ID Task Task Name DurationStart Finish Predecessors Resource Jan 27, '18 Feb 3, '18

Mode Names M T S W S
1 SUBSTRUCTURE CONSTRUCTION WORK 49 Thu 2/1/18 Tue 3/20/18 excavators
SCHEDULE days
2 sub-structure work 48.43 days
Thu 2/1/18 Tue 3/20/18
3 Demolish of existing MASJID 15 daysThu 2/1/18 Thu 2/15/18

4 Site clearance 4 days Thu 2/15/18Mon 2/19/18 3

5 Layout and profile setting out 1 day Mon 2/19/18Tue 2/20/18 4

6 Excavation of footing and trench 7 days Tue 2/20/18Tue 2/27/18 5

7 Lean concrete of footing 2 days Tue 2/27/18Thu 3/1/18 6

8 Bar preparation, cutting, 20 Thu 3/1/18 Tue 3/20/18 7 bar benders


bending,Formwork preparation and days
placement
9 Footing pads preparation 2 days Thu 3/1/18 Sat 3/3/18

10 Concrete pouring process with 2 days Sat 3/3/18 Mon 3/5/18 9


respective concrete grade and
mechanism(footing
11 Construction of rubble masonry 1 day? Mon 3/5/18 Tue 3/6/18 01

12 Backfilling with selected materials as 7 days Tue 3/6/18 Mon 3/12/18 11


per the requirement

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Task Name DurationStart Finish Predecessors Resource Jan 27, '18 Feb 3, '18
Mode Names M T S W S
13 Compaction as per the design 2 days Tue 3/13/18Wed 3/14/18 21 ciid

14 Backfilling with selected hardcore as 0 days Wed Sun 3/4/18 31


per design 3/14/18
15 GROUND FLOOR WORK SCHEDUAL 78.57 days
Sat 3/24/18 Sat 6/9/18
16 GROUND FLOOR COLUMN CONSTRUCTION 17 daysSat 3/17/18 Mon 4/2/18
21 Formwork preparation and placement for 15 daysMon 4/2/18Mon 4/16/18

22 Beams and slab 10 daysMon 4/2/18 Thu 4/12/18 02

23 Main staircase 5 days Thu 4/12/18Tue 4/17/18 22

24 Bar preparation, cutting, bending and 18.43 Mon Thu 5/3/18


placement for days 4/16/18
25 Beams and slab 7 days Tue 4/17/18Tue 4/24/18 32

26 Main staircase 3 days Tue 4/24/18Thu 4/26/18 52

27 electrical pipes preparation work 3 days Thu 4/26/18Mon 4/30/18 62


28 Check day for the project supervisors 1 day? Mon 4/30/18Mon 4/30/18 72
29 Concrete pouring process with respective 1 day Tue 5/1/18 Tue 5/1/18 82
concrete grade and mechanism

30 curing 28 daysTue 5/1/18 Tue 5/29/18 92

31 FIRST FLOOR WORK SCHEDULE 48 daysMon 5/28/18


Sat 7/14/18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
ID Task Task Name DurationStart Finish Predecessors Resource Jan 27, '18 Feb 3, '18
Mode Names M T S W S
32 FIRST FLOOR COLUMN CONSTRUCTION 17 Mon Wed 6/13/18
days 5/28/18
33 Bar preparation, cutting, bending and 5 days Tue Sun 6/3/18 03
placement for 5/29/18
34 Formwork preparation and placement 7 days Sun 6/3/18 Sun 6/10/18 33
for
35 Check day for the project supervisors 1 day? Sun 6/10/18Mon 6/11/18 43
36 Concrete pouring process with 2 days Mon Tue 6/12/18 53
respective concrete grade and 6/11/18
mechanism
37 Formwork preparation and placement for 15 Sat 6/9/18 Sat 6/23/18
days
38 Beams and slab 10 daysWed 6/13/18Sat 6/23/18 63

