ID Task Name Duration Month 2 Month 3 Month 4 Mont

W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15


1 RENOVATION OF GUBIO II PRIMARY SCHOOL, GUBIO LGA, 75 days
BORNO STATE

2 SITE MOBILISATION AND DEMOBILISATION 5 days

3 SITE LAYOUT 5 days

4 BLOCK I 18 days

14 BLOCK II 18 days

24 BLOCK III 24 days

35 BLOCK IV 17 days

45 BLOCK V 24 days

56 BLOCK VI 25 days

67 BLOCK VII 17 days

77 BLOCK VIII 25 days

88 BLOCK IX 19 days

98 SITE CLEANING 4 days

99 SITE HAND OVER 1 day