essors Successors Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarte
Mode May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
135 Roof Slab,Beam 1 day Sat 17‐08‐19 Sat 17‐08‐19 134FS+1 day 136FS+14
Concrete days,138
136 Deshuttering 3 days Wed 04‐09‐19 Fri 06‐09‐19 135FS+14 day344FS+1 day
137 Third Floor 36 days Sat 23‐05‐20 Fri 03‐07‐20
138 Column starter 5 days Sat 23‐05‐20 Thu 28‐05‐20 135 139SS
concrete
139 Column Reinforcement 7 days Sat 23‐05‐20 Sat 30‐05‐20 138SS 140FF+2 days
140 Column Shuttering 7 days Tue 26‐05‐20 Tue 02‐06‐20 139FF+2 days141FF+2 days
141 Column Concrete 7 days Thu 28‐05‐20 Thu 04‐06‐20 140FF+2 days142FF+3 days
142 Roof Slab,Beam 7 days Mon 01‐06‐20 Mon 08‐06‐20 141FF+3 143FF+3 days
formwork & shuttering days
143 Roof Slab,Beam 7 days Thu 04‐06‐20 Thu 11‐06‐20 142FF+3 144FS+1 day
reinforcement days
144 Roof Slab,Beam 1 day Sat 13‐06‐20 Sat 13‐06‐20 143FS+1 day 145FS+14
Concrete days,147
145 Deshuttering 3 days Wed 01‐07‐20 Fri 03‐07‐20 144FS+14 day364FS+1 day
146 Fourth Floor 36 days Mon 15‐06‐20 Sat 25‐07‐20
147 Column starter concrete5 days Mon 15‐06‐20 Fri 19‐06‐20 144 148SS
148 Column Reinforcement 7 days Mon 15‐06‐20 Mon 22‐06‐20 147SS 149FF+2 days
149 Column Shuttering 7 days Wed 17‐06‐20 Wed 24‐06‐20 148FF+2 days150FF+2 days
150 Column Concrete 7 days Fri 19‐06‐20 Fri 26‐06‐20 149FF+2 days151FF+3 days
151 Roof Slab,Beam 7 days Tue 23‐06‐20 Tue 30‐06‐20 150FF+3 152FF+3 days
formwork & shuttering days
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: COMMERCIAL BUILDIN
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Thu 21-06-18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress