GENERAL ABSTRACT OF COST

Name of work :- Construction of RCC Bridge over Sajirok river

SL No Sub -Head/ Items of Work Quantity Rate(Rs-p) Unit Amount(Rs-p) Remarks

1 MAIN BRIDGE 1.00 6683501.64 Each 6683501.64 Annexure-A

2 PROTECTION WORK 1.00 770486.06 Each 770486.06 Annexure-B

3 DISMANTLING 1.00 66944.03 Each 66944.03 Annexure-C


Rs 7520931.74 a
Add . 12% GST on (A) Rs 902511.81
Add 1% labour cess on (a) Rs 75209.32
Say Rs 8498652.86 b
Add 3% contingency charge on (b) _ Rs 254959.59
Rs 8753612.45 c
Add 11.75% Agency charge on (c) _ Rs 1028549.463
Rs 9782162
(Rupees Ninety Seven Lakh Eighty Two Thousand One Hundred and Sixty Two) only