This document provides a cost summary for the construction of an RCC bridge over the Sajirok river. It outlines 3 main items of work - the main bridge, protection work, and dismantling - along with their quantities, rates, and costs. It then calculates the total project cost including taxes, cess, contingency charges, and agency fees, which amounts to approximately 97.82 lakhs.
This document provides a cost summary for the construction of an RCC bridge over the Sajirok river. It outlines 3 main items of work - the main bridge, protection work, and dismantling - along with their quantities, rates, and costs. It then calculates the total project cost including taxes, cess, contingency charges, and agency fees, which amounts to approximately 97.82 lakhs.
This document provides a cost summary for the construction of an RCC bridge over the Sajirok river. It outlines 3 main items of work - the main bridge, protection work, and dismantling - along with their quantities, rates, and costs. It then calculates the total project cost including taxes, cess, contingency charges, and agency fees, which amounts to approximately 97.82 lakhs.
Name of work :- Construction of RCC Bridge over Sajirok river
SL No Sub -Head/ Items of Work Quantity Rate(Rs-p) Unit Amount(Rs-p) Remarks
1 MAIN BRIDGE 1.00 6683501.64 Each 6683501.64 Annexure-A
2 PROTECTION WORK 1.00 770486.06 Each 770486.06 Annexure-B
3 DISMANTLING 1.00 66944.03 Each 66944.03 Annexure-C
Rs 7520931.74 a Add . 12% GST on (A) Rs 902511.81 Add 1% labour cess on (a) Rs 75209.32 Say Rs 8498652.86 b Add 3% contingency charge on (b) _ Rs 254959.59 Rs 8753612.45 c Add 11.75% Agency charge on (c) _ Rs 1028549.463 Rs 9782162 (Rupees Ninety Seven Lakh Eighty Two Thousand One Hundred and Sixty Two) only