Metrado de Cargas: 1. Carga Muerta
Metrado de Cargas: 1. Carga Muerta
Datos
𝐸𝑑𝑖𝑓𝑖𝑐𝑖𝑜: 6 𝑝𝑖𝑠𝑜𝑠
Á𝑟𝑒𝑎: 45 ∗ 55 𝑚
𝐾𝑔
𝑝𝑜𝑟 𝑝𝑖𝑠𝑜 𝑊: 800 𝑚2
𝑆 𝐾𝑔
𝑝𝑜𝑟 𝑝𝑖𝑠𝑜 𝐶 : 250 𝑚2
𝐾𝑔
𝑡𝑒𝑐ℎ𝑜: 150 𝑚2
𝛿𝑚𝑎𝑥 : 2.5𝑐𝑚
𝑐𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑎𝑟 5 𝑠𝑢𝑏𝑒𝑠𝑡𝑟𝑎𝑡𝑜𝑠
1. Metrado de cargas
Carga muerta
𝐶𝑀 = 6𝑝𝑖𝑠𝑜𝑠 ∗ 0.80𝑡𝑛/𝑚2 ∗ (4.5𝑥5.5𝑚)
𝐶𝑀 = 118.8𝑡𝑛
𝑄𝑉 = 𝐶𝑀 + 𝐶𝑉
𝑄𝑉 = 90 + 17
𝑄𝑉 = 107
𝑄ℎ 𝑀 𝑀
= 0.2 = 1.5 𝑒=
𝑄𝑉 𝑄ℎ 𝑄𝑉
𝑄ℎ 𝑀 32.1
= 0.2 = 1.5 𝑒=
107 21.4 107
𝑄ℎ = 21.4 𝑀 = 32.1 𝑒 = 0.3
𝑐𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑎𝑐𝑖𝑜𝑛𝑒𝑠
𝑘𝑔
−𝑓 ′ 𝑐 = 210
𝑐𝑚2
−𝑓𝑦 = 4200 𝑘𝑔/𝑐𝑚2
5
− 𝐴𝑠 = 5∅ ′′
8
− 𝐿𝑜𝑛𝑔𝑖𝑡𝑢𝑑 𝑑𝑒𝑙 𝑝𝑖𝑙𝑜𝑡𝑒 𝑛𝑜 𝑚𝑎𝑦𝑜𝑟 𝑑𝑒 11 𝑚
−Seccion cuadrada
− Concreto prefabricado
𝐶𝑎𝑟𝑔𝑎 𝑑𝑒 𝑡𝑟𝑎𝑏𝑎𝑗𝑜
𝑄𝑎 = 25 𝑡𝑛
𝑄𝑑𝑖 = 𝑄𝑎 . 𝐹𝑆
𝑄𝑑𝑖 = 25𝑥3 = 75 𝑇𝑛
𝑄𝑑𝑖 = 𝐶𝑁𝑐 𝐴𝑝𝑢𝑛𝑡𝑎 + ∑ 𝐶𝑎 𝐴𝑙𝑎𝑡𝑒𝑟𝑎𝑙
𝐸𝑠𝑡𝑟𝑎𝑡𝑜 1
𝐶 = 0.5 → 𝐶𝑎 = 0.375 (𝑡𝑎𝑏𝑙𝑎) = 0.375(400)(120) = 18000
𝐸𝑠𝑡𝑟𝑎𝑡𝑜 2
𝐸𝑠𝑡𝑟𝑎𝑡𝑜 3
𝐶 = 2.00 → 𝐶𝑎 = 0.65(𝑡𝑎𝑏𝑙𝑎) = 0.65(𝑥)120
𝑃𝑢𝑛𝑡𝑎
𝐶=2 = 2(9)(900) = 16200
𝑧 550
𝑍 = 5.5 𝑚 = = 18.33
𝑏 = 30𝑐𝑚 𝑏 30
𝑧
= 18.33 → 𝑁𝑐 = 9
𝑏
𝑁𝑢𝑚𝑒𝑟𝑜 𝑑𝑒 𝑝𝑖𝑙𝑜𝑡𝑒𝑠
𝑄𝑣
# 𝑝𝑖𝑙𝑜𝑡𝑒𝑠 =
𝑄𝑎
145.72 𝑡𝑛
# 𝑝𝑖𝑙𝑜𝑡𝑒𝑠 =
25𝑡𝑛
#𝑝𝑖𝑙𝑜𝑡𝑒𝑠 = 5.82 (𝑅𝑒𝑞𝑢𝑒𝑟𝑖𝑑𝑜) → #𝑝𝑖𝑙𝑜𝑡𝑒𝑠 = 6 (𝐴𝑠𝑢𝑚𝑖𝑑𝑜)
