Professional Documents
Culture Documents
Observations/GMP Compliance:
-
flipper intendend for specific lines marked with "holes" e.g. 1 hole for line 1, 2 for line 2
forth are not strictly followed due to not enough available flippers for turn over per line
left handed personnel.
- project contractors don't endorsed properly the used uniform after getting undressed at
room. Shirt and pants are put to cabin messily/untidy.
- advised to hold all WIP from 1st - 3rd shift, line 2, 9218DV code date, H- Level
-
revised sampling of MARS, 1st lot - 1 sample (25kg), following lots, every 2 lots e.g. 200
= 1 sample, 10 bags, 2010 -2029 = 1 sample ,20 bags ; if ever there are samples that hav
sample must be taken immediately then will follow sampling 1 sample/10 bagsuntil pass
proceed to 1 sample/20bags.
Dry Process
Line 1 - continuous milling
- H-Level Run ( Arasco) Conventional
- continue cordon of line 1 packing area
- separate "crocs" / slippers use inside the cordoned area
- will conduct trial manually for satake machine then proceed to trial run installed below r
machine
- conduct BLS Swab before installation.
Sprout Retrive :
Weight (kg)
PMO - 94
Line 1 - 16
Line 2 - 13
Total - 123
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
- hourly Test Run/passing of Metal Seeded Bags on Metal Detector , done
- No metal alarm bag ( Finished Goods)
VCO
- no operation
In - Process Rejections
Defect Weight in lbs
Process Related Defective (PRD) Line 1 Line 2 Line 3 Total
High Moisture 0
Low Moisture 0
Off Color 0
Off Sieve 0
Off Odor 0
High Paring Specks Count/Fiber 0
High Discolored Specks Count 152 707 859
Off Size 0
Bypassed due to Contamination 0
Bypassed sue to equipment breakdown 0
Sub - Total 152 0 707 859
100 lbs 0
25 Kg 18188 0 16920 35108
20 Kg 0 0 2821.9 2821.9
Weight in lbs
25 lbs 0 0 0 0
100 lbs 0 0 0 0
Total lbs 18188 0 19742
NCRS Contamination
- none
Metal Contamination
- none
- End -
h "holes" e.g. 1 hole for line 1, 2 for line 2 and so
gh available flippers for turn over per line and for
H - Level
Unsulfited Run
Date : 08/07/19
Code Date : 9219DV
Group : Eagle
Shif : 2nd
- Still cordon line 1 from picking line to packing area due (S+) .
Continues milling at 48 rpm with 10 rpm reprocessing. A left-over from outgoing shift (Team Eagle).
- All MARS sample fiber and specks count have passed
- Cut-off milling at around 10:16 PM.
Additional input:
- Since we have encouter (S+) at line 1. PSS discussed together with dry process leadman, Pqc-leadman and 3ps
supervisor in proper handling and execution of cleaning:
● First, before start cleaning at all equipments or touching of all equipments. Let's first fully clean and
sanitized all flooring at dry process area from line 1 to 4, picking line, packing line including MCC room,
hallway and decon area.
Metal Contamination
- None
Surge Tank
Line 1 - Already Drained
Line 2 - Already Drained
Grinder
Line 1 - Cut-off
Line 2 - 48 rpm w/ 10 rpm repro
Line 3 - 60 rpm (puremeat)
Warehouse
- hourly Test Run/passing of Metal Seeded Bags on Metal Detector , done
- No metal alarm bag ( Finished Goods) from left-over.
Line 1 - Still cordon line 1 from picking line to packing area due (S+) .
- continue remaining swab points. Done.
- start milling at around 5:15pm
- Swab for (S+) , jack pallete, macaroon and medium vibrox cover, motor medium, platform(medium and
macroon)
- Provide sample for sulfite.
Line 2 - No milling.
- Continues full welding activity on hopper after screw conveyor 1. Cleaning Port were made last shutdown
cleaning. Wealding build needed to be fixed and elimination of pin holes. ( Not Thoroughly
done, As advise activity to be continued next shutdown, done coordinate w/ Maam Fyne. )
- For turned-over to the next shift: Thorough cleaning and sanitation of screw and hopper affected during
welding activity. Swab to be made (both ATP and BLS after cleaning.)
Others:
Metal Contamination
- None
Surge Tank
Line 1 - Drained
Line 2 - Drained
Grinder
Line 1 - 46rpm
Line 2 - no milling
Line 3 - 60 rpm / 10 rpm repro
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
VCO
- No Operation/No personnel assigned
Date: - 08/05/19
Code Date - 9217DV
Group - Apo
Shif - 1st
PRE-START-UP ACTIVITY:
● Continues cleaning both dryer's Line 1, 2 and 3 using compressed air apecially at steam coils, stiffiners
and its structure and after used katsa rag to wipe all dc fines in every compartment. Including picking
line, packing line, mezzanine area, hallway and decon area.
