DURASI PROQUREMENT PROYEK NPK

Inquiry Manufacturing
Duration Shipment
No Name Start Finish & PO & Testing Remarks
(month) (month)
(month) (month)
II PROCUREMENT 9/May/19 07/Feb/21 21,33
i Civil 22/May/19 25/Sep/20 16,40
1 Concrete Spun Pile 13/Jun/19 31/Jan/20 7,73 0,20 7,03 0,87
2 Steel Pipe Pile 13/Jun/19 02/Oct/19 3,70 0,43 2,77 0,87
3 Concrete Material 22/May/19 25/Sep/20 16,40 0,20 16,37 162,67
4 Reinforcing Bar 22/May/19 27/Dec/19 7,30 2,10 4,63 47,00
5 Roofing & Siding 22/May/19 10/Jan/20 7,77 2,10 4,63 9,67
6 Steel Structure Material 3/Sep/19 02/Jul/20 10,10 1,83 7,30 9,00
7 Bolts & Nut 3/Sep/19 02/Jul/20 10,10 1,83 7,30 9,00
ii Mechanical 9/May/19 09/Oct/20 17,30
Long lead item,
1 Rotary Drum 23/May/19 21/Aug/20 15,20 0,70 12,47 1,97
critical equipment
Long lead item,
2 Crusher 20/Jul/19 21/Sep/20 14,30 0,97 12,30 0,97
critical equipment
Long lead item,
3 Vibrating Screen 9/May/19 03/Jun/20 13,03 0,43 11,30 1,23
propietary equipment
4 Weigh Feeder 14/Jun/19 10/Feb/20 8,03 0,97 4,97 2,03 Critical equipment
5 Pumps 22/Aug/19 19/Feb/20 6,03 0,97 4,03 0,97 Critical equipment
6 Fan & Blower 7/Jul/19 10/Jun/20 11,30 0,97 9,03 1,23 Critical equipment
Long lead item,
7 PN Reactor + Agitator 9/May/19 03/Jun/20 13,03 0,43 11,30 1,23
propierary equipment
8 Air Compressor 6/Jul/19 09/Jun/20 11,30 0,97 9,03 1,23 Critical equipment
9 Conveyor 28/May/19 22/Jun/20 13,03 0,70 11,03 2,23 Long lead item
10 Bucket Elevator 24/May/19 22/Jul/20 14,17 0,83 11,03 2,23 Long lead item
11 Heat Exchanger 15/Aug/19 19/Jul/20 11,30 0,97 9,30 0,97
12 Rubber Lining 15/Aug/19 12/May/20 9,03 0,97 7,03 0,97
13 Stack 22/Dec/19 28/Jun/20 6,30 1,03 4,23 0,97
14 Pressure Vessel 15/Aug/19 19/Jun/20 10,30 0,97 8,03 1,23
15 Bin & Hopper 22/Aug/19 24/Sep/20 13,30 0,97 10,30 1,97
16 Tank 15/Aug/19 12/May/20 9,03 0,97 6,03 1,97 Propietary equipment
Inquiry Manufacturing
Duration Shipment
No Name Start Finish & PO & Testing Remarks
(month) (month)
(month) (month)
17 HVAC and Ducting 2/Aug/19 29/Apr/20 9,03 0,97 7,03 0,97
18 Plumbing 12/Aug/19 24/Jan/20 5,50 0,97 4,03 0,43
19 Dehumidifier Package 29/Aug/19 16/Apr/20 7,70 0,97 4,70 1,97
20 Burner System 20/May/19 30/Jun/20 13,57 1,23 11,30 0,97 Long lead item
21 Dedusting Unit 18/Jul/19 10/Jun/20 10,93 0,60 9,03 1,23
22 Bagging & Palletizing System 17/Jul/19 14/Mar/20 8,03 0,97 6,03 0,97 Critical equipment
