016 issued to  issued to Contractor
164+000 of Ayodhya‐Gorakhpursection of  Contractor
NH‐28 in Uttar Pradesh, India Contract 
package : LMNHP‐EWII‐WB‐4 (Award Date 
30.05.2015)

37 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/Tech  29.03.2017 21.04.2017 13.09 29.03.2017 21.04.2017


Pradesh /Lucknow‐Muzaffarpur National Highway  /LMNHP/WB‐3/2016/92664 
Project‐ 4 Laning from km 92.000 to  dated 20.12.2016 issued to 
135.000 of Lucknow ‐ Ayodhya section of  Contractor
NH‐28 in Uttar Pradesh, India Contract 
package : LMNHP‐EWII‐WB‐3, (Award 
Date 22.07.2014)

38 Tamilnadu Hindustan Construction Company Ltd.  14.12.2016 Letter No NHAI/12011/4 /CBP‐ 20.02.2017 As per the decision  Letter No NHAI/12011/4 /CBP‐


/Construction of Chennai Bypass, Phase II,  II/2006/537 dated 19.12.2016  of Hon'ble High  II/2006/600 dated 23.02.2017 issued to 
connecting NH‐4 & NH‐5 and Widening‐ of  issued to Concessionaire Court, NHAI  Concessionaire
Chennai Bypass, Phase II, connecting NH‐ deposited AT 
45 & NH‐4 in Tamil Nadu Contract Package  amount including 
CBPII interest, 
amounting to Rs. 
6.73 crore with 
Registrar General, 
High Court, Delhi.

39 Tamilnadu Hindustan Construction Company Ltd.  14.12.2016 Letter No. NHAI/12011/4/ CBP‐ Awaited


/Construction of Chennai Bypass, Phase II,  II/2006/539 dated 19.12.2016 
connecting NH‐4 & NH‐5 and Widening‐ of  issued to Contractor
Chennai Bypass,Phase II, connecting NH‐
45 & NH‐4 in Tamil Nadu Contract Package 
CBPII
40 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No. Arbitration /UP/ABP‐ 02.05.2017 24.05.2017 137.01 02.05.2017 24.05.2017
Pradesh /Allahabad bypass ‐ Construction of Road  2&3/2010/92674 dated 
from Km 158 to Km 198 (except Ganga  20.12.2016 issued to 
Bridge) Contract Package ‐ ABP2 Contractor
41 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No. Arbitration/UP/ABP‐ Case closed Delhi High Court decided in favour of 
Pradesh /Allahabad bypass ‐ Construction of Road  2&3/2010/92673 dated  NHAI. Contractor not eligible for 75% 
from Km 158 to Km 198 (except Ganga  20.12.2016 issued to  payment against Arbitral Award.
Bridge) Contract Package ‐ ABP2 Contractor /Claim Rejected

42 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No.  20.02.2017 09.03.2017 10.38 01.03.2017 16.03.2017 Letter No. NHAI/Tech/LMNHP/WB‐
Pradesh /Lucknow‐Muzaffarpur National Highway  NHAI/Tech/LMNHP/WB‐ 1/2016/95580 dated 23.02.2017 issued 
Project‐ 4 Laning from km 9+000 to km  1/2016/92665 dated  to Contractor
45+000 of Lucknow‐Ayodhya section of  20.12.2016 issued to 
NH‐28 in Uttar Pradesh, India Contract  Contractor
package :LMNHP‐EWII‐WB‐1 (Award Date 
28.05.2014)

43 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No.  30.03.2017 21.04.2017 32.49 30.03.2017 21.04.2017


Pradesh /Lucknow‐Muzaffarpur National Highway  NHAI/Tech/LMNHP/WB‐
Project‐ 4 Laning from km 45+000 to km  2/2016/92666 dated 
92+000 of Lucknow‐Ayodhya section of  20.12.2016 issued to 
NH‐28 in Uttar Pradesh, India Contract  Contractor
package : LMNHP‐EWII‐WB‐2 (Award Date 
13.06.2015)

44 Rajasthan Hindustan Construction Company Ltd.  14.12.2016 Letter No NHAI /12018/ADB‐ Awaited The matter belongs to Dispute NO. 04 