𝑏)Forma y área como grupo
𝑐𝑜𝑚𝑜 𝐿𝑝 = 10.7
𝐺 = 4𝑏
𝐺 = 4(30)
𝐺 = 120 𝑐𝑚
𝐴𝑟𝑒𝑎 = (150)(270)
𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑟𝑜 = 2(150 + 270)
= 840 𝑐𝑚
352 𝜋
𝐴𝑟𝑒𝑎 = = 962.11 𝑐𝑚2
4
𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑟𝑜 = 𝜋𝐷 = 109.96𝑐𝑚2
𝑓’𝑐 = 280 𝑘𝑔/𝑐𝑚2
𝑓𝑦 = 4200 𝑘𝑔/𝑐𝑚2
𝐴𝑠 = 5 ф ½
Presión efectivo
=20b
=20(35)
=700cm
𝜎𝑡′ = 0.959
𝑁𝑞 = 62 (𝑡𝑎𝑏𝑙𝑎) = 0.959(62)(2)(962.11) = 114410.27 𝑘𝑔
𝐴𝑝𝑢𝑛𝑡𝑎 = 2𝐴𝑝𝑖𝑙𝑜𝑡𝑒
𝐴𝑝𝑢𝑛𝑡𝑎 = 2(962.11)
𝐶𝑜𝑚𝑜 𝐿𝑝 = 11
∴ 𝐺 = 4𝑑
𝐺 = 4(35)
𝐺 = 140𝑐𝑚
𝑑
= 𝑘√3
2
35
= 𝑘√3
2
𝑘 = 10.10 𝑐𝑚
𝐵 = 𝐺 + 2𝑘
𝐵 = 140 + 2(10.10)
𝐵 = 160.2𝑐𝑚 ≅ 160𝑐𝑚
𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑟𝑜 = 160(6)
𝑃𝑒𝑟𝑖𝑚𝑒𝑡𝑟𝑜 = 960𝑐𝑚
𝐵
𝐴𝑟𝑒𝑎 = 6 (𝐵 ( ) √3)
2
3 2
𝐴𝑟𝑒𝑎 = 𝐵 √3
2
3
𝐴𝑟𝑒𝑎 = (160)2 √3
2
𝐴𝑟𝑒𝑎 = 66510.75 𝑐𝑚2
𝑑
𝐶𝑠 = (0.93 + 0.16√ ) 𝐶𝑝
𝑏
1100
𝐶𝑠 = (0.93 + 0.16√ ) 0.03
35
𝐶𝑠 = 0.0548
𝑑 = 1100
𝜎 ′ 𝑡 = 0.959
𝑁𝑞 = 62
(0.0548)(11910)
∆𝑝𝑠 = 1100(0.959)(62)=0.0099
∆0 = ∆𝑠 + ∆𝑝𝑝 + ∆𝑝𝑠
∆0 = 0.23 + 0.55 + 0.01
∆0 = 0.79𝑐𝑚 < 5 … … . 𝑜𝑘‼!
Asentamiento Grupo de pilote
𝐵
∆𝑔 = ∆0 √
𝑑
160
∆𝑔 = 0.9055√
35
∆𝑔 = 1.936 𝑐𝑚 < 5 … . 𝑜𝑘‼‼‼