You are on page 1of 7

BAM Netley School Development

Method Statement

1 Method Statement

Installation of
Structural Steel for
Contractor Koyda Steel Works to be
carried out
the sports hall at
Netley School
Development
Units 1-3 44A Gloucester Road, Croydon,
Surrey, CR02DA

Method statement
BAM/NSD/01 Revision no. 01
No.
Date 12/08/13 Package No N/A
Title Installation of Structural Steel for the sports hall

2 Description
Location of Work Sports Hall Slab
Start Date 22/08/2013 Duration 8 days
Sequence Of Work
Operatives to be booked in prior to the works taking place
Delivery arrives at the main entrance via HIAB lorry
Materials to be offloaded using the HIAB and lifted using the site crane if feasible on to the slab
Alternatively the steel will be boomed up using a sufficient HIAB

A cordoned area will be set up around the slab whilst erection is taking place
The works will be carried out in normal working hours

Description & Method of Work


Operatives will attend a site briefing with the KOYDA Manager to receive the BAM induction, a Method Statement
briefing and a daily safe start to highlight the risks surrounding the work areas.

The delivery will arrive at the main entrance and will be off loaded and materials and tools will be taken to the work
area.
The operatives will cordon off the immediate work area when lifting is taking place and a Koyda operative will patrol
this exclusion zone.

Lifting will take place using a mobile spider crane, which will be lifted in to position using the BAM site crane. This will
be used to erect the remainder of the steelwork.

The positions and loads applied by the outriggers of the crane will be marked up on a drawing and then transferred to
site using a spray mark. This will then denote the position of the back propping by others. In order to establish the
capacity of the slab we will require information from BAM.

Roof steels will be delivered to site and craned up on to slab. These sections will then be manoeuvred on the slab to
the appropriate lifting site for the erection. Once positioned the crane will be tracked into position and the steel will be
slung by the banks man ready for lifting.

Review Revision No Review Date Revision No


Date
KOYDA 12/08/2013 01 Installing stair
MetalWorkers panels
T1.7 Method statement format Page 1 of 7
BAM Netley School Development
The erectors will be operating from the MEWP at each fixing position and will wait for the lifting of the steel. Once the
erectors are secure and ready to fix the signal will be given to the banks man in this case verbally, visually and using
the appropriate hand signals.

Once ready the banks man will take the strain of the load to insure that it is secure under load and proceed with the
lift, gently manoeuvring the steel into position.

The erectors will use podgers and spanners followed by a nut runner (110V) to secure the bolts.

The remainder of the steel will be installed using the same methods until the structure is complete and ready for the
installation of the Rib Deck.

The rib deck pallets will be slung from the lorry using 2 1 ton slings and taken directly to the slab. The Spider crane
will lift the sheets onto the appropriate positions and operatives will access the decking using MEWP’s Safety netting
will also be used to protect agenised falling from heights
The shear studs will be installed using the appropriate welding equipment from on top of the rib decking and all edges
will be protected using span sets. Operatives will be attached to the span sets locally to their work area to provide a
secondary means of fall arrest.
Once the decking is complete and after every shift operatives will insure that the working area is left clear and tidy and
safe for other operatives to work in.

Following the completion, the sign off process will take place and bolts will be checked for correct torque and paint
touched up. These sheets will be made available to BAM for their signoff process.

Review Revision No Review Date Revision No


Date
KOYDA 12/08/2013 01 Installing stair
MetalWorkers panels
T1.7 Method statement format Page 2 of 7
BAM Netley School Development
3 Resources
Name of Supervisor in Charge: Atilla Kuti Number of Persons: 2
Method statements Method statements
4 Risk Assessment
List any Subcontractors to be used approved? attached?
Hazard Identification Yes No Hazard Identification
Yes No Yes
Yes No
No
No
SlipsSubcontractors
and Trips to be used for this
YES operation COSHH NO
Manual handling
Materials and Equipment to be used: YES Noise YES
Hand tools YES Work at Height YES
Materials
Excavations NO Structural
Dust/Fumes steel beams and columns YES
Machinery/Lifting equipment YES Rib deck sections
Lighting
Fire 3rd party (Contractor) NO
Fall of material YES HAVS YES
Equipment
Electrical NO Welders
Use of Lasers YES
Who might beMEWP
harmed? x2
Yes No UNIC spider crane Yes No
Own Personnel YES Office Staff or Visitors YES
Other Contractors YES
Tools
Members of the Public NO
Potential severity of injury or illness First Aid Leads
Reportable Major Disablement Fatal

Number of workers
Equipment exposed to hazard
To Be Used 1 2–5 6 – 20 Yes21 – 100 100 +
Lifting NO Equipment To Be Used Yes No
Probability ofhoist
Mechanical injury or illness Happens
YES Happens Each
Cradle Happens On Most Happens Certain
NO To
Mobile elevating working platform Rarely
YES Year Excavation shoring
Jobs Regularly Happen
NO
Ladder NO Mechanical tools YES
Hoist Overall Assessment Of Risk Prior YES To The Implementation
Lasers Of Control MeasuresYES (Tick One)
Test Equipment Low Moderate NO CAT Substantial High NO
Task Lighting NO Ventilation/Extraction Equipment NO
Scaffolding NO Excavation shoring NO
Mobile scaffolds YES Lifting slings/chains YES

