NH- 111 (New NH-130) from Km 163.400 to Km. 215.800 (Shivnagar 1. Name of Contract to Ambikapur) to two lane with paved shoulder under NHDP-IV through Engineering Procurement & Construction (EPC) basis contract. 2. Place & State Chhattisgarh 3. Contract No. & Date K 502684/ Dated 12.04.2017 The Chief Engineer Name and Address of 4. National Highway Zone, Employer PWD, Pensionbada, Raipur (CG) Value of Contract (Rs. 5. Rs 223.89 Crore Crores) Value of work executed till 6. Rs. 169.42 Crore 22nd June, 2020 Value of Works remaining to 7. Rs. 62.88 Crore be completed (Rs. Crores) 8 Date of Commencement 12.06.2017 Stipulated Date of 9. 11.06.2019 (EOT Upto 31.08.2020) Completion Anticipated Date of 10. 28.02.2019 Completion