PROJECT MONORAIL SWL= 6 TONS
CONTRACTOR CCK Engineering & Construction Co.,Ltd. Rev.A
Date:28.12.18
CLIENT VINYTHAI PUBLIC COMPANY LIMITED
3.0 LOADS...............................................................................................................3
3.1 Impact Factor............................................................................................ 4
3.2 Crane runway Horizontal forces ............................................................. 4
3.3 Load Combinations.................................................................................. 4
] This document is the property of CCK. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited Page 2
PROJECT MONORAIL SWL= 6 TONS
CONTRACTOR CCK Engineering & Construction Co.,Ltd. Rev.A
Date:28.12.18
CLIENT VINYTHAI PUBLIC COMPANY LIMITED
1.0 SCOPE
This document covers the Structural Design calculations for the proposed mono rail support
beam proposed, at various locations and capacity of crane is SWL = 6 tons lifting with 2 trolley 3
tons and lifting bar
Modeling and analysis for main and secondary steel work is based on linear elastic theory.
The aim of structural design is to be provide, with due regard to economy, a support steel work
capable of fulfilling its intended function and sustaining the specified loads for its intended life.
The design of member shall be based on LRFD / Ultimate strength design and load factors shall
be considered.
2.3 Materials
Use JIS G 3101 Grade SS400 or ASTM A36 with minimum yield strength of structural
steel fy = 2450 kg/cm2
3.0 LOADS
Dead Load- Weight of materials forming the permanent part of the structure
Live load- Mono rail capacity –Safe Working Load (6Tons)
Wind load is not considered (monorail crane is located inside the Building).
Seismic load is not considered (Seismic is not applicable)
] This document is the property of CCK. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited Page 3
PROJECT MONORAIL SWL= 6 TONS
CONTRACTOR CCK Engineering & Construction Co.,Ltd. Rev.A
Date:28.12.18
CLIENT VINYTHAI PUBLIC COMPANY LIMITED
Impact Factor 1.25 is applied. (As per AISC – ASD section – 5.4.2 factor is only
3.3.1 Deflection
All members of structural steel framing system should satisfy the following deflection criteria at
service loads.
For beams : L/360 (For Simply supported)
: L/180 (For Cantilever)
Where L -span of beam
The mono rail beam is analysed in STAAD PRO as an overhung beam. The Live load is
considered as a moving load.
4.0 CONCLUSION
Unity Ratio Check
] This document is the property of CCK. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited Page 4
PROJECT MONORAIL SWL= 6 TONS
CONTRACTOR CCK Engineering & Construction Co.,Ltd. Rev.A
Date:28.12.18
CLIENT VINYTHAI PUBLIC COMPANY LIMITED
] This document is the property of CCK. Any unauthorised attempt to reproduce it, in any form, is strictly prohibited Page 5