● Conduct swab of buhler pipes including optical sorter of Line 2 and Line 3. After swab of buhler pipes,
there was an assigned personnel to install of buhler pipes.
● There was still working on Line 1 Rotex machine chute by Project Team. They were able to conduct
adjustment of Rotex Hopper. (All Rotex chute and hopper must be clean and sanitized since it was used
during there activity for adjustment and testing of rotex machine).
● Conduct checking and verification of cleaning in the line's form PMO area to Dry Process Area:
PMO - Area's are un-clean are pitbull mezzanine specially at overhead pipes and outside conveyor.
- Cobweb are still present specially below shelling bin and above surfaces like piping line.
- Also need for cleaning are crates, push cart and other structural areas.
WET - Trimming line (cross black belt conveyor) is unclean need for scrab of its surfaces.
- other equipment like inlcined screw conveyors, floater, decapping blade, surge tank are clean.
- Grinder area (distributing and sulfite screw conveyor including repro hopper are clean).
- All blancher (stage A and B) of both line's (1, 2 and 3) are need to scrab all surfaces of screw
and flight since there was brown in color that stick to it.
DRY - Unclean areas that need to be clean are Line 3 stage C1 and C2, Packing area (Line 1, 2 and
3) specially at weighing hopper, since there was a presence of dc fines.
Line 2 -
Continues milling at 48 rpm with 10 rpm reprocessing. A left-over from outgoing shift (Team Eagle).
- All MARS sample fiber and specks count have passed
- Cut-off milling at around 10:16 PM.
Line 3 - Continues milling at 60 rpm (pure meat). A left-over from outgoing shift (Team Eagle).
- Checked and inspect of primary and secondary blue belt conveyors:
Time of
Frequency of Status
Checking
checking
- Start 10:05 PM ok
- Cut-off milling at 10:17 PM.
Additional input:
- Since we have encouter (S+) at line 1. PSS discussed together with dry process leadman, Pqc-leadman and 3ps
supervisor in proper handling and execution of cleaning:
● First, before start cleaning at all equipments or touching of all equipments. Let's first fully clean and
sanitized all flooring at dry process area from line 1 to 4, picking line, packing line including MCC room,
hallway and decon area.
Metal Contamination
- None
1st Cleaning Acitvity:
- Partial cleaning at dryer's line 1, 2 and 3.
- Partial cleaning of picking line and packing line.
- Remove all Generated WIP at dry process and transfer to wet area (grinder).
- Transfer all pallet at wet area for wet wash.
- Not all equipments, detachables and perforated baffles are transfer to wet area.
Wet Process Area
Grinder
Line 1 - Cut-off
Line 2 - 48 rpm w/ 10 rpm repro
Line 3 - 60 rpm (puremeat)
Warehouse
VCO
- No Operation/No personnel assigned
- Check and inspect VCO lines, still there was a accumulted fines at collecting tank, need for intensive
cleaning.
Date: - 08/03/19
Code Date - 9215DV
Group - Eagle
Shift - 3rd
Finished Good Sieve Testing : All samples are within specified limit
NCRS Contamination
- Negative of Non-coconut related specks with the shift.
Metal Contamination
- none
Grinder
Line 1 - 46 rpm w/ 16 rpm repro
Line 2 - 48 rpm w/ 10 rpm repro
Line 3 - 60 rpm (puremeat)
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
VCO
- No Operation
Date: - 08/03/19
Code Date - 9215
Group - Apo
Shift - 2nd
Dry Process
Finished Good Sieve Testing : All samples are within specified limit
NCRS Contamination
- black rubber found at picking table line 1
- bypass all materials and labeled accordingly
Metal Contamination
- none
Wet Process
Grinder
Line 1 - 46 rpm w/ 16 rpm repro
Line 2 - 48 rpm ,10 - 12 rpm
Line 3 - 60 rpm, 10 repro rpm
Sprout Retrive :
Weight (kg)
Line 1 - 15.0
Line 2 - 5.0
Total - 20.0
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
VCO
- no Operation
- continuous cleaning
-
-
-
Date: - 08/03/19
Code Date - 9215 DV
Group - Durian
Shift - 1st
Dry Process
Finished Good Sieve Testing : All samples are within specified limit
NCRS Contamination
- none
Metal Contamination
- none
Wet Process
Grinder
Line 1 - 46 rpm w/ 16 rpm repro
Line 2 - 48 rpm , with 16 repro rpm.
