Autoput Bar - Boljare/The Bar - Boljare Highway

Dionica: Smokovac – Uvač – Mateševo/Section: Smokovac – Uvac – Mateševo


Glavni projekat / Main Design: Most/ Bridge 02 Moračica
Desna traka/Right line: RK 6+476.57 - RK 7+436.38
Lijeva traka/Left line: LK 6+482.14 - LK 7+442.33
Knjiga/Book: BBC030MO102GL09
3. TEKSTUALNA DOKUMENTACIJA/TEXTUAL DOCUMENTATION
3.1 TEHNIČKI IZVJEŠTAJ / TECHNICAL REPORT .................................................................................... 4

3.1 1 OSNOVE ZA PROJEKTOVANJE / DESIGN BASIS .......................................................................................... 4


3.1.1.1 Opšte / General .................................................................................................................... 4
3.1.1.2 PODACI O MOSTU / BRIDGE DATA...................................................................................................... 4
3.1.1.3 Podloge za projektovanje / Design basis ............................................................................ 14
3.1.2 TEHNIČKI ZAHTJEVI / TECHNICAL REQUESTS .......................................................................................... 15
3.1.2.1 Elementi trase/ Elements of route ...................................................................................... 15
3.1.2.2 Karakterističan poprečni presjek puta na mostu / Typical cross section of the road on the bridge 16
3.1.2.3 Izvod iz geotehničkog elaborata / Abstract from Geotechnical Elaborate ......................... 16
3.1.2.4 Izvod iz Hidrotehničkog elaborata / Abstract from Hydrotechnical elaborate ................... 19
3.1.2.5 Osvrt na likovnu i estetsku stranu rješenja i njegovo uklapanje u ambijent / The review of artistic
aspect and aesthetical aspect of the plan and it’s fitting into the environment ............................ 20
3.1.3 TEHNIČKI OPIS KONSTRUKCIJE MOSTA / TECHNICAL DESCRIPTION OF BRIDGE STRUCTURE ............................... 20
3.1.3.................................................................................................................................................... 20
3.1.3.1 Opis tehničkih karakteristika i parametara mosta, sa objašnjenjem konstruktivne koncepcije i
statičko-konstruktivne koncepcije / The description of technical characteristics and bridge parameters,
including the explanation of construction concept and static-construction concept ..................... 20
3.1.3.2 Gornji stroj mosta/ The superstructure of the bridge......................................................... 21
3.1.3.3 Donji stroj mosta / The substructure of the bridge ............................................................ 25
3.1.3.4 Temelji / Foundations ......................................................................................................... 29
3.1.4 STATIČKI PRORAČUN / STATIC CALCULATION.......................................................................................... 30
3.1.4.1 Opterećenja / Loads ........................................................................................................... 30
3.1.4.2 Modeliranje konstrukcije / Structure modelling ................................................................. 33
3.1.4.3 Rezultati analize nosača / Result of Girder Analysis ........................................................... 35
3.1.5 OPIS OSTALIH ELEMENATA MOSTA / THE DESCRIPTION OF OTHER BRIDGE ELEMENTS ..................................... 38
3.1.5.1 Ležišta / Bearings ............................................................................................................... 38
3.1.5.2 Dilatacije /Expansion joints ................................................................................................ 38
3.1.5.3 Kegle / Cone slopes............................................................................................................. 39
3.1.5.4 Ivični vijenci i beton u razdjelnom pojasu / Cornices and concrete in median strip ............ 39
3.1.5.5 Prelazna ploča i šljunčani klin / Transition slab and gravel wedge ..................................... 39
3.1.5.6 Hidroizolacija i odvodnjavanje / Waterproofing and drainage .......................................... 40
3.1.5.7 Saobraćajna signalizacija i oprema / Traffic signalization and equipment ........................ 41
3.1.5.8 Osvetljenje kolovoza mosta, osvetljenje unutrašnjosti nosača i dekorativno osvetljenje / The lighting
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
1
of the bridge deck, the interior of girder and decorative lighting .................................................. 41
3.1.5.9 Vjetrobrani / Windscreens ................................................................................................. 41
3.1.6 MATERIJALI KONSTRUKCIJE MOSTA / MATERIALS OF BRIDGE STRUCTURE..................................................... 41
3.1.7 OSVRT NA TEHNOLOGIJU IZVODJENJA / REVIEW OF CONSTRUCTION TECHNOLOGY ........................................ 42
3.1.7.1 Iskop i zaštita kosina / Excavation and slope protection .................................................... 43
3.1.7.2 Temelji / Foundations ......................................................................................................... 43
3.1.7.3 Stubovi / Pillars .................................................................................................................. 44
3.1.7.4 Glavni nosač – kolovozna ploča / Main girder-bridge deck ................................................ 44
3.1.7.5 Osvrt na mere za zaštitu životne sredine tokom izvodjenja / Review of environmental protection
measures during the construction .................................................................................................. 45
3.1.8 MJERE I RJEŠENJA ZA OBEZBJEDJENJE TRAJNOSTI OBJEKTA / MEASURES AND SOLUTIONS RELATED TO PROVIDING OF
STRUCTURE DURABILITY ............................................................................................................................ 45
3.1.9 OSVRT NA PREDMJER I PREDRAČUN RADOVA / THE REVIEW OF BILL OF QUANTITIES ...................................... 46
3.1.10 SPISAK KORIŠĆENIH ZAKONA, OPŠTIH I TEHNIČKIH PROPISA, NORMATIVA I STANDARADA / THE LIST OF APPLIED LAWS,
GENERAL REGULATIONS, TECHNICAL REGULATIONS, NORMATIVES AND STANDARDS................................................ 47
3.2 TEHNIČKO I TEHNOLOŠKO REŠENJE / TECHNICAL AND TECHNOLOGICAL SOLUTIONS ................. 49

