Professional Documents
Culture Documents
Instruction Manual
Email: info.india@howden.com
Web: www.howden.com
Customer: HSV,FRANCE
Our ref: ICBD 5003
Project: TCDRI BATURAJA ,INDONESIA
Your ref: 573453/690025
Site: INDONESIA
Date:
14-07-2016
CONTENTS
SAFETY PRECAUTIONS 5
CONDITION ON DELIVERY 6
ERECTION
SIMPLY SUPPORTED FAN 7 - 8
CERAMIC ROPE FIXING DETAIL 9
BELLE VILLE WASHER FIXING DETAIL 9
RIGID & FLEXIBLE ATTACHMENT 10
ROTOR ASSEMBLY 11 - 12
LIFTING ARRANGEMENT OF ROTOR 13
ROTOR ALIGNMENT 14
INLET CONE FIXING DETAIL 15
COUPLING ALIGNMENT 16
SEALING PLATE FIXING DETAIL 17
OVERHUNG FAN 18
ASSEMBLY PROCEDURE OF BEARINGS 19 - 23
IMPELLER LOCKING ARRANGEMENT 24
SOME IMPORTANT NOTES 25
FANS ON VIBRATION ISOLATOR 26
ACCESSORIES 27 - 28
COMMISSIONING PROCEDURE
ASSEMBLY & START UP CHECK LIST 29
PRECAUTIONS BEFORE STARTING 30
CHECK UP DURING RUNNING 31
CONTENTS
MAINTENANCE
RUNNING MAINTENANCE 32
SHUTDOWN MAINTENANCE 32
LUBRICATION 33 - 35
VIBRATION ACCEPTANCE NORMS 36 - 37
LOCATION FIXED & FREE BEARINGS 38
AFTER MOUNTING CLEARANCE OF BEARINGS 39
SOFN HOUSING
BEARING ASSEMBLY 40
OIL LEVEL 41
LUBRICATION 42
MOUNTING/DISMOUNTING 43
MAINTENANCE 43
INLET DIMENSION 44
LIST OF SPARE 45
ANNEX
DATA RECORDED DURING TRIAL RUNNING
46
OF FAN
DOS & DON'T'S 47
BRIEF DESCRIPTION OF FAN COMPONENTS 48
TROUBLE SHOOTING CAN HELP WHEN YOU
49 - 51
SUSPECT A PROBLEM
HOW TO ORDER 52
SOLYVENT SERIES
FAN IMPELLER
DISC
SQUARE FLANGE
SCROLL PLATE
INLET DAMPER
INLET
INSPECTION DOOR
SHROUD
SHAPPED INLET
SHAFT TECHNOLOGY
SQUARE FLANGE
STIFFENER
STRAIGHT SHAFT FOR IMPELLER OUTLET
BETWEEN BEARINGS
SPLIT FLANGE
SOLEPLATE
SQUARE FLANGE
BEARING
SAFETY PRECAUTIONS
The operation and maintenance of machinery of any kind requires a person to be cautions and
aware of the damages that exist. In order to avoid injuries to personal and damage to
machinery, the following precautions are very important.
1. Never apply power to the fan motor for any reason until the fan has been completely
installed in its system, and the system inspected to be sure that no debris has been left
in the fan & ducts, and it is known that the inspection doors at the inlet and outlet of the
air passages are shut. The usual procedure is to remove the fuses from the disconnect
switch and open its safety isolation switch until the installation is completed and
inspected.
2. Start the fan momentarily and disconnect it. Observe rotation of the wheel or the drive
rotation is correct. Do not allow the fan to run backward, except momentarily.
4. Always open the disconnect switch and lock it in the open position with a padlock before
doing any service or maintenance work on the fan.
5. After service of any kind make certain that all adjustment have been properly made and
tightened ,inspection doors closed, there is no debris in the air passages and all tools
have been removed before unlocking the disconnect switch to place the fan in operation.
6. Make a periodic inspection of the fan wheel, bearings and coupling to be sure that
corrosion has not set in to weaken them. Where there are signs of corrosion there is
danger of mechanical failure. Corroded parts should be replaced.
1. Ensure that the concrete foundation has been made at site as per general assembly
drawing.
4. Place the foundation bolts in all foundation pockets as required and hook up with the
common holding rods provided in the foundation.
