Professional Documents
Culture Documents
0 Issued for review & 9 Aug. 2017 Orlando Engr. Sayed Engr. Iyad
approval
Page 1 of 7
Client: Main Contractor:
1.1 The Scope of this method statement covers Copper pipes & fittings installation
for hot & cold water supply. The purpose of the documentation emanating
from this statement is to ensure that quality control objectives are maintained
and accurate records are established for all related activities. The objective is to
ensure that the construction plan is executed, controlled and documented in
compliance with the contract drawings and specifications.
2.0 References
3.1 Check material against delivery order and check any damage during
transportation.
3.3 When off-loading, pipes shall be lowered to the ground either manually or with
mechanical aid like crane depending on the quantity of the pipe and should not
be dropped to the ground.
3.4 Pipes shall be stacked on a flat surface free from any sharp objects.
Page 2 of 7
Client: Main Contractor:
3.5 Timber supports of a least 75x75 mm shall be placed beneath the pipes with
spacing not greater than 1.8 meters. Closer supports will be required for sizes
below 160mm dia.
3.6 Pipes shall not be stored under direct sunlight to avoid ultra-violet degradation.
3.7 Larger pipe sizes of thicker class shall always be placed at the bottom.
3.8 Materials shall be transferred / moved carefully to the installation site when
required and with the instruction of the Site Engineer.
4.1 Only specified and approved make of Pipe and Fittings shall be used as per
approved Material Submittal.
4.2 Installation shall be as per approved shop drawings and as per Manufacturer’s
Recommendation.
4.3 Horizontal pipe work shall be laid level as per the recommendations
laid by the Consultant, Manufacturer and concerned local authority.
4.4 All pipes and fittings shall be new / unused with required length and size as
indicated in the approved shop drawings.
4.5 Copper pipes shall be cut with the help of suitable wheel cutter.
4.6 Provide correct size of clamps with optimum spacing as stipulated in the
Project Specification and as recommended by the Manufacturer.
4.7 In case of plastic coated pipes, cut the plastic coat back 75mm along the tube.
Page 3 of 7
Client: Main Contractor:
4.8 Prepare for jointing by cleaning with emery paper. Heat and apply soldering
flux to the pipe and fitting. Connect them and heat joint to create uniform
temperature and apply soldering wire to make a joint.
4.9 Keep a wet rag around the folded plastic to minimize the conduction of heat. Be
sure not to aim the blowtorch directly at the plastic.
4.10 When the joint is complete and cool, fold back the plastic coat and wrap the
joint to give continuity of protection.
4.11 After completing the pipe work or section of a network, installation must be
inspected by Consultant and same shall be documented.
5.1 All joints on testing pipe line shall be inspected with a witness by the Engineer prior to testing
5.2 Test for water supply piping shall be tested at least 1.5 times the operating pressure, without
exceeding pressure rating of piping system materials and water shall be kept in test boundary
5.3 If this test is acceptable, piping shall be drained completely and the piping ends will be covered
5.4 The result of the test shall be recorded and documented on inspection report for the
approval of the Engineer.
Page 4 of 7
Client: Main Contractor:
6.0 Safety
6.1 All personnel who are engaged in the erection activities shall follow safety rules and they will
use the required personal protective equipment like helmet, safety shoes, eye protection safety
glass until the erection works are completed. As a safety precaution, a safety officer and first
aid kit shall be standby and ready at site during working hours.
7.0 Records
8.0 Responsibilities
1. All works associated with above mentioned project is limited to the installation and
testing of Copper pipes & fittings will be the responsibility of the Mechanical
subcontractor in accordance with their contract.
2. The Project Engineer will have the overall responsibility for the fabrication and
installation.
Page 5 of 7
Client: Main Contractor:
3. The Site Engineer / Supervisor / Foreman will be in – charge for the execution of
work at site.
4. The QA/QC Engineer will be responsible for the quality control of the fabrication
works, verification of installed material & including documentations.
5. The Safety Officer will be responsible for the implementation of all safe practices at
site including but not limited to personal protective equipment, proper access to work
area, housekeeping, tool box talk, etc. as described in section 6.0, Safety, at all times.
CHECK LIST
Page 6 of 7
Client: Main Contractor:
Area As applicable
Location As applicable
Page 7 of 7