You are on page 1of 7

Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

APARTMENT COMPLEX, N-180

- Method Statement for Installation & Testing


- Checklist
- Inspection & Test Plan
- Risk Assessment

Rev. Description Date Prepared By Reviewed By Approved By

Issued for 7 Aug. 2017 Orlando Engr. Sayed Engr. Iyad


0 approval

1.0 Scope, Purpose and Objective


Page 1 of 7
Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

1.1 The Scope of this method statement covers the PPR pipes installation &
hydrostatic / pressure test for hot & cold water. The purpose of the
documentation emanating from this statement is to ensure that quality control
objectives are maintained and accurate records are established for all related
activities. The objective is to ensure that the construction plan is executed,
controlled and documented in compliance with the contract drawings and
specifications.

2.0 References

2.1 Approved Material Submittal


2.2 Project Specifications and QCS 2014
2.3 Approved Shop Drawings

3.0 Applicable Location

Aboveground

4.0 Methodology

4.1 Material Storage & Handling

4.1.1 When off-loading, pipes shall be lowered to the ground either manually or with
mechanical aid like crane depending on the quantity of the pipe and should not
be dropped to the ground.

4.1.2 Pipes shall be stacked on a flat surface free from any sharp objects.

4.1.3 Timber supports of a least 75x75 mm shall be placed beneath the pipes with
spacing not greater than 1.8 meters. Closer supports will be required for sizes
below 160mm dia...

4.1.4 Pipes shall not be stored under direct sunlight to avoid ultra-violet degradation.
Page 2 of 7
Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

4.1.5 Larger pipe sizes of thicker class shall always be placed at the bottom.

4.1.6 Materials required for installation shall be carefully moved / transferred to the
location only upon the instructions of the Site Engineer.

4.2 Installation Procedure

“First of all ensure that clearances from the Main contractor & other trades at
site are obtained and site is ready for the installations.”

4.2.1 Only specified and approved make of PPR Pipe and Fittings shall be used.

4.2.2 Installation shall be as per approved shop drawings and as per Manufacturer’s
Recommendation.

4.2.3 Horizontal pipe work shall be laid level as per the recommendations
laid by the Consultant, Manufacturer and concerned local authority.

4.2.4 All pipes and fittings shall be new / unused with required length and size as
indicated in the approved shop drawings.

4.2.5 Fittings by local fabrication from approved supplier shall be used where
non-standard fittings are required after approval obtained from the
concerned authority/ Consultant.

4.2.6 Provide correct size of clamps with optimum spacing as stipulated in the
Specification and as recommended by the Manufacturer.

4.2.7 Check & cut 4 to 5 cm of the pipe from each end if necessary to prevent cracks
appearing on the pipe that may have been damaged during unloading time.

4.2.8 Clean the inner & outer surface of the pipe & fitting. Make sure it is clean and
free of any oily substance.

4.2.9 Mark the length of the pipe to be inserted into the fitting (socket length).
Page 3 of 7
Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

Connect the welding (heater) machine to the electric supply and wait till the
green light blinks. Now the welding temperature ( 260°C ) has reached.

4.2.10 Heat the pipe up to the marked as describe above and after heating push the
pipe & fitting together smoothly & evenly to form an acceptable joint into
position.

4.2.11 Any minor adjustment / correction has to be made with in 4 sec. after
making the joint.

4.2.12 If the joint is to be imbedded in the block work and for vertical drops in areas
like toilet and kitchen, make all joints for the whole section in the worktable
&install in the block work after 5 min.

4.2.13 After completing the pipe work, installation has to be tested at a pressure
of 1.5 times the working pressure.

5.0 Testing

PRESSURE TEST

5.1 All joints on testing pipe line shall be inspected with a witness by the Engineer prior to testing
and shall be exposed to be able to access during the test.

5.2 Test for water supply piping shall be tested at 1.5 times the operating pressure, without
exceeding pressure rating of piping system materials and water shall be kept in test
boundary for at least 24 hours.

5.3 A calibrated pressure gauge shall be connected to at one end of the length to be tested while all
other ends shall be plugged.

5.4 A Pressure Test Report, PL-01 shall be filled up to be attached to the IR and a joint inspection
shall be performed.

Page 4 of 7
Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

5.5 If this test is acceptable, piping shall be drained completely and the piping ends will be covered
by end caps to prevent entrance of foreign materials.

5.6 The result of the test shall be recorded and documented on inspection report for the
approval of the Engineer.

6.0 Safety:

6.1 All personnel who are engaged in the erection activities shall follow safety rules and they will
use the required personal protective equipment like helmet, safety shoes, eye protection safety
glass until the erection works are completed. As a safety precaution, a safety officer and first
aid kit shall be standby and ready at site during working hours.

7.0 Records

7.1 Inspection Request (IR)


7.2 Checklist
7.3 Inspection & Test Plan (ITP)
7.4 Pressure Test Report (PL-01)

8.0 Responsibilities

1. All works associated with above mentioned project is limited to the installation and
testing of PPR pipes will be the responsibility of the Mechanical subcontractor in
accordance with their contract.

2. The Project Engineer will have the overall responsibility for the fabrication and
installation.

Page 5 of 7
Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

3. The Site Engineer / Supervisor / Foreman will be in – charge for the execution of
work at site.

4. The QA/QC Engineer will be responsible for the quality control of the fabrication
works, verification of installed material & including documentations.

5. The Safety Officer will be responsible for the implementation of all the safety
standards and practices on site at all times.

CHECK LIST
System Water Supply System

Area

Location

Material Use PPR Pipes & Fittings

Description Reference Remarks


Confirm Compliance with Approved Material Approval
Material Submittal Yes No Request
Confirm routing/layout complies to Shop Drawings
Page 6 of 7
Client: Main Contractor:

SHEIKH KHALID HAMAD METHOD STATEMENT


ABDULLAH JASSIM AL
THANI
Consultant

Project Name:
MEP
APARTMENT Contractor
COMPLEX – N180

DOCUMENT TITLE: Submittal No. 180-MS-MECH-


003
Installation & Testing of PPR Pipes & Fittings for cold
& Hot Water System Revision No. Rev 0
Date: 7 AUG. 2017

approved drawings Yes No


Confirm Compliance with approved
Method Statement
Method Statement
Yes No
Confirm material is not damaged
Yes No
Confirm Proper Supports installed to
prevent displacement Yes No
Confirm the workmanship &
housekeeping Yes No
Confirm levels are maintained as per
approved drawing
Shop Drawings
Yes No
Confirm all open ends are tightly plugged
with test plugs for testing Yes No
Confirm availability of Inspection and test
plan at site
ITP
Yes No

Page 7 of 7

You might also like