6. Generally the concrete block foundation provided to support the fan unit should be at a
level lower than the final installation level by about 50mm. This clearance allows
correction of the civil engineering false level. It is therefore necessary to maintain the
center of the fan and the level of installation.
7. Place the steel packers in between the foundation bolts to the required height.
8. Place the base frame on the packers and bolt together at four corners.
10. Adjust the horizontal level of the base frame by adjusting steel packers by using dumpy
level. The dimensions to be maintained as per the GA drawing. Check up the diagonal
dimensions for assuring the squareness of the base frame.
11. Place the bearing pedestals on the base frame and bolt with base frame. Check up the
horizontal level of the bearing pedestals by using water level/dumpy level. The level of pedestal
to be checked with water level /dumpy level.
12. Check up the center-to-center distance of bearing pedestal and diagonal of holes on the
pedestal for ensuring the square ness. This should be maintained as per the drg.
Temporary locking arrangement to be provided for the base frame to avoid disturbance
of the base frame during grouting. The temporary locking can be removed after grouting.
13. Put the grouting materials for the foundation bolts up to the pocket level.
NOTE: Make sure that non-shrinkage type grout materials are used. Allow the
grout to dry long enough.
14. Again check the level and height of bearing pedestals and record the values.
NOTE: Top surface level of bearing pedestals should be checked by master level.
Permissible deviation is 2 division of master level having accuracy 0.02mm/meter. This
level should be obtained by adjusting steel packers in-between base frame and
foundation. Please avoid shims providing between base frame and pedestal.
15. Bolt the bottom half of the casing with inlet box. Provide ceramic rope in between the
flanges as per the fig. 11.
16. Place lower part of casing on base frame and bolt it. Provide Belleville washer in
casing with base frame fixing bolt, as shown in fig. 12.
17. Check the center line of casing, shaft and impeller axis with respect to base frame
and bearing pedestals.
18. Weld the rigid attachment at motor end in-between casing and base frame as per
fig. 13.
FIG. No. 11
CERAMIC ROPE
19. Weld the flexible attachment at free end on inlet box and base frame as per fig. 14.
FIG. No. 14
(WHEREVER APPLICABLE)
ROTOR ASSEMBLY :-
20. Assemble the bearings in shaft as per the instruction given in the enclosed manual.
21. Sling the fan rotor assembly consisting of impeller, hub, shaft, bearings and bearing
housings with inlet cone as shown in fig. 15.
22. Position the fan rotor assembly with inlet cone on the bearing pedestals. Bolt the bearing
housing with the bearing pedestals, The holding bolt is of high tensile grade and should
have plain washer, spring washer, main nut and lock nuts are to be used.
23. Check level of shaft and align shaft axis for approx. gap between inlet cone to impeller
shroud.
24. To achieve the shaft level at coupling end to horizontal, follow the procedure as explained
here.
26. Install top half of the casing and inlet box and bolt it. Put ceramic rope in-between
parting flanges as shown in fig.11
27. Tighten the parting flange bolts, all bolts should be provided with plain washer.
28. Bolt the supporting plates which is welded on the bottom casing as shown in fig. 17. with
the top casing.
29. Position the inlet cone on its place with fixing clamp or bolted arrangement (refer GA
drawing.)
30. Check overlap and clearance between impeller and inlet cone and note down the value in
annex. The back mark dimension between the casing and impeller disc also to be
maintained as per the drawing. After achieving the dimensions as per the drg. weld the
cone with its flange as per fig. 18(In some cases cones are not welded with flange at our
workshop to facilitate adjustment at site.) . While welding the cone with its angle flange
sequence welding is to be adopted (not continuous welding) to avoid distortion.
If the overlap dimension is deviating from the drawing, this can be achieved by cutting
the tack weld of the cone with the angle flange and can be moved as required.
31. Insert the coupling half on to the fan shaft by heating the coupling hub in hot oil bath up
to 125 °C. Please check up the bore and shaft dimensions.
32. Insert the other coupling half on to the motor shaft by heating the coupling hub in hot oil
bath up to 125 °C. Please check up the bore and shaft dimensions.
33. Place the motor base frame on the foundation with packing plates, and foundation bolts.
Level the base frame with water level by adjusting the packers placed below the base
frame.
34. Place the motor on the base frame and check up the coupling gap and coupling side and
up/down variations. If required adjust the same by moving the motor along with the base
frame.
