You are on page 1of 1

G.

Implementing schedule
2017

Activities March April May

1 2 3 4 1 2 3 4 1 2 3 4
I. Procurement of
equipment and hiring
of construction worker

II. Area development


and excavation
III. Construction worker
A. Foundation

B. Structure

IV. Rough framing

V. Rough plumbing,
electrical and HVAC

VI. Installing insulation

VII. Compute any wall


and interior texture;
start exterior
VIII. Finishing interior
trim; install exterior
driveways and
walkways
IX. Transferring and
organizing of hardware
products

You might also like