Professional Documents
Culture Documents
Inspection Report-January 2019
Inspection Report-January 2019
During this month, following review of the design reports and relevant drawings were
carried out against my input on this project. All the below mentioned review work were
submitted to TL, PMAE for further action at his end.
4. Review of the structural drawings of the superstructure of the two major bridges
at Ch. 15+784 and Ch 19+265 respectively as submitted by the contractor vide
its letter no. 2711 dated 31.12.2018 for PMAE review.
5. Worked on the review of revised design and drawing of pier pile foundation of
pier V3-P12 and V3-P13 under viaduct-3 as submitted by the contractor vide its
letter no. 2740 dated 07.01.2019.
(Shailesh Rastogi)