35. Put the grouting materials for the foundation bolts of the motor base frame up to the
pocket level.
NOTE: Make sure that non-shrinkage type grout materials are used. Allow the grout to dry
long enough.
36. Gap between coupling halves should be maintained as per the dimensions shown in
assembly drawing.
FIG. No. 15
(same procedure for overhung rotor also)
FIG No. 16
ROTOR ALINGMENT
FIG. No. 17
Fig No. 18
(Wherever applicable)
COUPLING ALIGNMENT
1. Level and align the motor to the fan shaft level by using brass / stainless steel shims
underneath the motor pads.
2. Align the motor with respect to fan coupling. Alignment of the couplings should be done
using two axial dial gauges and one radial dial gauge as shown in fig. 19.
Allowable radial misalignment max. 0.05 mm.
Allowable axial misalignment max. 0.05 mm.
3. Arrange for final grouting of fan and motor base frame by using non-shrink type
grout material.
4. Couple the fan and motor through the coupling after taking a trial run of motor in de-
coupled condition.
FIG No. 19
FIG No.20
FIG No. 21
OVERHUNG FANS
1. Check up the civil foundation level for its surface level evenness, and different elevation
level as per the drawing. Chip off the uneven surface.
2. Check up and ensure that the foundation pocket dimensions are as per drawing.
3. Place the packers in between all the pockets. Place the foundation bolts on all the packers.
4. Place the lower part of casing and common base frame on the packers and fix the
foundation bolts.
5. Check up and adjust the horizontal level of the base frame and casing using water level.
This can be adjusted by adding and removing the packer plates below the base frame.
6. Insert the bearing on the fan shaft as explained in the assembly procedure for bearings.
7. Install the impeller on the base frame and bolt with the base frame.
8. Grout the foundation pockets with non shrinkage grout material upto the pocket level
allow long enough for proper curing.
9. Level the impeller shaft by using master level. The level has to be checked in between the
bearings. The shaft should be levelled with in 2divisions (0.04mm).
10. Install the top casing and inlet cone, put ceramic rope in between the parting flanges.
Check up the cone gap and overlap and record the values. If required the cone gap can be
adjusted by heating and hammering the inlet cone tip, to maintain the gap as per the
drawing.
11. Fix the inlet damper and flexible connection at fan inlet.
12. Fix Evase and outlet flexible connection at fan outlet.
13. Fix the coupling on the impeller and motor fan shaft.
14. Align the motor with respect to the fan shaft as explained earlier.
15. Fix cooling disc with cover (fig. 21), coupling cover and shaft cover.
16. After completing installation and alignment, final grouting of the foundation bolts shall be
carried out.
The following procedure will be applicable rotor, loose bearings and bearing housings, if and
when used.
As the bearings are finished to high precision, thorough inspection and checking on the
following points are essential prior to assembly :
a) On opening the packing of bearings, the same shall be thoroughly checked for dirt or
other foreign matter and if found, same shall be carefully washed unless and until it is
necessary.
b) The shaft shall be checked for damage due to transport and handling. Particularly the
surfaces where the bearings are to be mounted should be checked for rusting, scoring etc.
Rust, if found, should be removed by rust remover. Heavy pitting on bearing surfaces of
shaft is not acceptable.
Localized scorings could be removed using oil stone.
If the shaft is found to have a bend, the same should not be used for assembly.
d) Bearing to be mounted shall be taken out of the original protective packing only
immediately before mounting.
e) The mounting and dismounting tools and necessary jigs must be of proper dimension and
simple design so that they do not cause any mechanical damage to the bearings.
A bearing with tapered bore, which is seated direct on a shaft, or which is mounted with
an adapter sleeve, ordinarily requires a somewhat tighter fit than a bearing with
cylindrical bore. This fit is achieved by pressing on the inner ring by means of a nut or by
driving in the sleeve. In both cases, the inner bearing is expanded and this results in a
reduction of radial bearing clearance.
If a double row self aligning ball bearing is mounted on an adapter sleeve, the sleeve nut
might be tightened but not so much as to prevent the outer bearing from turning easily
and it must be possible to swing the outer race easily from one side to the other side.
