Professional Documents
Culture Documents
Required working area will be closed with required barriers, cones, and sign boards as
per regulations.
Manhole covers & GRP sealing plates have to be opened carefully
After opening the sump covers 5 to 10 minutes ventilation has to be provided.
Jetting tanker will be located in the place where the hoses to be inserted.
The cleaners will be provided with safety jackets, helmets, safety shoes and rubber long
gloves.
Upper surface of the manhole is to be cleaned by flushing water with tankers.
Jetting tanker will be operated by trained personal and flushing of water from
downstream to upstream or upstream to downstream will be carried out.
While flushing of water, screened shovel will be kept to drain the water and sludge.
Suction tanker will suck the water from downstream manhole.
Sludge, rags, silt and debris will be collected by long screened shovel and disposed in the
approved areas (Asker land fill).
When there is severe blockage, it will be cleared by manually by jointing the push rods
with special tools then water will be flushed by jetting tankers and sand, silts & debris
will be collected by tankers.
Once flushing and removal of wastages is finished the manholes will be cleaned with
water.
Manhole covers & sealing plates will be fixed back in the right manner.
Grease will be applied in the sides of the manholes for easy operations of opening &
closing the manholes.
Once blockage is cleared the length of the pipe line cleaned will be measured by tapes
for reporting purpose.
Before leaving, the site will be cleaned with water and disinfectant will be sprayed in the
worked area.
METHOD STATEMENT
Existing control panel will be replaced with new control panel and electrical cables from
control panel to junction boxes will be replaced.
New pumps will be installed in the new pedestal.
After completion of work dry inspection will be carried out and sump will be opened.
After completing necessary checks, sump covers will be closed.
Before leaving the pumping station worked area will be cleaned well.
METHOD STATEMENT
Sump covers will be opened using appropriate keys with the help of chain blocks.
Existing beam will be supported from inside of the sump by jacks and wooden planks (4
rows along the beam and 2 columns).
Interlocks will be removed all around the manhole frame.
Chipping out the concrete around the frame and remove the frame.
500mm beam concrete will be removed slowly by electric chisel without damaging
reinforcement.
250mm top portion of the existing beam concrete will be removed inclined for the
purpose of overlapping with the new concrete for effective bonding.
The existing reinforcement will be bent upwards for new concreting and remaining
unnecessary reinforcement will be removed.
16mm reinforcement will be fixed for the new up beam.
Form work will be carried out for the new beam concreting.
Before pouring the concrete approved bonding agent (ISOBOND) will be used in the
existing beam concrete for effective bonding of concrete.
Manhole frames will be kept with alignment on the new beam and sides will be
concreted.
METHOD STATEMENT
METHOD STATEMENT
UNINSTALL INLET & WASTE PENSTOCK AT FILTER
OPTION – 1
OPTION – 2
Disconnect electric supply cable from the penstock actuator.
Remove the Penstock drive actuator/ unscrew.
Remove the actuator stand.
Remove the drive spindle and leave the existing frame in position.
Weld the gate to the frame if possible at close position.
Remove the GRP baffle from the inlet penstock.
After removing the penstocks the upper open area will be closed with MS
epoxy coated sheet.
The above procedures complying for all the filters.
Apply paint remover on all the bolts in the existing pipe joints and carry out
hot bolting.
Disconnect all backwash butterfly valve power supply.
Backwash all the remaining Sand filters which are in service with the
coordination of P2M & SEOMD.
In coordination with SEOMD representative backwash pumps will be shut
down for few hours / a day to install blind flange and gasket.
In order to drain the back wash pipe line, rotate the back wash pipe end
flange 180˚and fix gate valve with hose adaptor to drain the water.
Sand bags will be kept 2m behind the back wash pipe end flange to avoid
water spill inside the whole gallery.
Once the water is drained from back wash pipe, unscrew the bolts in filter
no.07 joint (600mm) and 5mm thick blind flange will be kept in between
the joints and bolts will be tighten again.
During shut down of backwash pumps, 3 to 4 blinds will be installed in the
joints to isolate 3 to 4 filters.
After installing the blind, 2 nos Butter fly valves, Tee joints will be removed.
INSTALL BLIND FLANGE IN AIR SCORE PIPE
Apply paint remover on all the bolts in the existing pipe joints and carry out
hot bolting.