/Rehabilitation and Upgrading of Km  IV/RJ‐07/2005/386 dated  and is pending before Hon'ble High 
253.00 to Km 316.00 of NH‐76 to 4‐Iane  19.12.2016 issued to  Court, New Delhi and Hon'ble Supreme 
configuration, in the state of Rajasthan  Concessionaire Court of India, New Delhi.
ContractPackage EW‐II‐RJ‐7 The Decretral amount of Rs. 74.53 Cr. 
has been deposited by this office after 
obtaining the approval of Competent 
Authority of NHAI, with The Registrar 
General, Hon'ble High Court New delhi 
in compliance to order dated 
24 10 2017
45 Rajasthan Hindustan Construction Company Ltd.  14.12.2016 Letter No NHAI/12018/ADB‐ Case closed Delhi High Court decided in favour of 
/Rehabilitation and Upgrading of Km  IV/RJ‐07/2005/385 dated  NHAI. Contractor not eligible for 75% 
253.00 to Km 316.00 of NH‐76 to 4‐Iane  19.12.2016 /Claim rejected payment against Arbitral Award.
configuration, in the state of Rajasthan 
Contract Package EW‐II‐RJ‐7
46 Uttar  Hindustan Construction Company Ltd.  14.12.2016 Letter No.  29.03.2017 12.04.2017 114.10 29.03.2017 12.04.2017
Pradesh /Lucknow Muzaffarpur National Highway  NHAI/Tech/LMNHP/WB‐
Project‐ 4 Laning from km 92.000 to Km  3/2016/92667 dated 
135.000 of Lucknow ‐ Ayodhya Section of  20.12.2016 issued to 
NH‐28 in Uttar Pradesh, India, Contract  Contractor
package : LMNHP‐EWII‐WB‐3, (Award 
Date 30.11.2015)

47 Madhya  Backborne Projects Ltd. /Four Laning km  14.12.2016 Revised Letter No.  Awaited Letter No. NHAI/30030 /6/NS‐21/ 2001‐


Pradesh 85 to km 103 Section of NH‐3 Agra Gwalior  NHAI/30030/6/NS‐21/2001‐ Tech/ 92630 dated 20.12.2016 issued to 
Section in the State of Madhya Pradesh –  Tech/93070 dated 28.12.2016  Contractor
Contract Package No.NS‐21/MP issued to Contractor

48 Tamilnadu DS Toll Road Ltd. /Design Construction  14.12.2016 Letter No NHAI/Tech/NS‐ Awaited


Development finance Operation and  2/TN/Conc/2005/1265 dated 
Maintenance of km 373.275 (Start of  19.12.2016 issued to 
proposedflyover atDindigul Bypass) to km  Concessionaire.
426.6 (Samayanallore) on NH‐7 in the 
State of Tamil Nadu on BOT basis.
49 Tamilnadu NK Toll Road Ltd. /Design, Construction,  16.12.2016 Letter No. NHAI/Tech/NS‐ Awaited
Development, Finance, operation and  2/BOT/TN‐3/Conc./2005/982 
Maintenance of Km. 258/645 (of  dated 19.12.2016 issued to 
Namakkal Bypass) to Km. 292/6 (start of  Contractor
Karur Bypass) and (ii) Improvement, 
Operation and maintenance of Km. 
248/645 (start of proposed flyover on 
Namakkal bypass) to Km. 258/645 (end of 
Namakkal bypass) on Nh‐7 in the State of 
Tamil Nadu on BOT basis Contract Package 
NS‐2/BOT/TN‐3
50 Uttar  Sunway Construction SDN BHD ‐ 19.12.2016 Letter No.  Awaited
Pradesh Rehabilitation and Upgrading of km  NHAI/DGM(T)/sunway/UP‐
104.00 to km 170.00 of NH‐25 to 4/lane  4/2016/92906 dated 
configuration in the State of Uttar Pradesh  26.12.2016 issued to 
Package No.EW‐II(UP‐4) Contractor
51 Madhya  BSCPL Infrastructure Ltd.‐Construction of  23.12.2016 Letter No.  09.04.2017 03.05.2017 49.40 19.04.2017 08.05.2017
Pradesh four laning of Jhansi‐Lakhnadon Section  NHAI/Tech/MP/AT/C‐
from km 255 to km 297 (Upto end of  7/2015/93148 & letter No. 
Grade‐separator at RajmargChauraha) on  NHAI/Tech/MP/AT/C‐
NH‐26 in the state of Madhya Pradesh  7/2015/93149 dated 
Package‐ADB‐II/C‐7 – Payment due as per  29.12.2016 issued to 
Arbitral Awards dated 23/03/2010 &  Contractor
13/05/2015

52 Uttar  Hindustan Construction Company Ltd.  27.12.2016 Letter No. NHAI/Tech/LMNHP  04.04.2017 21.04.2017 72.17 04.04.2017 21.04.2017