3.2.1 PRIKAZ STRUKTURE ČIJA JE IZGRADNJA PLANIRANA / L AYOUT OF THE STRUCTURE WHICH WILL BE CONSTRUCTED 49
3.2.2 RADNI DANI ZA IZVOĐENJE KONSTRUKCIJE / CONSTRUCTION WORKING DAYS ............................................... 49
3.2.3 SPISAK MAŠINA I OPREME / LIST OF MACHINERY AND EQUIPMENT ............................................................ 50
3.2.4 PROCES IZGRADNJE I TEHNOLOGIJA IZGRADNJE / CONSTRUCTION PROCESS AND METHODS ............................. 52
3.2.4.1 Pripreme / Preparations ..................................................................................................... 52
3.2.4.2 Glavni radovi / Main works ................................................................................................ 52
3.2.5 KONCEPT MATERIJALA , UREDJAJA I OSTALIH SREDSTAVA TRANSPORTA / CONCEPTION OF MATERIALS,DEVICES AND OTHER
RESOURCES TRANSPORTATION .................................................................................................................... 60
3.3 PROJEKAT PRETHODNIH I PRIPREMNIH RADOVA / DESIGN OF PRELIMINARY AND PREPARATORY WORKS
........................................................................................................................................................ 61

3.3.1 KONCEPT IZMJEŠTANJA ILI UKLANJANJA POSTOJEĆIH ELEMENATA / CONCEPT OF RELOCATION AND/OR DEMOLITION OF
EXISTING STRUCTURES .............................................................................................................................. 62
3.3.2 KONCEPT PUTEVA ZA INTERNU UPOTREBU NA PROJEKTU, VEZA SA SPOLJNIM PUTEVIMA I PRISTUPNIM PUTEVIMA / CONCEPT
OF INTERNAL ROADS, CONNECTION TO THE EXTERNAL ROADS AND ACCESS ROADS ................................................. 62
3.3.3 KONCEPT VODOSNABDIJEVANJA I NAPAJANJA ELEKTRICNOM ENERGIJOM / CONCEPT OF WATER SUPPLY AND POWER SUPPLY 62
3.3.4 KONCEPT POZICIONIRANJA I LOKACIJA FABRIKE BETONA / CONCEPT OF POSITIONING AND LOCATION OF PLANT ... 63
3.3.5 PROJEKAT PRIVREMENIH NASELJA SA OBJEKTIMA / DESIGN OF TEMPORARY SETTLEMENT WITH THE FACILITIES.... 63
3.3.6 SHEMA ORGANIZACIJE GRADILIŠTA / SITE ORGANIZATION SCHEME............................................................. 63
3.3.6.1 Pristupni put i privremena saobraćajna signalizacija / Access road and temporary traffic
signalization ................................................................................................................................... 64
3.4 PLANIRANJE VREMENA, TROŠKOVA I RESURSA / TIME, MONEY AND RESOURCE PLANNING ..... 64