In coordination with SEOMD representative Air blowers will be shut down
for few hours/ a day to install blind flange (18mm thick) and gasket.
Once the blind is fixed (starting from top Tee joint) air score pipes which
are feeding the filters 11 to 20 will be removed.
METHOD STATEMENT
REPAIR AND MAINTENANCE OF SLUICE GATE IN BALANCING TANK
METHOD STATEMENT
Before dismantling the valves, the alternate bolts & nuts will be removed to have
shortest shut down period.
All the station pumps will be started to make the sump empty before dismantling
the valves.
Once the sump is emptied fully, a dummy flange will be fixed in the Sump A rising
main pipe to avoid backflow during installation of valves and to allow Sump B in
operation.
Suction tanker will be available in standby, if there is a back flow during
installation of dummy flange.
Once the dummy flange is fixed in the Sump A rising main pipe, Sump B will be
put in operation till we replace the valves in Sump A.
All the bolt & nuts will be removed in the Sump A, Pump no. 1.
New valves will be installed by providing temporary supports and the flange
adaptor will be adjusted to suit the new valves dimensions.
3mm EDPM rubber gasket will be used in between the valves and pipes to have a
leak proof.
Once the valves are installed, the dummy flange will be removed and put the
rising main in operation.
Pumps in sump A will be started to check the leak.
If there is no leak then concrete thrust blocks will be made to provide the support
to the valves.
Once the thrust blocks are ready the temporary support will be removed and the
Particular pump will be put in operation.
Before leaving the pumping station worked area will be cleaned well.
METHOD STATEMENT
METHOD STATEMENT
REFURBISHMENT OF PUMPING STATION A1C
Before dismantling the valves, the alternate bolts & nuts will be removed to have
shortest shut down period.
All the station pumps will be started to make the sump empty before dismantling
the valves.
Once the sump is emptied fully, a gate valve will be fixed in the Particular rising
main pipe to avoid backflow during installation of valves and to allow other
Pumps in operation.
Suction tankers will be available in standby, if there is a back flow/flooding during
installation of Gate valve.
Once the Gate valve is fixed in the Particular rising main pipe, other pumps will be
put in operation till we replace the valves.
All the bolt & nuts will be removed in the particular pump discharge.
New valves will be installed by providing temporary supports and the flange
adaptor will be adjusted to suit the new valves dimensions.
3mm EDPM rubber gasket will be used in between the valves and pipes to have a
leak proof.
Once the valves are installed, the gate valve will be opened and put the pump in
operation.
Pumps will be started to check the leak.
If there is no leak then concrete thrust blocks will be made to provide the support
to the valves.
Once the thrust blocks are ready the temporary support will be removed and the
Particular pump will be put in operation.
The above mentioned procedures will be followed for the entire pump’s valve
replacement.
Before leaving the pumping station worked area will be cleaned well.
METHOD STATEMENT – PRELIMINARY ARRANGEMENTS FOR DESILTING IN E1
MAJOR PUMPING STATION
Sanitary Network Section will stop the Flow from the upstream network by closing the
stop board at the main chamber on trunk main which is collecting Flow from F-Network
and E-Network.
Sump covers have to be opened carefully by using hiab.
The Remaining Flow reaching the Station which will Minimal will be controlled by
Overpumping
After opening the sump covers 10 to 15 minutes ventilation has to be provided.
Mobilize diesel pumps & electrical pumps and arrange overpumping setup to manage
the flow at E1 pumping station (transfer water from inlet chamber to sump A and C to
reduce flow of sump B).
.Upper surface of the sump is to be cleaned by flushing water with tankers.
Sump level will be reduced by operating station pumps manually.
Before entering in to the sump all electrical supply to the pumps will be switched off and
breakers will be locked by padlocks.
Flush the sump inlet area by TSE water.
Aluminum ladder will be lowered in the sump carefully to carryout cleaning works.
The sump cleaner will be provided with water proof jackets, rubber boots and rubber
long gloves.
Two numbers of Confined space trained personnel will enter the sump with breathing
apparatus and fix the inflatable mechanical test plug.
Upon completion of desilting work in sump B (by other contractor) stoppers will be
removed.
After completing necessary checks, sump covers will be closed.
Before leaving the pumping station the worked area will be cleaned well.