1st Notice
1st Notice
Province of Sarangani
OFFICE OF THE PROVINCIAL ENGINEER
2nd Floor, James L. Chiongbian Building
Capitol Compound, Alabel
Telephone: (083) 508-2184
e-mail: peo@sarangani.gov.ph
Based on the approved PERT/CPM Network, the planned accomplishment is _1.08%_ % while
your Actual accomplishment is only _8.69_ %.
In view hereof, you are hereby directed to submit a detailed “catch-up” program on a
fortnightly (two weeks) basis to eliminate the slippage.
In the action program being required, specify therein the additional input resources such as
manpower, materials, equipment, and management to cope up and meet the desired result
accordingly.
JERRY E. BELBIDER
Provincial Engineer