OMAHKU.ID
3 1 m2 Pas. Batako, 1 Pc : 3 Ps
a. Bahan
- Batako 14x28x7 cm 23.0000 bh 2,000.00 46,000.00
- Semen / Pc 0.0850 zak 60,000.00 5,100.00
- Pasir pasang 0.0185 m3 250,000.00 4,625.00
55,725.00
b. Tenaga
- Pekerja 0.8500 org/hr 115,000.00 97,750.00
- Mandor 0.2200 org/hr 150,000.00 33,000.00
130,750.00
1 m2 Pas. Batako, 1 Pc : 3 Ps Sub Total 186,475.00
OMAHKU.ID
OMAHKU.ID
10 1 m2 Pasang hollow
a. Bahan
- Rangka hollow 2/2 0.2000 m1 235,000.00 47,000.00
- Cat 0.1000 m1 75,000.00 7,500.00
- alat bantu 1.0000 ls 2,500.00 2,500.00
57,000.00
b. Tenaga
- Tukang Besi 0.3000 org/hr 115,000.00 34,500.00
- Mandor 0.0500 org/hr 150,000.00 7,500.00
42,000.00
1 m2 Pasangan rangka hollow Sub Total 99,000.00
OMAHKU.ID
DI BUAT OLEH :
YUDHO ASTANTO
ENGINEER OMAHKU.ID