39 Main staircase 5 days Sat 6/23/18 Wed 6/27/18 83

40 Bar preparation, cutting, bending and 10 Fri 6/29/18 Sun 7/8/18


placement for days
41 Beams and slab 7 days Sat 6/30/18 Thu 7/5/18 93

42 Main staircase 3 days Thu 7/5/18 Mon 7/9/18 14

43 Electrical pipes preparation work 2 days Mon 7/9/18 Tue 7/10/18 24


44 Check day for the project supervisors 1 day? Wed 7/11/18Wed 7/11/18 34
45 Concrete pouring process with respective 1 day? Wed Thu 7/12/18 44
concrete grade and mechanism 7/11/18

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
ID Task Task Name DurationStart Finish Predecessors Resource Jan 27, '18 Feb 3, '18
Mode Names M T S W S
46 Curing or giving water for all fresh 28 Thu Thu 8/9/18 54
concrete structures up to 28 days days 7/12/18
47 SECOND FLOOR WORK SCHEDULE 264.29Sat
days
8/4/18 Sat 4/20/19
64 FINISHING 148 days
Tue 8/7/18 Sun 12/30/18
65 Block work construction 20 daysThu 8/9/18 Tue 8/28/18 64

66 plastering for all walls 30 daysWed 8/29/18Thu 9/27/18 56

67 Ceramic floor finish with skirting for all 15 Thu Thu 10/11/18 66
the floors as per the design days 9/27/18
68 Sanitary& water discharge pipes 3 days Thu 10/11/18
Mon 10/15/18 76

69 Two, coats of white washing distember 15 Mon Mon 10/29/18 86


and painting for all the floors days 10/15/18
70 Window-door installation for all the floors 5 days Mon Sun 11/4/18 96
10/29/18
71 Finish electrical fittings installation for all 21 Sun Sat 11/24/18 07
the floors days 11/4/18
72 Microphone and load speakers installation 2 days Sat Mon 11/26/18 17
11/24/18
73 Staircase - marble and hand rail 20 Mon Sun 12/16/18 27
installation days 11/26/18
74 Final finishing paint (the third coat) 7 days Sun 12/16/18Sun 12/23/18 37

75 SITE WORK AND LANDSCAPING 121.43Sat


days12/22/18Thu 4/18/19
76 Site layout with the level difference as per 5 days Sun Thu 12/27/18 47
the design 12/23/18
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 4
ID Task Task Name DurationStart Finish Predecessors Resource Jan 27, '18 Feb 3, '18
Mode Names M T S W S
77 Site fence wall construction and site door 2 days Thu Sat 12/29/18 67
installation and finishing 12/27/18
78 Installation of sewage pipes 2 days Sun 12/30/18Mon 12/31/18 77

79 Building of ablution places 1 day Mon 12/31/18


Tue 1/1/19 87

80 Excavation of septic tank and building 3 5 days Tue 1/1/19 Sun 1/6/19 97
toilets
81 Two service rooms 5 days Sun 1/6/19 Thu 1/10/19 08

82 Building of MINNARAD 90 daysSat 1/12/19 Tue 4/9/19 18

83 The overall check time for the project 1 day Tue 4/9/19 Wed 4/10/19 28
supervisors
84 Correction work time 1 day Wed 4/10/19Thu 4/11/19 38

85 Final check time for supervisors 1 day Thu 4/11/19Sat 4/13/19 48

86 Project handover for the client 1 day Sat 4/13/19 Sat 4/13/19 58

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 5
Feb 10, '18 Feb 17, '18 Feb 24, '18 Mar 3, '18 Mar 10, '18 Mar 17, '18 Mar 24, '18 Mar 31, '18 Apr 7, '18
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 6
Feb 10, '18 Feb 17, '18 Feb 24, '18 Mar 3, '18 Mar 10, '18 Mar 17, '18 Mar 24, '18 Mar 31, '18 Apr 7, '18
S T F M T S W S T F M T S W S T F M T S
ciid

3/4

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 7
Feb 10, '18 Feb 17, '18 Feb 24, '18 Mar 3, '18 Mar 10, '18 Mar 17, '18 Mar 24, '18 Mar 31, '18 Apr 7, '18
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 8
Feb 10, '18 Feb 17, '18 Feb 24, '18 Mar 3, '18 Mar 10, '18 Mar 17, '18 Mar 24, '18 Mar 31, '18 Apr 7, '18
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 9
Feb 10, '18 Feb 17, '18 Feb 24, '18 Mar 3, '18 Mar 10, '18 Mar 17, '18 Mar 24, '18 Mar 31, '18 Apr 7, '18
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 10
Apr 7, '18 Apr 14, '18 Apr 21, '18 Apr 28, '18 May 5, '18 May 12, '18 May 19, '18 May 26, '18 Jun 2, '18
S W S T F M T S W S T F M T S W S T F M

