Professional Documents
Culture Documents
3.3.2 Planning
A proper planning means planning before, during and after survey work such as software
configuration, hardware and equipment and fieldwork planning. The specification of this work
include six control point for first order, 22 control points for second order, two benchmarks
(BM) and two CORS points.
3.3.3 First Order Control Point
6 CPs
Hz: 2cm
3 sessions
V: 4cm
observation
H: 5cm
1st Order
Control
Point
2 CORS
1 hour station and 2
BM
Static
method
Figure about show the criteria of first order control point. For this first order control point, it is
consist of six control points (6CPs). The control points were established on right and left side
of the road for each 2.5km section route. The point have been establish within 5km distance
of road which is start 0km for first and second control point and end 5km for fifth and sixth
control point. These points were established with distance approximately 300m from centre
of road. There are three sessions of observation that have been done to create the
independent baseline. All the observation doing is connecting with base and the base was
connected to two CORS station and 2 benchmark (BM) for control all the observation work.
The observation was static method with 1 hour observation but more than 2 hours
observation for base point. Then, the required accuracy for this task are 2cm for horizontal
(Hz), 4cm for vertical (V) and 5cm for orthometric height (H). The equipment for observation
work consists of Trimble R4, Trimble R6, CHCNAV and Topcon GR5. The observation data
from receivers had been stored and downloaded after all observation was finished. The data
were process by using Trimble Business Centre (TBC) software. Then, the result is
analyzed.
Guidelines
Procedure Observation
22 CPs
15
minutes
For this second order control point, it is consist of 22 control points (22CPs). The control
points were established close to existing road for each 500m section route. Each section
needs 2 control points and situated on line more than 75m each other. The observation was
used fast static method with 15 minutes observation. The observation was observed more
than 3 hour as a base. Then, the required accuracy for this task are 3cm for horizontal (Hz),
6cm for vertical (V) and 8cm for orthometric height (H). The observation data from receivers
had been stored and downloaded after all observation was finished. The data were process
by using Trimble Business Centre (TBC) software. Then, the result is analyzed. Below show
the guidelines and procedure of second order control point observation.
Guideline
i. Receivers were set up at 22 control points. The control points had been chosen
based on the sky visibility more than 90% and cut-off angle at least 15°.
ii. Six receivers were used. Two receivers used at the same time at different control
point but move to the next point differently each other with overlay in between 5
to 10 minutes.
iii. The receivers were connected to smartphone via Trimble DL software for Trimble
and CHCNAV instruments its connected to controller via Bluetooth.
iv. Antenna height, measurement method, logging interval, elevation mask, PDOP
warning, measurement timers, point name and code and measured to had been
set in the controller before the observation started.
v. The log file name of the observation was recorded manually in observation form
for checking purpose.
vi. The data had been stored and downloaded after the observation finished.
vii. Trimble Business Centre (TBC) software had been used to process the data.