STATUS OF 33 KV FEEDER LINE UNDER DDUGJY 11TH PLAN PHASE ‐ II & 12TH PLAN

Achievement Weekly 
Scope as per  Cumulative  Cumulative 
Scope as per LOA  (23.11.18 to 
Sr.  Survey  Achievement  Achieveme
District Name of PSS Name of Feeder  30.11.18) Remarks 
No.  nt (In % of 
Pole Length  Pole  Length  Pole  Length  Pole  Length 
length) 
( Nos.)  (CKM)  (Nos.)  (CKM)  (Nos.)  (CKM)  (Nos.)  (CKM) 
Katiahr 1 Manihari PSS Katakus GSS to Manihari Pss 194 9.535 194 9.535 Charged
Katiahr 2 Azamnagar PSS Salmari GSS to Azamnagar PSS 234 11.383 234 11.383 Charged
Katiahr 3 Balrampur PSS Dalkhola GSS to Balrampur PSS 284 10.559 284 10.559 Charged
Katiahr 4 Amdabad PSS Katakus GSS to Amdabad PSS 308 16 308 11.921 WIP
Katiahr 5 Mansahi PSS Katakus GSS to Mansahi PSS 0 0
Katiahr 6 Hasanganj PSS Dantkhora PSS to Hasanganj PSS 40 2 40 WIP
Katiahr 7 Sameli PSS Kurshela PSS to Sameli PSS 145 12 115 WIP