Double row spherical roller bearings which are used mostly in heavy load applications are
mounted with greater interference. The radial clearance is adapted to this fit and its
reduction can be measured while mounting by means of a feeler gauge. For checking the
correct fit of the inner ring, both the reduction of radial clearance and the distance of
the inner ring is driven axially on the tapered seating or on the adapter sleeve and is
measured. For solid shafts, the axial displacement is approximately fifteen times as large
as the desired clearance reduction.
ASSEMBLY PROCEDURE
e) Keep the rotor assembly in position but slightly elevated position on supports above the
bearing housing bottom halves.
f) Insert the double - lip seal on to the shaft at impeller end if applicable.
g) Insert the taper sleeve on to the shaft to the location with thread portion outside.
h) Locate the bearing position and assemble the lock washer and nut with the taper sleeve.
(no locating ring for this bearing as this is free bearing).
i) Keep the gap between bearing to bearing housing to accommodate the expansion of
shaft as shown in our drawings.
j) Tighten the lock nut on the taper sleeve. For tightening the nut, do not use steel chisel
or rod but use either brass or copper rod for taking the force of hammer. The
necessary tightness is achieved when the brass or copper rod flares at the load
transfer end. Check for the clearance between roller and outer race as mentioned in
SKF catalogue.
l) Now start assembly of drive side (coupling side) bearing by inserting the double lip seal
on to the shaft if applicable.
n) Arrange the locating ring on one side or either side of bearing , as the case may be.
q) Locate the bearing position and assemble the lock washer and nut with the taper sleeve.
s) Now keep the lock washer teeth locked to the lock nut groove by bending.
w) Place the top half bearing housing without applying any grease. Check for free rotation
of the rotor assembly.
SKF can supply heating tools, such as oil baths, induction heaters,
heating cabinets and electric and electric plates with adjustable thermostat and
cover, for all common mounting needs.
Bearings with
shields or seats
should not be
heated.
Lifting gear
(housing)
Direction of discharge
The fans are supplied in discharge direction as specified in order . This can be altered at
site .
Connection of duct
Duct connection of the fan casing must not exert any load directly on the fan as the casing
may be deformed and the inlet cone may come in contact with impeller .
Direction of impeller
The main idea of providing vibration isolator is to avoid transmission of undue vibration
from the equipment to the surrounding structure and not to reduce equipment vibration
, in fact equipment vibration may be on higher side due to soft foundation and vibration
value 10 mm/s ( Peak Value ) is acceptable for Fans.
We do not normally recommend to use vibration isolator when fans are installed at ground
level.
6. Fix the inlet damper with inlet box (wherever applicable) /inlet
Ensure correct damper orientation; the close to open direction of damper will be same
with that of impeller rotation.
Ensure flexibility after installation ; For dust application flexible connection are
provided with sleeve . Follow the air flow mark for correct installation.
10. Fix the linkage between actuator and damper. The operating lever on the actuator and the
lever on the damper should be in parallel and of equal length , for proper operation of
the damper.
80 10
90-100 15 5 49 36.1
110 25
A
Assembly of disc halves
13. Weld the cooling disc guard fixing angle on the bearing pedestal as shown in fig. 21.
14. Weld the coupling guard fixing angle on the bearing pedestal.
15. After completing all erection and alignment work, full grouting of the foundation bolts
shall be carried out.
NOTE :
Whenever welding is carried out on the fan parts during erection at site condition, direct
STATIC PARTS:
ROTOR PARTS:
Shaft alignment :
LUBRICATION:
UTILITIES:
5. Check that the different components of the control system are correctly connected.
7. Check that no foreign object has been left anywhere in side the fan.
8. Check that no water stays in the bottom of the casing and inlet box.
10. Check that the inspection door on the casing and inlet box are correctly shut.
11. Check that the rotor can turn freely without rubbing with any static parts.
11. Check that the bearings have been correctly filled with bearing lubricant as it is noted
T IMPELLER
P IMPELLER
B IMPELLER
1. People responsible for the starting must always stay nearest as possible to the
emergency stop switch.