Review Revision No Review Date Revision No


Date
KOYDA 12/08/2013 01 Installing stair
MetalWorkers panels
T1.7 Method statement format Page 3 of 7
BAM Netley School Development

5 Proposed Control Measures to Reduce the Risks


Slips trips and falls: ensure that all areas of work are clear from debris prior to carrying out the task

Manual handling: All components are to be kept to a minimum weight and the correct number of operatives to Spread the Load on
heavier items it is preferred that no operative singularly lifts more than 25kgs.
Working At Heights and Fall of Materials: ensure that operatives are briefed on the use of scaffolds and access towers. Ensure
all towers are erected properly and used in accordance with the manufactures guidelines. If it is appropriate an exclusion zone to be
used below the work area. Tower to be erected by PASMA certified operatives only.
Use of Hand Tools: All hand held equipment is to be kept within the toe board and edge protection. Hand Arm vibration limits are to
be adhered to and recorded if necessary.
Fire: All operatives are to receive an induction and will be familiar with the fire evacuation procedure a Hot work Permit must be in
place prior to commencement of any hot works taking place NOT FOR THIS TASK
COSHH: NOT FOR THIS TASK
Noise: All operatives will wear ear protection when drilling. Or when close to a drilling operation. NOT FOR THIS TASK
Scaffold: All operatives involved in aluminium tower erection must be PASMA trained.
Dust: All operatives will use a dust mask whilst drilling or close to a drilling operation.
Machinery and lifting equipment: All lifting equipment must be tagged and inspected, do not use equipment, which is no identified
in this method statement.
Only trained riggers and erectors to use this lifting equipment
Do not use faulty equipment
Only use lifting equipment for the purpose it was intended for in this method statement.
Lifting frames must be fitted correctly and all safety pins must be checked prior to use. NOT FOR THIS TASK

HAVS: All drills must appear within the HAVS approved list of equipment, operatives must use low vibration gloves when drilling,
operatives must not drill for more than 1 min at any one time. A break of 2 min is suggested between intervals. Where possible take
it in turns to drill
Permits Required Assessments Required
Yes No Yes No
Hot works NO COSHH NO
Crane check list NO Noise NO
Excavation NO Manual handling YES
Confined space entry NO Other (state) NO
Riser shafts NO
Further Control Measures / Security Requirements.
Ensure operatives are fully inducted on to the Project and are current CSCS holders to the correct level for their trade

Ensure management have relevant SMSTS, SSSTS, or NVQ3 Qualifications

Training Certificates Required


Yes No Yes No
Scaffold NO Mobile Elevating Platform NO
Forklift NO Mobile Access Towers NO
Dumper NO Banksman NO
Excavator NO Abrasive Wheels NO
Others (Please state):None anticipated for the survey
Overall Assessment of Risk after the Implementation of Control Measures (tick one)
Low Moderate Substantial High

6 Personal Protective Equipment Yes No Yes No


Safety Helmet YES Gloves YES
Protective Footwear YES Hearing Protection NO
High Visibility Clothing YES Overalls YES

Review Revision No Review Date Revision No


Date
KOYDA 12/08/2013 01 Installing stair
MetalWorkers panels
T1.7 Method statement format Page 4 of 7
BAM Netley School Development
Eye protection YES Body Harness NO
Face Respirator NO Other? NO

Review Revision No Review Date Revision No


Date
KOYDA 12/08/2013 01 Installing stair
MetalWorkers panels
T1.7 Method statement format Page 5 of 7
BAM Netley School Development

7 Emergency Arrangements
First Aid Measures Required Rescue / Security Measures Required

In the event of an incident operatives must seek first aid Rescue / Security measures are as per the BAM safety
from the KOYDA Metalworkers first aider; if more and logistic plans
severe the BAM Nurse will be available for
Rescue Spillage control requirements
By whom No task specific rescue plan is required for There are no environmental hazards associated to this
this operation task

Review Revision No Review Date Revision No


Date
KOYDA 12/08/2013 01 Installing stair
MetalWorkers panels
T1.7 Method statement format Page 6 of 7
BAM PHF

8 Any Amendments to Current Systems


Traffic routes Yes No
Emergency arrangements Yes No
Existing systems of work Yes No
Other Yes No

9 Contractor Information control


Method statement checked by Martin Sweeney
Method Statement review date Revision no. 001
Who is authorised to update / amend Joe KOYDA or Martin Sweeney
the Method Statement and under what
circumstances.
Confirmation of briefing from Persons Carrying out the Work
Print Name Signature Date

1 Contractor monitoring & compliance


0
Who is accountable for monitoring compliance with the method
Martin Sweeney
statement?
Will any test / sampling requirements impose compliance standards? Yes No NO
If Yes who will carry them out and with
what equipment?

Signature of Contractor Print Date


Martin Sweeney Joe Cromwell 20/08/2013

Review Date Revision No Review Date Revision No


KOYDA 26/11/12 01 Installing Stair
Metalworker Panels
s
T1.7 Method statement format Page 7 of 7