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 11
Apr 7, '18 Apr 14, '18 Apr 21, '18 Apr 28, '18 May 5, '18 May 12, '18 May 19, '18 May 26, '18 Jun 2, '18
S W S T F M T S W S T F M T S W S T F M

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 12
Apr 7, '18 Apr 14, '18 Apr 21, '18 Apr 28, '18 May 5, '18 May 12, '18 May 19, '18 May 26, '18 Jun 2, '18
S W S T F M T S W S T F M T S W S T F M

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 13
Apr 7, '18 Apr 14, '18 Apr 21, '18 Apr 28, '18 May 5, '18 May 12, '18 May 19, '18 May 26, '18 Jun 2, '18
S W S T F M T S W S T F M T S W S T F M

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 14
Apr 7, '18 Apr 14, '18 Apr 21, '18 Apr 28, '18 May 5, '18 May 12, '18 May 19, '18 May 26, '18 Jun 2, '18
S W S T F M T S W S T F M T S W S T F M

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 15
Jun 2, '18 Jun 9, '18 Jun 16, '18 Jun 23, '18 Jun 30, '18 Jul 7, '18 Jul 14, '18 Jul 21, '18 Jul 28, '18
M T S W S T F M T S W S T F M T S W S T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 16
Jun 2, '18 Jun 9, '18 Jun 16, '18 Jun 23, '18 Jun 30, '18 Jul 7, '18 Jul 14, '18 Jul 21, '18 Jul 28, '18
M T S W S T F M T S W S T F M T S W S T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 17
Jun 2, '18 Jun 9, '18 Jun 16, '18 Jun 23, '18 Jun 30, '18 Jul 7, '18 Jul 14, '18 Jul 21, '18 Jul 28, '18
M T S W S T F M T S W S T F M T S W S T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 18
Jun 2, '18 Jun 9, '18 Jun 16, '18 Jun 23, '18 Jun 30, '18 Jul 7, '18 Jul 14, '18 Jul 21, '18 Jul 28, '18
M T S W S T F M T S W S T F M T S W S T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 19
Jun 2, '18 Jun 9, '18 Jun 16, '18 Jun 23, '18 Jun 30, '18 Jul 7, '18 Jul 14, '18 Jul 21, '18 Jul 28, '18
M T S W S T F M T S W S T F M T S W S T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 20
l 28, '18 Aug 4, '18 Aug 11, '18 Aug 18, '18 Aug 25, '18 Sep 1, '18 Sep 8, '18 Sep 15, '18 Sep 22, '18
T F M T S W S T F M T S W S T F M T S W

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 21
l 28, '18 Aug 4, '18 Aug 11, '18 Aug 18, '18 Aug 25, '18 Sep 1, '18 Sep 8, '18 Sep 15, '18 Sep 22, '18
T F M T S W S T F M T S W S T F M T S W

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 22
l 28, '18 Aug 4, '18 Aug 11, '18 Aug 18, '18 Aug 25, '18 Sep 1, '18 Sep 8, '18 Sep 15, '18 Sep 22, '18
T F M T S W S T F M T S W S T F M T S W

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 23
l 28, '18 Aug 4, '18 Aug 11, '18 Aug 18, '18 Aug 25, '18 Sep 1, '18 Sep 8, '18 Sep 15, '18 Sep 22, '18
T F M T S W S T F M T S W S T F M T S W

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 24
l 28, '18 Aug 4, '18 Aug 11, '18 Aug 18, '18 Aug 25, '18 Sep 1, '18 Sep 8, '18 Sep 15, '18 Sep 22, '18
T F M T S W S T F M T S W S T F M T S W

