Professional Documents
Culture Documents
1.0 Purpose:
1.1 This is to define the installation of HVAC Control Panel used in this project
2.0 Scope:
3.0 Material:
3.1 HVAC Control Panels used shall be as per the consultant approvals.
5.0 Responsibilities:
5.1 The Project Manager (PM) shall be responsible for the overall implementation
of the project quality plan, HSE plan and work instructions.
5.2 The Project Engineer is responsible to carry out detail Engineering and
preparation of shop drawings within the scope of contract project
specification.
5.3 Project engineer is responsible to co-ordinate and explain the works to be
carried out to the supervisors.
5.4 QA/QC is responsible for monitoring and controlling the quality work as per
specification/approved drawings.
5.5 The Project engineer is responsible to ensure the materials are as per approved
material submittal.
5.6 Project engineer/Site Engineer/Supervisor will inspect the equipment as per
manufacture’s recommendation prior to installation and are responsible for the
installation for the equipment as per approved drawings.
5.7 Supervisor/Storekeeper will inspect for any damage during shipping, handling
and storage.
5.8 Storekeeper will review the documents and verify the items with the packing
list.
5.9 Storekeeper is responsible for proper storage as per site requirement.
6.0 Safety:
6.1 Safety Officer will ensure the appropriate safety precautions to avoid any
unexpected events in protection, storage and handling of the material.
6.2 All safety precautions shall be followed as per the established Project safety
plan during the installation of services.
6.3 Proper scaffolding certified by Safety Engineer, safety harness shall be used
and secured, if required.
6.4 Dust masks, goggles and gloves shall be worn while doing cleaning and
chipping.
6.5 Work area shall be maintained neat and clean.
7.0 References:
The following stages are applicable for the installation of HVAC Control panel.
10.1.3 If wall mounted type panel, check the wall has been painted where you
want to install the control panel.
10.1.4 Check and confirm there is no obstruction to access the control panel.
10.1.5 Check and confirm there is no water line crossing above the control
panel.
10.1.6 Check the control panel as per approved submittal.
11.0 Records:
Prepare work inspection request (WIR) and have them approved by Consultant.