ID Task Task Name Duration Start Finish Predecessors Successors Quarter 3rd Quarter 4th Quarter 1st Quarter

essors Successors Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarte
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
135 Roof Slab,Beam  1 day Sat 17‐08‐19 Sat 17‐08‐19 134FS+1 day 136FS+14 
Concrete days,138
136 Deshuttering 3 days Wed 04‐09‐19 Fri 06‐09‐19 135FS+14 day344FS+1 day
137 Third Floor 36 days Sat 23‐05‐20 Fri 03‐07‐20
138 Column starter  5 days Sat 23‐05‐20 Thu 28‐05‐20 135 139SS
concrete
139 Column Reinforcement 7 days Sat 23‐05‐20 Sat 30‐05‐20 138SS 140FF+2 days
140 Column Shuttering 7 days Tue 26‐05‐20 Tue 02‐06‐20 139FF+2 days141FF+2 days
141 Column Concrete 7 days Thu 28‐05‐20 Thu 04‐06‐20 140FF+2 days142FF+3 days
142 Roof Slab,Beam  7 days Mon 01‐06‐20 Mon 08‐06‐20 141FF+3  143FF+3 days
formwork & shuttering days
143 Roof Slab,Beam  7 days Thu 04‐06‐20 Thu 11‐06‐20 142FF+3  144FS+1 day
reinforcement days
144 Roof Slab,Beam  1 day Sat 13‐06‐20 Sat 13‐06‐20 143FS+1 day 145FS+14 
Concrete days,147
145 Deshuttering 3 days Wed 01‐07‐20 Fri 03‐07‐20 144FS+14 day364FS+1 day
146 Fourth Floor 36 days Mon 15‐06‐20 Sat 25‐07‐20
147 Column starter concrete5 days Mon 15‐06‐20 Fri 19‐06‐20 144 148SS
148 Column Reinforcement 7 days Mon 15‐06‐20 Mon 22‐06‐20 147SS 149FF+2 days
149 Column Shuttering 7 days Wed 17‐06‐20 Wed 24‐06‐20 148FF+2 days150FF+2 days
150 Column Concrete 7 days Fri 19‐06‐20 Fri 26‐06‐20 149FF+2 days151FF+3 days
151 Roof Slab,Beam  7 days Tue 23‐06‐20 Tue 30‐06‐20 150FF+3  152FF+3 days
formwork & shuttering days

152 Roof Slab,Beam  7 days Fri 26‐06‐20 Fri 03‐07‐20 151FF+3  153FS+1 day


reinforcement days
153 Roof Slab,Beam  1 day Mon 06‐07‐20 Mon 06‐07‐20 152FS+1 day 154FS+14 
Concrete days,156
154 Deshuttering 3 days Thu 23‐07‐20 Sat 25‐07‐20 153FS+14 day384FS+1 day
155 Fifth Floor 36 days Tue 07‐07‐20 Mon 17‐08‐20
156 Column starter  5 days Tue 07‐07‐20 Sat 11‐07‐20 153 157SS
concrete
157 Column Reinforcement 7 days Tue 07‐07‐20 Tue 14‐07‐20 156SS 158FF+2 days
158 Column Shuttering 7 days Thu 09‐07‐20 Thu 16‐07‐20 157FF+2 days159FF+2 days
159 Column Concrete 7 days Sat 11‐07‐20 Sat 18‐07‐20 158FF+2 days160FF+3 days
160 Roof Slab,Beam  7 days Wed 15‐07‐20 Wed 22‐07‐20 159FF+3  161FF+3 days
formwork & shuttering days
161 Roof Slab,Beam  7 days Sat 18‐07‐20 Sat 25‐07‐20 160FF+3  162FS+1 day
reinforcement days
162 Roof Slab,Beam  1 day Tue 28‐07‐20 Tue 28‐07‐20 161FS+1 day 163FS+14 
Concrete days,165
163 Deshuttering 3 days Fri 14‐08‐20 Mon 17‐08‐20 162FS+14 day404FS+1 day
164 Sixth Floor 36 days Wed 29‐07‐20 Tue 08‐09‐20
165 Column starter  5 days Wed 29‐07‐20 Mon 03‐08‐20 162 166SS
concrete
166 Column Reinforcement 7 days Wed 29‐07‐20 Wed 05‐08‐20 165SS 167FF+2 days
167 Column Shuttering 7 days Fri 31‐07‐20 Fri 07‐08‐20 166FF+2 days168FF+2 days
168 Column Concrete 7 days Mon 03‐08‐20 Mon 10‐08‐20 167FF+2 days169FF+3 days
169 Roof Slab,Beam  7 days Thu 06‐08‐20 Thu 13‐08‐20 168FF+3  170FF+3 days
formwork & shuttering days
170 Roof Slab,Beam  7 days Mon 10‐08‐20 Mon 17‐08‐20 169FF+3  171FS+1 day
reinforcement days
171 Roof Slab,Beam  1 day Wed 19‐08‐20 Wed 19‐08‐20 170FS+1 day 172FS+14 
Concrete days,174
172 Deshuttering 3 days Sat 05‐09‐20 Tue 08‐09‐20 171FS+14 day424FS+1 day
173 Seventh Floor 36 days Thu 20‐08‐20 Wed 30‐09‐20
174 Column starter  5 days Thu 20‐08‐20 Tue 25‐08‐20 171 175SS
concrete
175 Column Reinforcement 7 days Thu 20‐08‐20 Thu 27‐08‐20 174SS 176FF+2 days
176 Column Shuttering 7 days Sat 22‐08‐20 Sat 29‐08‐20 175FF+2 days177FF+2 days
177 Column Concrete 7 days Tue 25‐08‐20 Tue 01‐09‐20 176FF+2 days178FF+3 days
178 Roof Slab,Beam  7 days Fri 28‐08‐20 Fri 04‐09‐20 177FF+3  179FF+3 days
formwork & shuttering days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: COMMERCIAL BUILDIN
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Thu 21-06-18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

Page 4