3.4.1 KONCEPT MATERIJALA, ELEKTRIČNOG NAPAJANJA I DRUGIH RESURSA / CONCEPTION OF MATERIALS, ELECTRIC POWER AND
OTHER RESOURCES ................................................................................................................................... 64
3.4.2 PLAN RADOVA / PLANING OF WORKS .................................................................................................. 65

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
2
3.4.2.1 Plan angažovanja radne snage i masina na Moracica mostu / Static plan in terms of labor and
Machinery for Moracica Bridge ...................................................................................................... 65
3.4.2 PLAN TRANSPORTA MAŠINA I OPREME / TRANSPORTATION PLAN OF MATERIAL AND MACHINE ........................ 76
3.5 STUDIJA O BEZBJEDNOSTI NA RADU / STUDY ON OCCUPATIONAL SAFETY ................................. 77

3.5.1 OSNOVNI PODACI O GRAĐEVINSKIM RADOVIMA ZA FAZU PRIPREMNIH RADOVA / GENERAL DATA ON CONSTRUCTION WORKS
FOR THE PHASE OF PRELIMINARY WORKS ...................................................................................................... 77
3.5.2 GRAĐEVINSKE JAME, RADOVI POD ZEMLJOM, TUNELI I ZEMLJANI RADOVI / CONSTRUCTION PITS, WORKS UNDER GROUND,
TUNNELS AND EARTH WORKS ..................................................................................................................... 80
3.5.3 GRAĐEVINKS RADOVI / MAIN CONSTRUCTION WORKS ............................................................................ 84
3.5.4 MJERE ZAŠTITE PRI RADU NA VISINI / WORK SAFETY MEASURES FOR WORKING AT HEIGHT .... 94
3.5.5 POSEBNE MJERE ZAŠTITE PRI MINIRANJU / SPECIAL PROTECTIVE MEASURES DURING BLASTING97

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
3
3.1 Technical report 3.1 TEHNIČKI IZVJEŠTAJ

3.1 1 Design basis 3.1.1 Osnove za projektovanje

3.1.1.1 General 3.1.1.1 Opšte

Employer: Government of Montenegro, Investitor: Vlada Crne Gore


Ministry of transport and maritime affairs
Ministarstvo saobraćaja i pomorstva

Road: Bar – Boljare highway Saobraćajnica: Autoput Bar – Boljare

Section: Smokovac – Mateševo Dionica: Smokovac – Mateševo

km 0+000 to 40+871 km 0+000 do 40+871

Subsection: km 0+000 to 11+483.05 Poddionica: km 0+000 to 11+483.05

Structure: Bridge Moracica Objekat: Most Moračica

Design phase: Main design Faza projektovanja: Glavni projekat

3.1.1.2 Bridge data 3.1.1.2 Podaci o mostu

3.1.1.2.1 The description of bridge layout 3.1.1.2.1 Opis dispozicije mosta

Integrated bridge for both highway lanes is Projektom je predvidjen jedinstven most za obe
designed. trake autoputa.

The Bridge spreads from chainage km Most se prostire od stacionaže km 6+482.14 do


6+482.14 to km 7+442.33 per left axis. km 7+442.33, po lijevoj osovini.

The bridge spreads from chainage km Most se prostire od stacionaže km 6+476.57 do


6+476.57 to km 7+436.38 per right axis. km 7+436.38, po desnoj osovini.

