Daily Working Record

Name : PHAL Pisey


Month : Jan 2018
Date Contents Achievement Remark
-Combine and compare quantity for all 7
20 Sat -Completed.
bridges.
21 Sun
-Calculate quantity of stone around the
gabion. -Short Presentaion of location and
-Combine and prepare summary condition of 7 bridges using
22 Mon -All finished.
quantity and calculation sheet for all Google Earth.
bridges. -Go to buy GPS device.
-Check location of google Earth
-Prepare schedule for business trip to
check condition at site.
23 Tue -All finished.
-Transfer data FDT (Field Density Test)
to a new form. Sta. 28+000 to 29+000.
-Prepare schedule for checking
24 Wed condition of Bridge at CP-2 & CP-3 -All finished.
Middle section.
25 Thu -Go to check conditions of 7 Bridges. -Completed.
-Prepare pictures and coditions at each
26 Fri -Completed.
bridge.
-Prepare map for 7 bridges, include
27 Sat
distance and duration of transportation.