2. The fan is rotating in correct direction
mm/s rms
N < 600 rpm: 2-1000 Hz Fixation Rigide Fixation Souple Fixation Rigide Fixation Souple Fixation Rigide Fixation Souple
N > 600 rpm: 10-1000 Hz Rigid Support Flexible Support Rigid Support Flexible Support Rigid Support Flexible Support
A
Démarrage
Start-up
2,3 A
Démarrage- Démarrage-
Start-up Start-up
2,8 Démarrage
Start-up B
3,5 Satisfaisant
Good
4,5
B
Satisfaisant Alarme Satisfaisant
C
6,3 Good Alarm Good
7,1
Alarme
New Manual Solyvent.docx AlarmSection title here Page 32 of 55
9 C
Satisfaisant Alarme
Good Alarm
D
11
Arrêt
Shutdown
11,2 Arrêt D
Shutdown
11,8
Alarme Arrêt
Alarm Shutdown
12,5
Arrêt
Shutdown
Customer: HSV ,FRANCE Our ref: ICBD 5003
Project: TCDRI BATUA JA Your ref: 573453/690025
Site: INDONESIA Date: 14-07- 2016
Afyonkaranhisar,Turkey
MAINTENANCE
RUNNING MAINTENANCE
1. Fill bearing lubricant of recommended specification and quantity at the specified intervals
for bearing housings. The interval should be determined based on local condition like
working environment etc.
3. Check periodically the proper seating of fan on the foundation and for abnormal vibration
at any location.
4. Check for looseness of any bolts in the fan pedestals, casing, etc.
1. Open inspection door in casing. Clean the impeller blades and internals.
3. Check the overlap and radial clearance between impeller shroud and inlet cone. If found
disturbed adjust the same.
5. Check the bearing condition like roller clearance and the rolling surfaces of races.
Appendices
MOBILTEMP SHC 32
MOBILUX EP 2 (1)
BEACON 325
BEACON EP 2 (1)
UNIREX N 2
ALVANIA EP 2 (1)
SHELL
DARINA R 2
MULTIS EP 2 (1)
TOTAL
CALORIS MS 3
BP ENERGREASE LS EP 2 (1)
SLYTEX ECO
HAFA
SUPERGREASE N° 6 EP 2 (1)
Do not mix grease types with different properties; it would greatly reduce
machine performances and induce overheating risks.
Appendices
CHEVRON Regal R&O 32 Regal R&O 46 Regal R&O 68 Regal R&O 100 Regal R&O 150
INLET DAMPER
According to the installation conditions and the operating frequency of the inlet damper
following should be lubricated.
VANE BEARINGS : Make sure when topping up that the spent grease is discharged normally.
Grease
For fans provided with spherical roller bearing, the bearings housing are
fitted with grease nipples and are fitted with the correct amount of grease
when requested.
The lubrication intervals and the amount of grease necessary for relubrication
The chart is based on a temperature of 70°C. For every 15°C increase in
temperature the lubrication interval should be reduced to 50% of the value
obtained from the chart.
(Example : For a fan fitted with spherical roller bearings with the bearing bore
diameter of 120mm and running at 1000RPM the relubrication interval will be
800 operating hours if the bearing's temperature does not exceed 70°C).
Oil
When inspecting the oil level of a bearing, check to ensure that the right type of oil is in use
and that the oil level gauge's air vent is unobstructed.
Take a small sample of the oil and compare it with fresh oil. If the sample look's cloudy, then
it is mixed with water and should be replaced.
Dark or thick oil is a sign of dirt or indicates that the oil has started to carbonize. Change
the oil completely and, if possible, clean the bearing by flushing it with fresh oil . When
changing the oil, be sure that you are using the same type of oil , and that you refill to the
required level .
A more reliable method for determining the oil condition is to analyze a sample . If the oil is
contaminated it may be worthwhile to change the seals or consider filtration .
Oil in oil bath circulation systems requires change only once each year, providing that the
operating temperatures does not exceed 50 to 60 º C and the oil does not become
contaminated . Change the oil four times each year for operating temperatures of 100 º C ;
monthly for operating temperature of 100 º C.
AT MOUNTING gm 240 310 340 380 470 680 850 1000 1800 2200
FREE BRG.
FIXED BRG.