The space between carriageway axis in the Razmak osovina kolovoza u osnovi je 11.70 m.
basis is 11.70m. The left carriageway is on the Lijevi kolovoz je na dionici ispred mosta, na
section in front of the bridge, on the bridge as mostu i iza mosta, paralelan sa desnim
well as behind the bridge. It is parallel to right kolovozom.
carriageway.

The bridge bridges main road Most premošćuje, redom, magistralni put
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
4
Podgorica-Kolasin, river Moraca and plateau Podgorica – Kolašin, rijeku Moraču i plato
Moracica (the bridge is named after this Moračica (po kome je most i dobio ime).
plateau), respectively.

It connects northeastern slopes of hill Zdrvanj Spaja sjevero-istočne obronke brda Ždrvanj i
and west slopes of hill Smrdulja. There is a zapadne obronke brda Smrdulja, izmedju kojih
gorge between them and it’s width is se nalazi klisura širine približno 1000 m. Mostu
approximately 1000m. The bridge is se prilazi iz kraćeg dijela otvorene trase (oko
approached from shorter part of open route 400 m) kojoj prethodi tunel Mrke. Iza mosta je
(it’s length is approximately 400m). The tunnel otvorena trasa autoputa (oko 4 km) nakon čega
“Mrke” is located in front of it. There is an slijedi tunel Klopot. Kote nivelete autoputa na
open route of highway of about 4km behind the početku mosta su oko 253 mnm, dok su na kraju
bridge and there is a tunnel “Klopot” mosta oko 293 mnm. Dužina mostovske
afterwards. The elevation of vertical alignment koonstrukcije, mjereno po lijevoj osovini
of the highway at the beginning of the bridge is autoputa, iznosi L=960.19m. Maksimalna visina
about 253 meters above sea level, the mosta iznad terena je veća od 175 m, na dijelu
elevation of vertical alignment at the end of the iznad rijeke Morače i dodatnih 30 m, kolika je
bridge is about 293 meters above sea level. dubina kanjona u odnosu na plato Močačica.
As measured by left axis of highway, the length
of bridge structure is L=960.19. The maximum
height of the bridge above the terrain exceeds
175m. It exceeds the additional 30 m on the
part above river Moraca (this is the depth of the
canyon in relation to plateau Moračica).

3.1.1.2.2 Geomorphological features of the 3.1.1.2.2 Geomorfološke odlike terena


terrain

In this area, the river Morača has formed an Rijeka Morača na ovom dijelu terena formirala je
extremely asymmetric valley. izrazito asimetričnu dolinu.

From geomorphological aspect, the following U geomorfološkom pogledu, u zoni mosta


areas are found in the area of the bridge: Moračica mogu se izdvojiti slijedeće cjeline:

 the right bank of river which can be divided  Desna dolinska strana koja se
into 2 morphometric units, being: morfometrisjki može podijeliti u 2 cjeline i to:

- Slope with relatively equal gradients of - Padina relativno ujednačenog nagiba oko
about 30°C, sporadical cascade shape, 30°, mjestimično kaskadno oblikovana, dužine
stretching in length of about 300 m in banked oko 300 m u bankovitim jurskim krečnjacima.
Jurassic limestone. Altutude ranges from about Nadmorska visina se kreće od oko 250 mnm u
250 masl in the beginning area of bridge to 100 zoni početka mosta do oko 100 mnm u zoni
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
5
masl in the main road area; magistrale;

- Slope with average gradient of about - Padina nagiba u prosjeku oko 30° u
30°C in terraced fluvio-glacial sediments, terasnim fluvio-glacijalnim sedimentima, lokalno
gradients vary locally within steep small promjenljivog nagiba sa strmim manjim
stretches and notches. The slope is about 60 odsjecima i potkapinama. Dužina padine je
m long. Altitude ranges from about 100 masl in oko 60 m. Nadmorska visina se kreće od oko
the main road area to about 70 masl in the 100 mnm u zoni magistrale do oko 70 mnm u
area of river Morača's bed. zoni korita rijeke Morače