Pradesh /Lucknow‐Muzaffarpur National Highway  /WB‐2/2016/93486 dated 
Project‐ 4 Laning from km92.000 to  06.01.2017 issued to 
135.000 of Lucknow‐Ayodhya section of  Contractor
NH‐28 in Uttar Pradesh Contract Package: 
LMNHP‐EWII‐WB‐3, (Award Date 
14 10 2016)
53 Andhra  Unitech–NCC (JV) /Widening to 4/6 lanes  27.12.2016 Letter No.  13.03.2017 03.07.2017 21.47 04.07.2017 05.07.2017 Letter No. NHAI/2013 /16/2000/Tech/ 
Pradesh and Upgrading of the existing 2‐lane road  NHAI/2013/16/2000/Tech/CG GM(E‐1)/299 dated 12.04.2017 issued 
including minor bridges (upto 30M),  M(E‐1)/95 dated 02.01.2017  to Contractor
Service Roads and Auxiliary works in the  issued to Contractor
state of Andhra Pradesh between km.2.8 
(Visakhapatnam) Km .0) to Ichapuram 
(Km.233) Section of NH‐5 Contract 
Package AP‐3
54 Andhra  Navyuga Engineering Co. Ltd. /Widening  27.12.2016 Letter No. NHAI/Tech/AP‐ Case Closed High Court gave order on 16.12.2016 in 
Pradesh to 4/6 lane and Upgrading the existing 2‐ 6/Icha‐Sri/Bridge  favour of Contractor. Order was not 
lane road (Bridges over 30m Flyover and  Package/93219 dated  challenged and payment was settled 
Road over bridges) in the state of Andhra  02.01.2017 issued to  vide Supplementary Agreement dt. 
Pradesh between Km.98 (Srikakulam) to  Contractor 02.02.2017.
Km.233 (Ichhapuram) of Vishakapatnam 
to Ichhapuram section of NH‐5 (Contract 
Package AP‐6)

55 Bihar Gammon India Ltd. /Widening and  16.01.2017 Letter No. NHAI/EW‐1/2/BR‐03  04.08.2017 31.08.2017


Strengthening Two‐4‐lane existing  /DRB/Arbitration/2014 /94034 
single/intermediate Carriageway of NH‐57  dated 18.01.2017 issued to 
section from km. 190.00 to km 230.00  Contractor
(Forebisganj‐Simarhi Section) in the State 
of Bihar on East West Corridor under 
NHDP Phase‐II (Contract Package C‐II/BR‐
3), (Awarded Date: 31.03.2016 & 
Amended by AT on 17.05.2016)

56 Odisha Gammon India Ltd. /Widening to 4/6 lanes  01.03.2017 Letter No.  20.12.2017 01.01.2018 53.49 22.12.2017 03.01.2018 Letter 
and Strength4ening of existing 2‐lane  NHAI/12013/6/2005/Tech/CK‐ No.NHAI/11011/19/RO/Od/1118/2017/
carriageway (Bridge, Flyovers & ROB) of  II/314 dated 19.01.2017 issued  100168 dated 22.05.2017 issued to 
NH‐5 in the State of Orissa from km.  to contractor Contractor
61.000 to km. 199.141 (Chandikole to 
Blaeswar) Contract Package No. OR‐V

57 Karnataka Supreme‐ MBL (JV) /Western Transport  15.02.2017 Letter No. NHAI/GM(MC‐ Awaited


Corridor, Tumbkur‐ Haveri‐NH 4 project ‐  III)/Supreme/Essentiality/9535
Rehabilitation and upgradation of  2 dated 20.02.2017 issued to 
Chitradurg Section [ km 189.00 to km  contractor
207.00] ‐ Balance Works [Contract 
package No. WTC‐ PKG3/NH/Re‐Bid]
58 Tamilnadu Agrawal ‐ JMC Joint Venture/Four laning  02.03.2017 Letter No.11015/7/2001/  27.11.2017 26.12.2017 8.25 12.12.2017 17.01.2018
and Strengthening of Existing Two lane  Tech/GM (WB‐II)/1059 dated 
National Highway No. NH 45B from Trichy  06.03.2017 issued to 
Bypass end to Tovarankurchi (Km. 0+000  Contractor
to KM. 60.950) in Tamil Nadu (Contract 
Package No. VII‐A) (Award Date 
29.03.2010)

59 Tamilnadu Agrawal ‐ JMC Joint Venture/Four laning  02.03.2017 Letter No.11015/7/2001/  22.01.2018


and Strengthening of Existing Two lane  Tech/GM (WB‐II)/1058 dated 
National Highway No. NH 45B from Trichy  06.03.2017 issued to 
Bypass end to Tovarankurchi (Km. 0+000  Contractor
to KM. 60.950) in Tamil Nadu (Contract 
Package No. VII‐A) (Award Date 
30.04.2014)
60 Tamilnadu Agrawal ‐ JMC Joint Venture/Four laning  02.03.2017 Letter No.11015/7/2001/  23.01.2018
and Strengthening of Existing Two lane  Tech/GM (WB‐II)/1057 dated 
National Highway No. NH 45B from   06.03.2017 issued to 
Tovarankurchi  to Madurai (Km. 60.950 to  Contractor
124.840) in Tamil Nadu (Contract Package 
No. VII‐B) (Award Date 29.03.2010)

