You are on page 1of 2

SCHEDULE OF CHARGES

Security Deposit Charges (Refundable)


1 2 3
S. No. Tariff Category (As per tariff order) Amount (Rs. per KW/KVA)
1 Domestic
(i) Upto 2 KW 600
(ii) Above 2 KW upto 5 KW 900
(iii) Above 5 KW 1200
2 Non-domestic 4500
3 Industrial 4500
4 Agriculture 300
5 Public Lighting 3000
6 Railway, DMRC, DIAL, DJB 3000
7 Mushroom Cultivation 600
8 Advertisement and Hoardings 4500
9 Charging stations for E-Rickshaw/ E-Vehicles 2500
10 Any other category not specified above To be decided by the Commission

Note: As per the directive of Govt. of India, GST @ 18% will be levied on all Non-Energy charges.

Service Line Cum Development Charges (Non - Refundable)


(1) (2) (3) (4) (5) (6)

S. Additional Total
Type of Area Sanctioned Load SLD Amount (Rs.)
No. Charges Amount

(i) upto 5 KW 3000 4+5

(3000 + 500 per kW or per kVA as


More than 5 kW and upto the case may be for load beyond
(ii) 4+5
Electrified 150 kW 5kW), limited to a maximum of
Area 25,000 a) Actual
Road
25,000 + 400 per kW or per kVA Restoration
More than 150kW to
(iii) as the case may be for load charges for 4+5
200kW/ 215kVA
beyond 150kW service line
Load upto 4kW, other than
(i) 8000 per kW 4+5
agriculture connection

Load above 4kW and upto b) GST @


(ii) 10kW, other than agriculture 12,000 per kW 18% on 4+5
connection Column No.
Unelectrified 4 & 5(a)
Area as on Load above 10kW and upto except
20,000 per kW or per kVA as the
31.7.2017* (iii) 200 kW/215 kVA, other than Agriculture 4+5
case may be
agriculture connection Connection
20% charges per kW for
respective slab of load mentioned
(iv) Agriculture connection 4+5(a)
at point (i), (ii) &(iii) of
Unelectrified area
OTHER CHARGES (WHEREVER APPLICABLE)

1 2 3 4 5 6
Total
S. No. Type Description Charges (Rs.) GST @ 18%
Charges (Rs.)

(i) Single phase connection 500 90 590


1 Meter Shifting Charges
(ii) Three phase connection 1000 180 1180

(i) Upto 5 KW 120 22 142


Installation Inspection (ii) More than 5 KW upto 10
Fee other than at the 36 236
2 KW 200
time of energising new
(iii) More than 10 KW 400 72 472
connection
(iv) HT Installation 1000 180 1180

Special Meter Reading (i) LT connection 50 9 59


3
Charges 36 236
(ii) HT connection 200

(i) Single phase connection 200 36 236


4 Reconnection Charges
(ii) Three phase connection 500 90 590

(i) Single phase 200 36 236

(ii) Three phase 500 90 590


5 Meter Testing Charges
(iii) CT meter 1000 180 1180

(iv) HT meter 4000 720 4720


250 per KW or
per KVA subject
One time non- (i) LT Supply GST @ 18%
to a maximum of
6 refundable charges for on Column 4+5
Rs. 25,000/-
Temporary Connections No. 4
1000 per KW or
(ii) HT Supply
per KVA
7 Dishonored Cheque 200 36 236
Non-refundable
registration cum
8 1000 180 1180
processing fee of EHT
and HT connections
Field inspection to be
9 scheduled on a holiday 500 90 590
for the Licensee
10 Copy of per Duplicate Bill 20 4 24