Professional Documents
Culture Documents
REPORT NO:
TSL/KLNR/STL/BACKUP_01
DATE:18/06/2019
Prepared By:
Sayantan Dutta
Checked By:
Partha Pratim Singha Roy
Contents of this report are the property of RHI MAGNESITA and should not be
reproduced, published or used in any way without the permission of RHI
MAGNESITA.
Steel Ladle Backup Shot Casting
Objective
Lower the time consumption and engagement of labour
Uninterrupted process to avoid defects like cracks , cavity formation , bulging etc.
Lower the surface temperature of ladle shell /Energy Saving
Targeted time to execute the shot casting within 120 hours
Background
To resist high service temperature and improving the durability of the ladle , a backup monolithic casting is
done . Initially insulation backup was done with Low Cement 70% Alumina castable (hydraulic bond) by
the process of vibration casting. The process was converted into short working schedule by the use of
pumpable castable (batch mix prepared in shotcrete machine). The working schedule of 132 hours was
reduced to 96 hours.
Issues with casting method with LC 70 LI
1. After the preparation of the mix , it is collected in the bucket and transferred & poured in the
formwork with the help of EOT crane. Total duration for completing the cycle of a single batch mix
(300 kg at a time) will be 12-15 minutes and more.
2. As there is no feeding as well as discharging system additional manpower required for feeding the
castable into the pan mixer and collecting the mix into the bucket from discharge end. Manpower is
engaged even for pouring of the mix into formwork
3. As LC 70 LI doesn’t have good flow-ability , therefore during the transfer of the mix & pouring , it
get solidify for quick setting time.
4. After pouring the mix into the formwork , continuous vibration is required to avoid formation of any
gap or cavity.
5. Due to quick setting time of LC 70 LI, we couldn’t prepare the next batch mix for casting until the
mix collecting bucket reaches to the discharge end of the mixer machine.
6. As there is material handling issue , the process is restricted to lower capacity for the preparation of
the mix.
7. As the procedure is fully dependent on the EOT crane (only mode of transport for the mix), it
becomes difficult to execute other jobs in ladle repair shop.
8. Due to multi-time casting , the process time material losses is comparatively more.
9. The process involves multiple safety issues like opening of bucket lock with mix , breakdown of
EOT crane while travelling etc.
Merits of Shotcasting/ Pumping method
1. Only for feeding the castable into the mixer of shotcrete machine , the process has to depend on EOT
crane.
Previously the shotcreting was done in the slagzone region of steel ladle (SL#2 , SL#11 & SL#10).
Procedure
1. After handover of the steel ladle ,we have checked the shell for slag/metal jam and loose retainer
plate and started for cleaning of shell (removal of worn insulation paper ) and vent holes .
2. Previously we first attempt for anchor cutting ,grinding and new welding , this time we skipped it
and started preparing for bottom casting .
5th layer
Shotcasting
Shell
Cleaning
Anchor
removal &
welding
Bottom
formwork Total number of sidewall
fixing formwork – 5
Bottom
Casting
Individual
Insulation + Job sequence in Casting with LC
Formwork 70 LI
Individual
layer Casting
Actual
Comparison of backup casting vs Plan Actual %
1 (beyond % Complete (beyond plan)
backup shotcreting Duration Start Complete
plan)
Steel Ladle Backup Shot Casting
Steel Ladle Back up shotcasting steps with pumpable castables including timeline:
No of steps reduced
along with time
Way forward
As we have tried to mitigate the demerits of casting with LC 70 method, replacing it with
shotcreting / use of pump able castable , we didn’t face any difficulty in this procedure as
per now.
We will evaluate the performance of the installation after completion of first circulation
campaign .