23 Ship Unloading Facility 24/May/19 02/Sep/20 15,57 1,23 12,30 1,97 Long lead item
24 Crane & Hoist 9/Sep/19 14/Jun/20 9,30 0,97 7,03 1,23
25 Weigh Bridge 8/Nov/19 07/May/20 6,03 0,97 4,03 0,97
Long lead item,
26 Ship Loader Recondition 7/Aug/19 09/Oct/20 14,30 0,97 12,30 0,97
critical equipment
27 Fire Fighting System 15/Aug/19 12/Apr/20 8,03 0,97 6,03 0,97
28 Mobile Mechanical Handling 30/Sep/19 03/Sep/20 11,30 0,97 9,30 0,97
iii Piping 11/Mar/20 07/Feb/21 11,10
1 Pipe 11/Mar/20 13/Dec/20 9,23 0,97 7,23 7,23
2 Fitting & Accessories 11/Mar/20 13/Dec/20 9,23 0,97 7,23 5,97
3 Valve 11/Jun/20 07/Feb/21 8,03 0,97 6,03 6,03
iv Electrical 17/Aug/19 21/Sep/20 13,37
1 Emergency Diesel Generator 17/Aug/19 15/Mar/20 7,03 0,97 5,03 0,97
2 Power Transformer 17/Aug/19 14/Apr/20 8,03 0,97 6,03 0,97
3 Medium Voltage Switchgear and MCC 19/Aug/19 16/Apr/20 8,03 0,97 6,03 0,97
4 Low Voltage Switchgear and MCC 19/Aug/19 16/Apr/20 8,03 0,97 6,03 0,97
5 Distribution & Lighting Panel 18/Sep/19 16/Apr/20 7,03 0,97 5,03 0,97
6 Electrical Cable Tray and Ladder 27/Sep/19 26/Mar/20 6,03 0,97 4,03 0,97
7 Cable and Wire 22/Aug/19 19/Apr/20 8,03 0,97 6,03 0,97
8 Grounding & Ligthning Protection 17/Oct/19 15/Apr/20 6,03 0,97 4,03 0,97
9 AC & DC UPS 31/Oct/19 05/Aug/20 9,30 0,97 7,30 0,97
10 Paging & Telephone 31/Oct/19 06/Jun/20 7,30 0,97 5,03 1,23
11 Fire Alarm System 17/Feb/20 22/Aug/20 6,23 0,97 4,23 0,97
12 Lighting Fixture 17/Feb/20 21/Sep/20 7,23 0,97 5,23 0,97
13 Electrical Bulk Material 17/Feb/20 22/Aug/20 6,23 0,97 4,23 0,97
14 Cathodic Protection 17/Feb/20 21/Sep/20 7,23 0,97 5,23 0,97
Inquiry Manufacturing
Duration Shipment
No Name Start Finish & PO & Testing Remarks
(month) (month)
(month) (month)
v Instrument 19/Aug/19 17/Sep/20 13,17
1 Control System 27/Aug/19 30/Aug/20 12,30 0,97 10,30 0,97 Critical equipment
2 CEMS 7/Oct/19 05/May/20 7,03 0,97 4,03 1,97
3 Field Instrument 30/Sep/19 05/Jul/20 9,30 0,97 7,30 0,97
4 CCTV 19/Aug/19 17/Mar/20 7,03 0,97 5,03 0,97
5 Control Valve 14/Oct/19 17/Sep/20 11,30 0,97 9,30 0,97
6 Instrument Cable 24/Oct/19 29/Jun/20 8,30 0,97 6,30 0,97
7 Instrument Cable Tray and Ladder 29/Dec/19 03/Jul/20 6,23 0,97 4,23 0,97
8 Wiring Acccessories 11/Jan/20 16/Jul/20 6,23 0,97 4,23 0,97
Keterangan:
yang tidak terdapat dalam list procurement adalah: Process Screen, Polishing Screen, Ammonia Sparger, Desupperheater dan DCS