NUT
Bearing bore Reduction in Axial drive-up Taper 1:30 Minimum permissible residual
diameter radial internal Taper 1:12 on diameter clearance after mounting
d clearence on diameter bearings with initial clearance
3
Over incl. min max min max min max Normal C C4
mm mm mm mm
30 40 0.020 0.025 0.35 0.4 0.015 0.025 0.040
40 50 0.025 0.030 0.4 0.45 0.020 0.030 0.050
50 65 0.030 0.040 0.45 0.6 0.025 0.035 0.055
65 80 0.040 0.050 0.6 0.75 0.025 0.040 0.070
80 100 0.045 0.060 0.7 0.9 1.75 2.25 0.035 0.050 0.080
100 120 0.050 0.070 0.75 1.1 1.9 2.75 0.050 0.065 0.100
120 140 0.065 0.090 1.1 1.4 2.75 3.5 0.055 0.080 0.110
140 160 0.075 0.100 1.2 1.6 3.0 4.0 0.055 0.090 0.130
160 180 0.080 0.110 1.3 1.7 3.25 4.25 0.060 0.100 0.150
180 200 0.090 0.130 1.4 2.0 3.5 5.0 0.070 0.100 0.160
200 225 0.100 0.140 1.6 2.2 4.0 5.5 0.080 0.120 0.180
225 250 0.110 0.150 1.7 2.4 4.25 6.0 0.090 0.130 0.300
250 280 0.120 0.170 1.9 2.7 4.75 6.75 0.100 0.140 0.220
280 315 0.130 0.190 2.0 3.0 5.0 7.5 0.110 0.150 0.240
315 355 0.150 0.210 2.4 3.3 6.0 8.25 0.120 0.170 0.250
355 400 0.170 0.230 2.6 3.6 6.5 9.0 0.130 0.190 0.290
400 450 0.200 0.260 3.1 4.0 7.75 10 0.130 0.200 0.310
450 500 0.210 0.280 3.3 4.4 8.25 11 0.160 0.230 0.350
500 560 0.240 0.320 3.7 5.0 9.25 12.5 0.170 0.250 0.360
560 630 0.260 0.350 4.0 5.4 10 13.5 0.200 0.290 0.410
630 710 0.300 0.400 4.6 6.2 11.5 15.5 0.210 0.310 0.450.
710 800 0.340 0.450 5.3 7.0 13.3 17.5 0.230 0.350 0.510
800 900 0.370 0.500 5.7 7.8 14.3 19.5 0.270 0.390 0.570
900 1000 0.410 0.550 6.3 8.5 15.8 21 0.300 0.430 0.640
1000 1120 0.450 0.600 6.8 9.0 17 23 0.320 0.480 0.700
1120 1250 0.490 0.650 7.4 9.8 18.5 25 0.340 0.540 0.770
The spherical Roller Bearing in SOFN blocks are lubricated with oil: a pick-up ring in the
housing serves to bring about oil circulation . The pick-up ring hangs loosely on a sleeve on the
shaft at one side of the bearing and dips into oil in the lower half of the housing. As the
shaft rotates, the ring follows and transports oil from the bottom of the housing to a
collecting trough formed in the spigot (cylindrical extension) of the one housing cover on a
level with the rollers of the bearing under the shaft thus permitting oil to enter the bearing.
The oil then flows through an opening in the spigot of the opposite housing cover back into
the reservoir at the bottom of the housing. The collecting trough is so dimensioned that the
level of the oil in the trough guarantees an optimum supply of lubricant to the bearing. The oil
in the rese3036rvoir at the bottom of the housing is cooled, depending on the ambient
temperature, before being re-circulated. This lubrication system permits SOFN plummer
blocks to be used for high-speed bearing applications. The difference between the maximum
and minimum oil levels in the reservoir may be relatively large when a pick-up ring is employed.
The intervals between oil replenishment or oil change are correspondingly long. The requisite
oil quantity for each housing is given in the tables.
The oil level indicator supplied with the housing should be screwed into one of
the four threaded holes provided in the housing covers. The remaining holes may be used for
oil drainage. The "max." and "min" oil levels given in the tables should be marked on the
indicator.
The pick up ring must always be in position and it's freedom of movement should not be
restricted. If the ring is not incorporated . There will be an almost immediate danger of
bearing damage because of dry running .
It is recommended the pick up ring be positioned on the side of the bearing nearest the
shaft end in plummer blocks having bearings with cylindrical bore.
The side cover with four recesses in the spigot should be place in the same side of housing as
the pick up ring .
The vent of oil level indicator must not be plugged as otherwise an air cushion in the sight
glass may lead to false reading . The actual oil level will be too high and oil will leak out of the
plummer block shaft passage.
Before starting up for the first time , the oil quantity quoted in the table should be put
into the housing . The maximum oil level guarantees lubrication of bearing when it starts
running before it can be supplied with the oil picked up by the ring . Thus the oil level should
be restored to maximum before starting up after long stoppage.