 The riverbed of the Morača is formed in  Korito rijeke Morače formirano u terasnim
the terraced fluvio-glacial sediments with fluvio glacijalnim sedimentima sa
modern alluvial gravels and sandy gravels savremenim aluvijalnim šljunkovima i
in width of 25-30m, having an altitude of pjeskovitim šljunkovima širine 25 do 30 m,
about 70 masl. Alongside the canyon's sa nadmorskom visinom oko 70 mnm. Duž
bed, erosion activities of the watercourse kanjonskog korita u terasnim
of river Morača are very strong in the konglomeratima, izraženo je eroziono
terraced conglomerates and this is djelovanje vodotoka Morače, koje se
manifested by formation of cave notches manifestuje kroz formiranje pećinskih
and potentially unstable blocks. potkapina i potencijalno nestabilnih blokova

 The left bank of river can be divided into  Lijeva dolinska strana koja se morfometrijski
the following three morphometric units: može podijelti u 3 cjeline i to:

- Steep stretch towards the river Morača in - Strmi odsjek ka Morači u glacio-fluvijalnim
the fluvio-glacial sediments with almost vertical sedimentima skoro subvertikalnog nagiba,
gradient, sporadically about 60°C with notches mjestimično oko 60° sa potkapinama visine oko
about 30 m high. Altitude ranges from 70 masl 30 m. Nadmorska visina se kreće od 70 mnm u
in the riverbed area to about 100 m in a zoni korita do oko 100 mnm u zoni platoa;
platform area;

- Wide platform made of glacio-fluvial - Široki plato formiran od glacio fluvijalnih


sediments (weakly to strongly bounded sedimenata (slabo do dobro vezan konglomerat
conglomerate and sandy gravel), about 140 m i pjeskovit šljunak), širine oko 140 m sa
wide with altitudes ranging between 98 and nadmorskim visinama od 98 do 102 mnm;
102 masl.

- Slope with equal average gradient of 30°C - Padina ujednačenog nagiba u prosjeku oko
in the Triassic-Jurassic interbedded dolomite 30° u trijasko jurskim slojevitim dolomitima i pri
and in the Cretaceous interbedded limestone vrhu u krednim slojevitim krečnjacima. Donji
around the top. Bottom of the slope is covered djelovi padine su pokriveni sa
by diluvial-coluvial materials (silty - clayey deluvijalno-koluvijalnim materijalom (prašinasto
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
6
debris) that lessen the gradient and form a mild glinovita drobina) koja ublažava nagib i formira
crossing to the platform. The slope is about blag prelaz ka platou. Dužina padine je oko
400 m long. Altitude ranges from about 100 400 m. Nadmorska visina se kreće od oko 100
masl in the platform area to about 285 masl in mnm u zoni platoa do oko 285 mnm u zoni kraja
the end area of the bridge. mosta.

