OMAHKU.ID

ANALISA HARGA SATUAN BAHAN DAN UPAH

NO. JENIS PEKERJAAN KOEF. SAT. HARGA JUMLAH HARGA SAT.


(Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7)

1 1 m2 Pasang rangka dinding sepandek


a. Bahan
- hollow 4/4 0.4000 m2 76,000.00 30,400.00
- hollow 2/2 0.2500 btg 50,666.67 12,666.67
- alat las 1.0000 ls 15,000.00 15,000.00
- screw driver 1.0000 bh 2,500.00 2,500.00
60,566.67
b. Tenaga
- Tukang Besi 0.2600 org/hr 115,000.00 29,900.00
- Mandor 0.1000 org/hr 150,000.00 15,000.00
44,900.00
1 m2 Pasang rangka dinding sepandek Sub Total 105,466.67

2 1 m2 Pasang dinding sepandek


a. Bahan
- Atap spandek 0.2800 m2 235,000.00 65,800.00
- cat minyak 0.3000 klg 80,000.00 24,000.00
- screw driver 1.0000 bh 2,500.00 2,500.00
92,300.00
b. Tenaga
- Tukang Besi 0.2600 org/hr 115,000.00 29,900.00
- Mandor 0.1000 org/hr 150,000.00 15,000.00
44,900.00
1 m2 Pasang dinding sepandek Sub Total 137,200.00

3 1 m2 Pas. Batako, 1 Pc : 3 Ps
a. Bahan
- Batako 14x28x7 cm 23.0000 bh 2,000.00 46,000.00
- Semen / Pc 0.0850 zak 60,000.00 5,100.00
- Pasir pasang 0.0185 m3 250,000.00 4,625.00
55,725.00
b. Tenaga
- Pekerja 0.8500 org/hr 115,000.00 97,750.00
- Mandor 0.2200 org/hr 150,000.00 33,000.00
130,750.00
1 m2 Pas. Batako, 1 Pc : 3 Ps Sub Total 186,475.00

4 1 m2 Pas. Bata merah


a. Bahan
- bata merah 85.0000 bh 900.00 76,500.00
- Semen / Pc 0.1500 zak 60,000.00 9,000.00
- Pasir pasang 0.0485 m3 250,000.00 12,125.00
97,625.00
b. Tenaga
- Pekerja 0.5500 org/hr 115,000.00 63,250.00
- Mandor 0.3200 org/hr 150,000.00 48,000.00
111,250.00
1 m2 Pas. Bata merah Sub Total 208,875.00


OMAHKU.ID

ANALISA HARGA SATUAN BAHAN DAN UPAH

NO. JENIS PEKERJAAN KOEF. SAT. HARGA JUMLAH HARGA SAT.


(Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7)

5 1 m2 Pasang rangka dinding GRC


a. Bahan
- hollow 4/4 0.3000 m2 76,000.00 22,800.00
- hollow 2/2 0.2500 btg 50,666.67 12,666.67
- alat las 1.0000 ls 15,000.00 15,000.00
- screw driver 1.0000 bh 2,500.00 2,500.00
52,966.67
b. Tenaga
- Tukang Besi 0.2000 org/hr 115,000.00 23,000.00
- Mandor 0.1000 org/hr 150,000.00 15,000.00
38,000.00
1 m2 Pasang rangka dinding GRC Sub Total 90,966.67

6 1 m2 Pasang dinding GRC


a. Bahan
- GRC 0.9000 m2 56,000.00 50,400.00
- cat dinding 0.3000 klg 156,000.00 46,800.00
- screw driver 1.0000 bh 2,500.00 2,500.00
99,700.00
b. Tenaga
- Tukang Besi 0.2000 org/hr 115,000.00 23,000.00
- Mandor 0.1000 org/hr 150,000.00 15,000.00
38,000.00
1 m2 Pasang dinding GRC Sub Total 137,700.00

7 1 m2 Pasang rangka pintu


a. Bahan
- hollow 2/2 0.4000 btg 50,666.67 20,266.67
- alat las 1.0000 ls 15,000.00 15,000.00
- screw driver 1.0000 bh 2,500.00 2,500.00
37,766.67
b. Tenaga
- Tukang Besi 0.4000 org/hr 115,000.00 46,000.00
- Mandor 0.1000 org/hr 150,000.00 15,000.00
61,000.00
1 m2 Pasang rangka pintu Sub Total 98,766.67