61 Tamilnadu Agrawal ‐ JMC Joint Venture/Four laning  02.03.2017 Letter No.11015/7/2001/  22.01.2018


and Strengthening of Existing Two lane  Tech/GM (WB‐II)/1056 dated 
National Highway No. NH 45B from   06.03.2017 issued to 
Tovarankurchi  to Madurai (Km. 60.950 to  Contractor
124.840) in Tamil Nadu (Contract Package 
No. VII‐B) (Award Date 30.04.2014)

62 Maharashtra M/s Atlanta Infra Assets  08.03.2017 Letter No. NHAI/BOT/ 11023/  27.03.2017 08.04.2017 117.88 07.04.2017 11.04.2017


Limited/Improvement, Operation &  20 /2008(pt) /96623 dated 
maintenance including Strengthening &  15.03.2017 issued to 
Widening of existing 2‐lane road to 4 lane  Contractor
dual carriageway from Km. 9.200 to Km. 
50.00 section of NH‐6 (Nagpur ‐ Kondhali 
Section) in the state of Maharashtra on 
Build, Operate & Transfer (BOT) basis

63 Andhra  M/s Limak‐SOMA (JV) / Contract Package ‐  22.03.2017 Letter No.  19.05.2017 REMINDER: Letter No. 


Pradesh AP‐18 ‐ widening ot 4/6 lanes &  NHAI/Tech/Gundu/CTE/2012/ NHAI/Tech/Gundu /CTE/2012 /456 
strengthening of existing 2 lane  342 dated 28/04/2017 issued  dated 10.07.2017 issued to Contractor, 
carriageway of NH‐5 in Vijayawada‐ to Contractor Reminder‐II dated 09.08.2017 also 
Visakhapatnam section in the state of  issued to Contractor. Arbital Award not 
Andhra Pradesh form km. 80.000 to km.  released. However, in compliance to 
164.500 (Gundugolanu near Eluru to  Hon'ble order dated 06.11.2017, full 
Gowthami bridge) Date of Award:  amount of award for for Rs. 
01.03.2008. 13,81,94,490/‐ includinmg interest 
@10% compounded monthly upto 
15.12.2017 has been deposited in the 
Court
64 Andhra  M/s Nirmal BOT Limited (Highway  01.05.2017 Letter No. NHAI /Tech /NS‐2  Case closed Since, the award is not in favour of the 
Pradesh Concessions) / Design, Construction,  /BOT /AP‐8/ 1/2008 /100460  Concessionaire (M/s Nirmal BOT 
Development, Finance, Operation and  dated 26.05.2017 issued to  Limited), therefore, payment of 75% of 
Maintenance of Km. 278.000 (Kadtal) to  Contractor. Arbitral Award cannot be released by 
308.000 (Armur) on NH‐7 in the State of  NHAI to the Concessionaire. Also, in any 
Andhra Pradesh under North ‐ South  case, the payment cannot be released 
Corridor (NHDP Phase‐II) on Build,  to any EPC Contractor of the 
Operate and Transfer (Annuity) Basis ‐  Concessionaire.
Arbitration Award dated 14 09 2016
65 Uttar  M/s HCC / Lucknow‐Muzaffarpur National  17.07.2017 Letter No. NHAI/CM/TP/Lko‐
Pradesh Highway Project ‐ 4 laning from km. 9+000  Ayodhya/km107/ NH‐
to Km. 45+000 of Lucknow‐Ayodhya  28/Arbitral Award/2011/Part/ 
section of NH‐28 in Uttar Pradesh, India,  103948 dated 04.08.2017 
Contract Package : LMNHP‐EWII‐WB‐1 ‐  issued to Contractor
Arbitration Award dated 31.03.2017.

66 Odisha M/s HCC Ltd‐Release of 75% of Arbitral  06.12.2016 BG in F/o  14.07.2017 43.34 07.02.2017 17.07.2017 BG Confirmation in the name of 


Award amount as per decision of  National  National Highways Authority of India on 
Government of India. Development of  Highways  07.04.2017 and 06.03.2017 by Export 
Adequate Road Connectivity to Paradip  Authority  Import Bank of India, Barakhamba 
Port (Four laning of Chandikhole‐ of India on  Road, New Delhi. Amended BG 
Paradip,Km.0.00 to Km 77.00 section of  11.01.2017  Confirmation in the name of Paradip 
NH‐5A) in Orrisa. & Amended  Port Road Company Limited on 
BG in F/o  09.06.2017 & 23.06.2017 by Export 
Paradip  Import Bank of India, Barakhamba 
Port Road  Road, New Delhi. Amended BG 
Company  Confirmation in the name of PPRCL on 
Limited on  23.06.2017 by Export Import Bank of 
02.05.2017 India, Mumbai, Head Office.
TOTAL 1482.22