In front of the bridge, the terrain gradient in the Prije mosta, nagib terena u poprečnom pravcu je
transverse direction is left to right. The route is sa lijeve na desnu stranu. Neposredno ispred
located in the low side cut immediately in front mosta trasa se nalazi u zasjeku male visine, koji
of the bridge and it becomes an enbankment zatim prelazi u nasip visine do 10 m. Iza mosta,
whose height does not exceed 10m. Highway autoput brzo ulazi u visoki usjek. Teren ispod
quickly enters the high cut behind the bridge. mosta na desnoj obali rijeke Morače se strmo
The terrain under the bridge on the right bank spušta ka kanjonu rijeke. Na dijelu krajnjeg
of the river Moraca descends to the river oporca A0, teren je, u podužnom pravcu, još
canyon steeply. At the section of abutment AO, uvijek u blažem nagibu oko 1:5 prema rijeci
the gradient of terrain in longitudinal direction Morači, a u poprečnom, na lijevu stranu. Dalje,
is still slight, that is, about 1:5 towards the river ka stubu P1, i podužni i poprečni nagib terena se
of Moraca. In the transversal direction, it povećavaju, tako da i podužni i poprečni nagib
inclines to the left side. Furthermore, iznosi oko 1:2. Teren u zoni stuba P2, u blizini
longitudinal and transversal gradient of terrain magistralnog puta, zadržava strm podužni nagib
increase towards pier P1, so both, longitudinal ka Morači, a poprečni se smanjuje i postaje
gradient and transversal gradient of terrain is relativno blag. Stub P3 se nalazi na platou
about 1:2. The terrain in the zone of pier P2 Moračica. Poprečno, teren oko stubova P4 i P5
near the main road keeps steep longitudinal je blago nagnut na desnu stranu. Podužno, oko
gradient towards Moraca. Transverse gradient stuba P4, nagib se polako povećava, ka stubu
is getting lower and becomes relatively slight. P5, gde dostiže 1:2, kao i na desnoj obali rijeke.
The pier P3 is located on the plateau Krajnji oporac A1 se nalazi ispod vrha brda, u
“Moracica”. Transversally, the terrain around koji trasa autoputa ulazi nakon mosta, u veoma
piers P4 and P5 is slightly inclined to the right strmom podužnom nagibu, takodje 1:2.
side. Longitudinally, the gradient increases
slowly around the pier P4 towards pier P5 and
it reaches 1:2 (as well as on the right river
bank). The abutment A1 is located under the
top of the hill which the highway route comes in
behind the bridge. The longitudinal gradient is
very steep, that is, 1:2.

3.1.1.2.3 Geologic structure on the site of 3.1.1.2.3 Geološka građa na lokaciji mosta
Moračica bridge Moračica

The geological structure along the route of U geološkoj građi terena, duž trase mosta
bridge Moračica includes carbonate rocks of Moračica, učestvuju karbonatne stijene trijasko -
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
7
Triassic- Jurassic (T, J), Lower Jurassic (J12,3) jurske starosti (T, J), donjojurske starosti (J12,3) i
and Lower-Cretaceous age. donjokredne starosti (K1).

Rheto-lias sediments are found on a slope at Retolijaski sedimenti otkriveni su na padini na


the left valley side. In the lower part of the lijevoj dolinskoj strani. U donjem dijelu padine
slope, they are overlaid by Quaternary slope pokriveni su kvartarnim padinskim sedimentima
sediments as well as glacio-fluvial terraced kao i glaciofluvijalnim terasnim sedimentima.
sediments. Along the bridge’s route, they are Duž trase mosta zastupljeni su od stacionaže
present from chainage RK 6+820 to chainage RK 6+820 do stacionaže RK 7+400 km.
RK 7+400 km. They are represented by Predstavljeni su bankovitim dolomitima i
banked dolomite and dolomitic limestone. dolomitičnim krečnjacima. Debljina retolijaskih
Thickness of the rheto-liasic sediments in sedimenata u geološkom stubu iznosi oko 600
geological column is about 600 m. At the m. Na stacionaži RK 6+820 u rasjednom su
chainage RK 6+820, they are in a fault contact kontaktu sa donjojurskim sedimentima, dok su
with the Lower Jurassic sediments, while they na stacionaži RK 7+400 takođe u rasjednom
are also in a fault contact with the Lower kontaktu sa donjokrednim karbonatnim
Cretaceous carbonate rocks at the chainage stijenama.
RK 7+400.

Lower Cretaceous sediments build the ending Sedimenti donjokredne starosti izgrađuju završni
part of the slope on the left side. They are dio padine na lijevoj strani. Predstavljeni su
represented by lithiotic, bedded to massive litiotskim, slojevitim do masivnim krečnjacima.
limestones. Thickness of these sediments in Debljina ovih sedimenata po geološkom stubu
geological column is 250 m. Contact with iznosi 250 m. Kontakt sa retolijaskim dolomitima
rheto-liassic dolomite and dolomitic limestone i dolomitičnim krečnjacima je rasjedni na
is a fault-like at chainage RK 7+400 km. The stacionaži RK 7+400 km. Rasjed u ovoj zoni je
fault in this area is covered by deluvial pokriven deluvijalnim sedimentima.
sediments.

