You are on page 1of 4

Weekly Executive Summary Week No.

47

Issues Path Forward Achievements

EPROM Mechanical Projects Engineers reviewed


the selection philosophy of the electrical heat
tracing system of the pi[ping systems as per project
specification.

Process Technology Department requested Based on the specification EPROM Mechanical


Engineering Department to check and confirm Projects Engineers re-calculated the heat loss loads
Electrical Heat Tracing for fuel oil line the capability of the supplied electrical heat and required heat for the requested shutdown
#12-P-600127. tracing system to maintain the temperature of scenario and submitted a detailed assessment
the fuel oil blender line 12-P-600127 at 90 C report for line 12-P-600127 and cross checked the
during the shutdown scenario results with the supplied cables vendor data.

EPROM Mechanical Projects Engineers found that


the supplied electrical tracing system is capable to
handle the shutdown scenario and maintain the
temperature of the fuel oil at 90 C.

EPROM Mechanical Projects Engineers conducted a


site visit to check ERC request and found that as
Review GS reply to ERC mechanical punch per isometric drawing # P-110301-61 a 3” spool is
items # PLWD-68771 concerning ERC request installed between the check valve and the
Punch items #PLWD-68771 unit 11
to relocate the position of check valve of H2 spectacle blind of an isolation gate valve of line 3-
line # 3-P-110301 P-110301 which is not matching the submitted
P&ID # 7T04-PR-11-PI-003 at which the check valve
is directly installed downstream the spectacle
Weekly Executive Summary Week No. 47
blind of an isolation gate valve of line 3-P-110301
with no extra piping spool between them.

EPROM Mechanical Projects Engineers


recommended to re-allocate the check valve to be
D/S the spectacle blind & accordingly the spool will
be re-allocated D/S the check valve which will
minimize the quantity of H2 released to ATM
during positive isolation and turn over periods.

EPROM Mechanical Projects Engineers also


highlighted that there is no obstacles at site that
hinder implementation of above mentioned
request.

EPROM Mechanical Projects Engineers conducted a


site visit to check ERC request and held a meeting
Review GS reply to ERC mechanical punch with ERC concerned engineer to discuss possible
items # PLWD-74606 concerning ERC request solutions.
Punch items #PLWD-74606 unit 60
to install mechanical plugs to all EDG-EN01
indicator cocks. EPROM Mechanical Engineer confirmed that there
is no need to install any plugs to the indicator cocks
openings as per vendor drawings.

EPROM Mechanical Projects Engineers conducted a


Review GS reply to ERC mechanical punch site visit to check ERC request and held a meeting
items # PLWD-74279 concerning unavailability with ERC concerned engineer to discuss possible
of accepted access way (space) for solutions.
Punch items #PLWD-74279 unit 60
maintenance of the fuel accumulator of EDG-
EN01 fuel oil skid to perform the required EPROM Mechanical Engineer confirmed that there
maintenance activities. is no need to make any extra access way or
platforms for the fuel oil accumulator as it doesn’t
Weekly Executive Summary Week No. 47
contain any filter media to maintain or replace
during skid maintenance.

EPROM Civil Projects Engineers reviewed all


comments and replies of GS team for the following
Civil punch items:
 Grating under compressor K-1301 A/B need to
Review GS reply to ERC civil punch items and be added (punch no. 80912 unit 13).
Civil Punch items in all project units cross check with reference codes and project  Grating to be installed under compressor K-
specifications. 1302 A/B (punch no.82138 (unit 13).
 Grating under compressor K-1202 A/B need to
be added (punch no. 81747 unit 12).
 Ladder of PSV-0033 need concrete step be
added (punch no. 83944 unit 51).

EPROM Civil Engineers assisted EPROM


Assist EPROM maintenance team to calculate maintenance team to calculate the max load of
HCU unit steel structure of R-1501 & R- the max load of steel structure deck that can steel structure deck of HCU unit (R-1501&R-1502)
1502 be resist. that can be resist.

EPROM Civil Project Engineers assisted ERC team to


develop layouts drawings, interior design drawings
for EPROM new offices building and control rooms
Assist ERC team to design and draft all details
layouts
New roads, buildings & rooms layouts required for any new roads, buildings & rooms
ERPOM Civil Project Engineers also developed the
and interior design. layouts and furniture.
required layout and interior design drawings for
the new documents library for the project’s
documentation storing and managing.
Weekly Executive Summary Week No. 47
EPROM Civil Project Engineers assisted ERC team to
develop technical scope of work with all the
Assist ERC team to prepare the technical
interior design requirements and furniture of the
Interior design of new Documents scope of work for the Interior design of new
new Documents Library and specifying the
Library (Document Control Room) . Documents Library (Document Control Room)
minimum requirements for each item including for
.
all required details as (Architecture, Plumbing,
HVAC…etc.)

On daily basis EPROM Mechanical Projects


Engineers perform site survey for random units to
overview the progress of the construction activities
Site Survey for all units and technical Daily site visits and survey to overview
and random and cross check the existing situation
reports developing construction activities and progress.
against the design specification and requirements
and discuss with ERC concerned disciplines any
observations.

Both Mechanical and Civil Projects Engineers


started to develop the required QA/QC
documentation for the engineering department
Developing all the required QA/QC
which was submitted and reviewed by the
Engineering Department documentation for the department in
Engineering Projects Senior Engineer
Documentation. reference to the department scope of work
 Job Description for each engineer
and project requirements.
 Engineering Department Forms
 Engineering Department Procedures

You might also like