Even if the housing is carefully cleaned before use there is risk that some impurities will be
left. It is therefore advisable to change the oil after an initial trial running period of few
hours. Subsequent changes can the be made at convenient intervals but should be undertaken
at least once in a year. The bearing must be at a standstill when the oil is changed.
If , during the trial run no oil leaves the housing , a monthly check of the oil level should be
adequate.
During operation , the oil level may sink to the minimum level given in the tables . If oil is to
be added during operation , it should be filled to a level some 5 mm beneath the maximum oil
level on the indicator to avoid overfilling , since some oil will be in circulation .
A blind hole with an M24 thread plugged with a plastic stopper , is provided in the housing
cap. If required , a thermometer or the sensor of some other temperature measuring device
, may be inserted .The hole stops just short of bearing outer ring , so that it is possible to
measure the temperature in close proximity of the source of heat. A more rapid indication of
temperature change is obtained , would be possible by measuring the temperature of oil .
INLET DIMENSION
As refer to drawing
LIST OF SPARES
The following spare parts are recommended to be kept as stand by for two years normal
operating condition. Quantity of replacement depends on individual application.
MOTOR NDE.
BEARING
DO’S :
THE FAN.
4. CHECK FOR LOOSENESS OF ANY BOLTS IN THE FAN PEDESTALS AND CASING
ETC.
AND CHANGE THE OLD OIL. CHECK IF ANY DIRT OR DUST IS SETTLED INSIDE
DONT’S :
CONDITION.
ANNEX
BRIEF DESCRIPTION OF FAN COMPONENTS
THIS IS COMPRISING OF
IMPELLER,SHAFT,HUB, BEARING
8. ROTOR ASSEMBLY
&
BEARING HOUSING. IMPELLER
BLADES ARE BACKWARDCURVED
DESIGN.
ANNEX
MARKETING OFFICES
ADDRESS TEL. NO FAX NO
Ahmedabad 079 2287 6731
73, Sanskartirth Society, hiren.trivedi@flaktwoods.com
Arbudanagar Road, Odhav
Ahmedabad - 382415
Pune 020 5534442 020 2553
Masters Executive Center Pvt. m.khandke@flaktwoods.com 9079
Ltd. "Sneha
Leela"
1237 , Apte Road
Deccan Gymkhana
Pune - 411004
Mumbai 022 56978940-043 022
301-303, Chintamani Plaza kj.shah@flaktwoods.com 66978940
3rd Floor
Andheri Kurla Road , Chakla
Andheri(East)
Mumbai - 400093
Landmark : Opp. German
Remedies
New Delhi 011 2922 4405, 011 2209
Ront Portion, 011 2209 1357 1357
First Floor, Plot – 28, soumyajit.chakraborty@flaktwoods.com
Okhla Industrial Estate,
Phase – 3
New Delhi - 20
MANUFACTURING ACTIVITIES
Kolkata 033 24901811 033 24902411
P.O & Villa. Jalkhura
Maheshtala
Dist : South 24 Pgns.
West Bengal -700141
Chennai 044 26272216 044 26272606
Village : Numbal
110, Poonamalle High Road
Chennai - 6000077
INSTRUCTION MANUAL
UID NO.:FAN MANUAL/ Howden 2015
1.1. DESCRIPTION
IDENTIFICATION SHEET
FLAKT REFERENCE
REF. DRG. NO.
APPLICATION
CUSTOMER
FAN DESCRIPTION :-
MAIN CHARACTERISTICS
TOTAL EFFICIENCY %
RATED OPERATING TEMPERATURE °C
MECHANICAL DESIGN TEMPERATURE °C
FAN SPEED RPM
DENSITY AT 180 ° C Kg/AM³
CRITICAL SPEED RPM
RATED FAN POWER KW
MOTOR POWER KW
FAN WEIGHT KG
FAN ACESSORIES WEIGHT KG
MOTOR WEIGHT KG.
DYNAMIC LOAD DUE TO ROTOR KGF.
GD² VALUE kg.M²
IMPELLER DIA mm
IMPELLER WEIGHT KG.
DAMPER OPERATING FORCE N
ACTUATOR STROKE LENGTH mm
BEARING LUBRICATION
INSULATION AREA (M2) mm
SHAFT DIA AT BRG. mm