The weekly executive summary provides updates on:
1) Issues being addressed including reviewing electrical heat tracing and punch list items.
2) Path forwards such as recommendations for relocating check valves and confirming no extra access ways or plugs are needed.
3) Achievements including assessments of heat tracing capabilities and assisting with load calculations and building design.
The weekly executive summary provides updates on:
1) Issues being addressed including reviewing electrical heat tracing and punch list items.
2) Path forwards such as recommendations for relocating check valves and confirming no extra access ways or plugs are needed.
3) Achievements including assessments of heat tracing capabilities and assisting with load calculations and building design.
The weekly executive summary provides updates on:
1) Issues being addressed including reviewing electrical heat tracing and punch list items.
2) Path forwards such as recommendations for relocating check valves and confirming no extra access ways or plugs are needed.
3) Achievements including assessments of heat tracing capabilities and assisting with load calculations and building design.
the selection philosophy of the electrical heat tracing system of the pi[ping systems as per project specification.
Process Technology Department requested Based on the specification EPROM Mechanical
Engineering Department to check and confirm Projects Engineers re-calculated the heat loss loads Electrical Heat Tracing for fuel oil line the capability of the supplied electrical heat and required heat for the requested shutdown #12-P-600127. tracing system to maintain the temperature of scenario and submitted a detailed assessment the fuel oil blender line 12-P-600127 at 90 C report for line 12-P-600127 and cross checked the during the shutdown scenario results with the supplied cables vendor data.
EPROM Mechanical Projects Engineers found that
the supplied electrical tracing system is capable to handle the shutdown scenario and maintain the temperature of the fuel oil at 90 C.
EPROM Mechanical Projects Engineers conducted a
site visit to check ERC request and found that as Review GS reply to ERC mechanical punch per isometric drawing # P-110301-61 a 3” spool is items # PLWD-68771 concerning ERC request installed between the check valve and the Punch items #PLWD-68771 unit 11 to relocate the position of check valve of H2 spectacle blind of an isolation gate valve of line 3- line # 3-P-110301 P-110301 which is not matching the submitted P&ID # 7T04-PR-11-PI-003 at which the check valve is directly installed downstream the spectacle Weekly Executive Summary Week No. 47 blind of an isolation gate valve of line 3-P-110301 with no extra piping spool between them.
EPROM Mechanical Projects Engineers
recommended to re-allocate the check valve to be D/S the spectacle blind & accordingly the spool will be re-allocated D/S the check valve which will minimize the quantity of H2 released to ATM during positive isolation and turn over periods.
EPROM Mechanical Projects Engineers also
highlighted that there is no obstacles at site that hinder implementation of above mentioned request.
EPROM Mechanical Projects Engineers conducted a
site visit to check ERC request and held a meeting Review GS reply to ERC mechanical punch with ERC concerned engineer to discuss possible items # PLWD-74606 concerning ERC request solutions. Punch items #PLWD-74606 unit 60 to install mechanical plugs to all EDG-EN01 indicator cocks. EPROM Mechanical Engineer confirmed that there is no need to install any plugs to the indicator cocks openings as per vendor drawings.
EPROM Mechanical Projects Engineers conducted a
Review GS reply to ERC mechanical punch site visit to check ERC request and held a meeting items # PLWD-74279 concerning unavailability with ERC concerned engineer to discuss possible of accepted access way (space) for solutions. Punch items #PLWD-74279 unit 60 maintenance of the fuel accumulator of EDG- EN01 fuel oil skid to perform the required EPROM Mechanical Engineer confirmed that there maintenance activities. is no need to make any extra access way or platforms for the fuel oil accumulator as it doesn’t Weekly Executive Summary Week No. 47 contain any filter media to maintain or replace during skid maintenance.
EPROM Civil Projects Engineers reviewed all
comments and replies of GS team for the following Civil punch items: Grating under compressor K-1301 A/B need to Review GS reply to ERC civil punch items and be added (punch no. 80912 unit 13). Civil Punch items in all project units cross check with reference codes and project Grating to be installed under compressor K- specifications. 1302 A/B (punch no.82138 (unit 13). Grating under compressor K-1202 A/B need to be added (punch no. 81747 unit 12). Ladder of PSV-0033 need concrete step be added (punch no. 83944 unit 51).
EPROM Civil Engineers assisted EPROM
Assist EPROM maintenance team to calculate maintenance team to calculate the max load of HCU unit steel structure of R-1501 & R- the max load of steel structure deck that can steel structure deck of HCU unit (R-1501&R-1502) 1502 be resist. that can be resist.
EPROM Civil Project Engineers assisted ERC team to
develop layouts drawings, interior design drawings for EPROM new offices building and control rooms Assist ERC team to design and draft all details layouts New roads, buildings & rooms layouts required for any new roads, buildings & rooms ERPOM Civil Project Engineers also developed the and interior design. layouts and furniture. required layout and interior design drawings for the new documents library for the project’s documentation storing and managing. Weekly Executive Summary Week No. 47 EPROM Civil Project Engineers assisted ERC team to develop technical scope of work with all the Assist ERC team to prepare the technical interior design requirements and furniture of the Interior design of new Documents scope of work for the Interior design of new new Documents Library and specifying the Library (Document Control Room) . Documents Library (Document Control Room) minimum requirements for each item including for . all required details as (Architecture, Plumbing, HVAC…etc.)
On daily basis EPROM Mechanical Projects
Engineers perform site survey for random units to overview the progress of the construction activities Site Survey for all units and technical Daily site visits and survey to overview and random and cross check the existing situation reports developing construction activities and progress. against the design specification and requirements and discuss with ERC concerned disciplines any observations.
Both Mechanical and Civil Projects Engineers
started to develop the required QA/QC documentation for the engineering department Developing all the required QA/QC which was submitted and reviewed by the Engineering Department documentation for the department in Engineering Projects Senior Engineer Documentation. reference to the department scope of work Job Description for each engineer and project requirements. Engineering Department Forms Engineering Department Procedures