Line 3 - 60 rpm puremeat
Sprout Retrive :
Weight (kg)
Line 1 - 18.0
Line 2 - 3.0
Total - 21.0
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
- hourly Test Run/passing of Metal Seeded Bags on Metal Detector , verified, done
- No metal alarm bag ( Finished Goods produced w/in the shift)
VCO
- No Operation/No activity
Date: - 08/02/19
Code Date - 9214 DV
Group - Eagle
Shift - 3rd
Dry Process
Finished Good Sieve Testing : All samples are within specified limit
NCRS Contamination
- none
Metal Contamination
- none
Wet Process
Grinder
Line 1 - 46 rpm w/ 16 rpm repro
Line 2 - 48 rpm , with 16 repro rpm.
Line 3 - 60 rpm, 10 repro rpm
Sprout Retrive :
Weight (kg)
Line 1 - 5.0
Line 2 - 10.0
Total - 15.0
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
- hourly Test Run/passing of Metal Seeded Bags on Metal Detector , verified, done
- No metal alarm bag ( Finished Goods)
VCO
- No Operation/No activity
Sulfite Screw,
k, Unsulfited Run
Date: - 08/02/19
Code Date - 9214 DV
Group - Apo
Shift - 2nd
Dry Process
Finished Good Sieve Testing : All samples are within specified limit
NCRS Contamination
- none
Metal Contamination
- none
Wet Process
Grinder
Line 1 - 46 rpm w/ 16 rpm repro
Line 2 - 48 rpm ,pure meat
Line 3 - 60 rpm, 10 repro rpm
Sprout Retrive :
Weight (kg)
Line 1 - 20.0
Line 2 - 4.0
Total - 24.0
Blancher 1,2,3
- No abnormalities, All parameters are within specified limit
Warehouse
VCO
- No Operation , oil present at storage tanks and at sweco
- conduct cleaning at around 8:00 am ,
- no manning from SP's
- cleaning done by FTE
- filter cloth not installed
Date: - 08/02/19
Code Date - 9214 DV
Group - Durian
Shift - 1st
Dry Process
Optical Sorter
Line 1 Satake - Not used w/in the shift
Line 2 Sortex - Operational /56.25% on % rejection test
Line 3 Sortex - Operational /55.17% on % rejection test
Finished Good Sieve Testing : All samples are within specified limit
NCRS Contamination
- none
Wet Process
Surge Tank Drained Water every 4 hours
Line 1 - done
Line 2 - done
Grinder
Line 1 - 46 rpm w/ 16 rpm repro
Line 2 - 48 rpm , 16 repro rpm
Line 3 - 60 rpm, 10 repro rpm
Warehouse
Dry Process
Line 1 -
- excessive spillages below Satake Machines
- 2:40pm up to 5:15pm , off specks Macaroon, (about 975 lbs were bypassed)
- no picking table at medium but assigned picker at the satake chute going to screw
- both Satake malfunctioned w/in the shift ( a total of 4,240 lbs of bypassed materials)
- uninstall Satake of Medium and Macaroon and picking table were used
- change process run from Unsulfited to H-Level ( Ferrero to Arasco Run)
- Provide Sulfite Sample
Line 2 -
- 2:50 pm , cut-off milling due to problem at Grinder Area
- Resume milling at around 4:55pm
- MARS Fiber and Specks Count Testing Per lot= All Lot passed
- Provide Sulfite Sample
-
Line 3 -
- continuous milling
- encountered trouble at horizontal screw, clogging of dc materials ( 1,638 lbs were bypassed)
- blue conveyor checking
7:30 PM ok
9:20PM ok
- Cleaning on Line 3, at 4:50pm
Change of Rotex Screens(L3) Insalled Screens, #6, 11, 12, 14 and 20 ( Autoclaved: 7/28/2019)
Change of Apron Brush on Line3 ( Autoclaved: 7/28/2019)
NCRS Contamination
- none
Wet Process
Surge Tank Drained Water every 4 hours
Line 1 - done
Line 2 - done
Grinder
Line 1 - 46 rpm , pure meat
Line 2 - 48 rpm , 16 repro rpm
- experienced overflowing of ground materials at the end part of sulfite screw near chute.
cut-off milling to fixed problem then resume milling.
Line 3 - 60 rpm, 10 repro rpm
Warehouse
oclaved: 7/28/2019)
w near chute.
Date: - 08/01/19
Code Date - 9213DV
Group - APO
Shift - 2nd
Dry Process
NCRS Contamination
- none
Wet Process
Sprout retrieved
Line 1 - 28 kg
Line 2 - 3 kg
VCO