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 25
2, '18 Sep 29, '18 Oct 6, '18 Oct 13, '18 Oct 20, '18 Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17, '18
W S T F M T S W S T F M T S W S T F M T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 26
2, '18 Sep 29, '18 Oct 6, '18 Oct 13, '18 Oct 20, '18 Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17, '18
W S T F M T S W S T F M T S W S T F M T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 27
2, '18 Sep 29, '18 Oct 6, '18 Oct 13, '18 Oct 20, '18 Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17, '18
W S T F M T S W S T F M T S W S T F M T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 28
2, '18 Sep 29, '18 Oct 6, '18 Oct 13, '18 Oct 20, '18 Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17, '18
W S T F M T S W S T F M T S W S T F M T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 29
2, '18 Sep 29, '18 Oct 6, '18 Oct 13, '18 Oct 20, '18 Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17, '18
W S T F M T S W S T F M T S W S T F M T

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 30
18 Nov 24, '18 Dec 1, '18 Dec 8, '18 Dec 15, '18 Dec 22, '18 Dec 29, '18 Jan 5, '19 Jan 12, '19
T S W S T F M T S W S T F M T S W S T F

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 31
18 Nov 24, '18 Dec 1, '18 Dec 8, '18 Dec 15, '18 Dec 22, '18 Dec 29, '18 Jan 5, '19 Jan 12, '19
T S W S T F M T S W S T F M T S W S T F

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 32
18 Nov 24, '18 Dec 1, '18 Dec 8, '18 Dec 15, '18 Dec 22, '18 Dec 29, '18 Jan 5, '19 Jan 12, '19
T S W S T F M T S W S T F M T S W S T F

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 33
18 Nov 24, '18 Dec 1, '18 Dec 8, '18 Dec 15, '18 Dec 22, '18 Dec 29, '18 Jan 5, '19 Jan 12, '19
T S W S T F M T S W S T F M T S W S T F

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 34
18 Nov 24, '18 Dec 1, '18 Dec 8, '18 Dec 15, '18 Dec 22, '18 Dec 29, '18 Jan 5, '19 Jan 12, '19
T S W S T F M T S W S T F M T S W S T F

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 35
Jan 19, '19 Jan 26, '19 Feb 2, '19 Feb 9, '19 Feb 16, '19 Feb 23, '19 Mar 2, '19 Mar 9, '19
F M T S W S T F M T S W S T F M T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 36
Jan 19, '19 Jan 26, '19 Feb 2, '19 Feb 9, '19 Feb 16, '19 Feb 23, '19 Mar 2, '19 Mar 9, '19
F M T S W S T F M T S W S T F M T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 37
Jan 19, '19 Jan 26, '19 Feb 2, '19 Feb 9, '19 Feb 16, '19 Feb 23, '19 Mar 2, '19 Mar 9, '19
F M T S W S T F M T S W S T F M T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 38
Jan 19, '19 Jan 26, '19 Feb 2, '19 Feb 9, '19 Feb 16, '19 Feb 23, '19 Mar 2, '19 Mar 9, '19
F M T S W S T F M T S W S T F M T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 39
Jan 19, '19 Jan 26, '19 Feb 2, '19 Feb 9, '19 Feb 16, '19 Feb 23, '19 Mar 2, '19 Mar 9, '19
F M T S W S T F M T S W S T F M T S W S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 40
Mar 16, '19 Mar 23, '19 Mar 30, '19 Apr 6, '19 Apr 13, '19 Apr 20, '19 Apr 27, '19 May 4, '19 May 11, '1
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 41
Mar 16, '19 Mar 23, '19 Mar 30, '19 Apr 6, '19 Apr 13, '19 Apr 20, '19 Apr 27, '19 May 4, '19 May 11, '1
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 42
Mar 16, '19 Mar 23, '19 Mar 30, '19 Apr 6, '19 Apr 13, '19 Apr 20, '19 Apr 27, '19 May 4, '19 May 11, '1
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 43
Mar 16, '19 Mar 23, '19 Mar 30, '19 Apr 6, '19 Apr 13, '19 Apr 20, '19 Apr 27, '19 May 4, '19 May 11, '1
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 44
Mar 16, '19 Mar 23, '19 Mar 30, '19 Apr 6, '19 Apr 13, '19 Apr 20, '19 Apr 27, '19 May 4, '19 May 11, '1
S T F M T S W S T F M T S W S T F M T S

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: 32233 Milestone Inactive Milestone Start-only


Date: Tue 1/23/18 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 45