8 1 m2 Pasang plat pintu


a. Bahan
- plat pintu 0.5000 btg 175,000.00 87,500.00
- cat minyak 0.4000 klg 80,000.00 32,000.00
- screw driver 1.0000 bh 2,500.00 2,500.00
122,000.00
b. Tenaga
- Tukang Besi 0.5000 org/hr 115,000.00 57,500.00
- Mandor 0.1000 org/hr 150,000.00 15,000.00
72,500.00
1 m2 Pasang plat pintu Sub Total 194,500.00


OMAHKU.ID

ANALISA HARGA SATUAN BAHAN DAN UPAH

NO. JENIS PEKERJAAN KOEF. SAT. HARGA JUMLAH HARGA SAT.


(Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7)

9 1 m2 Pas. Batako, 1 Pc : 3 Ps + rabat


a. Bahan
- Batako 12.0000 bh 2,000.00 24,000.00
- Semen / Pc 2.5000 zak 70,000.00 175,000.00
- Pasir pasang 0.8000 m3 300,000.00 240,000.00
439,000.00
b. Tenaga
- Pekerja 0.4500 org/hr 90,000.00 40,500.00
- Tukang batu 0.1000 org/hr 115,000.00 11,500.00
- Kepala tukang 0.0100 org/hr 120,000.00 1,200.00
- Mandor 0.0150 org/hr 150,000.00 2,250.00
55,450.00
1 m2 Pas. Batako, 1 Pc : 3 Ps + rabat Sub Total 494,450.00

10 1 m2 Pasang hollow
a. Bahan
- Rangka hollow 2/2 0.2000 m1 235,000.00 47,000.00
- Cat 0.1000 m1 75,000.00 7,500.00
- alat bantu 1.0000 ls 2,500.00 2,500.00
57,000.00
b. Tenaga
- Tukang Besi 0.3000 org/hr 115,000.00 34,500.00
- Mandor 0.0500 org/hr 150,000.00 7,500.00
42,000.00
1 m2 Pasangan rangka hollow Sub Total 99,000.00

11 1 m2 Pasang atap sepandek


a. Bahan
- Atap spandek P = 2m 1.1000 m2 125,000.00 137,500.00
- Rangka hollow 5/5 0.2000 m2 39,000.00 7,800.00
- screw driver 1.0000 bh 2,500.00 2,500.00
147,800.00
b. Tenaga
- Tukang Besi 0.3000 org/hr 115,000.00 34,500.00
- Mandor 0.0500 org/hr 150,000.00 7,500.00
42,000.00
1 m2 Pasangan atap spandek Sub Total 189,800.00

11 1 m2 Pasang atap polycarbonate


a. Bahan
- Atap poly carbonat 1.1000 m2 125,000.00 137,500.00
- Rangka hollow 5/5 0.2000 m2 39,000.00 7,800.00
- screw driver 1.0000 bh 2,500.00 2,500.00
147,800.00
b. Tenaga
- Tukang Besi 0.6000 org/hr 115,000.00 69,000.00
- Mandor 0.0500 org/hr 150,000.00 7,500.00
76,500.00
1 m2 Pasangan atap spandek Sub Total 224,300.00
RENCANA ANGGARAN BIAYA
PENAWARAN ASESORIS IDES CAFE
SAMARINDA, KALIMANTAN TIMUR

HARGA SAT. JML HARGA TOTAL


NO URAIAN PEKERJAAN VOLUME
( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6
I. PEKERJAAN ASESORIS
1 pek. chain flag + ongkos pasang area smd 1.00 m1 28,000.00 28,000.00
2 pek. standing shop sign + ongkos pasang area smd 1.00 m2 1,650,000.00 1,650,000.00
3 pek. neon box almunium + ongkos pasang area smd 1.00 m2 887,000.00 887,000.00
JUMLAH 2,565,000.00
TOTAL JUMLAH 2,565,000.00

OMAHKU.ID

DI BUAT OLEH :

YUDHO ASTANTO
ENGINEER OMAHKU.ID