Lower Jurassic sediments build the right valley Sedimenti donjojurske starosti izgrađuju desnu
side. They are represented by banked to dolinsku stranu. Predstavljeni su bankovitim do
bedded limestone. Thickness of these slojevitim krečnjacima. Debljina ovih sedimenata
sediments in geological column is 250 m. po geološkom stubu iznosi oko 250 m. Kontakt
Contact with rheto-liassic sediments is a sa retolijaskim sedimentima je rasjedni i to ispod
fault-like beneath the Morača’s riverbed. The korita rijeke Morače. Rasjed je pokriven
fault is covered by alluvial sediments. At the aluvijalnim sedimentima. Na trasi mosta ovi
bridge’s route, these sediments are present sedimenti su zastupljeni od početka mosta do
from the beginning point of the bridge to the stacionaže RK 7+400 km.
chainage RK 7+400 km.

The Quaternary sediments are basically Kvartarni sedimenti su generalno predstavljeni


represented by glacio-fluvial, alluvial and slope glaciofluvijalnim, aluvijalnim i padinskim
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
8
sediments. sedimentima.

Glacio-fluvial sediments are represented by Glaciofluvijalni sedimenti su predstavljeni slabije


weakly to strongly bound conglomerates with do jače vezanim konglomeratima sa proslojcima
layers and lenses of sandy gravel. The i sočivima pjeskovitog šljunka. Valutice su
boulders are mainly of carbonate origin uglavnom karbonatnog porijekla (krečnjak). U
(limestone). The Morača carved its riverbed in ovom materijalu Morača je usjekla svoje korito.
this material. Thickness of these sediments Debljina ovih sedimenata se kreće od 40 do 50
ranges from 40 to 50 m on left side of the m na lijevoj dolinskoj strani dok je na desnoj oko
valley, while it’s about 15 m on the right side. In 15 m. U zoni korita je debljine do 10 m dok
the zone of the riverbed, it’s thickness is up to izostaje u samoj desnoj ivici korita gdje su vidljivi
10 m, while it is not present in right edge of the krečnjaci donjojurske starosti.
bed where Lower Jurassic limestone is visible.

Alluvial (nowadays) deposits of the Morača Aluvijalni (savremeni) nanos Morače je debljine
have thickness of 4 to 5 m and are represented 4 do 5 m i predstavljen je šljunkom, pjeskovitim
by gravel, sandy gravel and larger pieces of šljunkom i većim komadima konglomerata koji
conglomerates that are escarped and ripped su odronjeni i otkinuti sa strmih strana rečne
off the steep sides of the river terrace. terase.

On the slopes, the slope processes have been Na padinama su razvijeni padinski procesi, a
developed. Primarily of all, there is a deluvial prije svega deluvijalni u kombinaciji sa
process along with colluvial process. In the koluvijalnim procesom. U donjim djelovima
lower parts of the slope, there is a clayey silty padine se radi o glinovito prašinastom materijalu
material with a lower percentage of debris, sa manjim procentom drobine dok se u srednjim
while there is a debris with silty sandy i gornjim djelovima radi o drobini sa prašinasto
component in the middle and upper parts. pjeskovitom komponentom, mjestimično se
Lessened scree appears sporadically. There pojavljuju umireni sipari. Aktivnih sipara ima u
are active screes in the upstream part of the uzvodnom dijelu lijeve dolinske strane i oni su
left side of the valley, outside the zone of van zone uticaja na budući most. Ovi kvartarni
impact to the future bridge. These Quaternary materijali imaju veće zalijeganje na lijevoj
materials have a larger dip and strike on the dolinskoj strani. U središnjem dijelu padine ima
left side of the valley. In the middle part of the debljinu do oko 3 m, dok je u donjem dijelu
slope, the thickness reaches up to about 3 m, padine debljine od 5 do 10 m. Takođe se javlja i
while the thickness in the lower part of the na višim djelovima padine gdje zapunjava
slope is 5 to 10 m. It also occurs on the higher džepove (manje depresije do 2 m) koje su
parts of the slope where it is infilling the formirane u krečnjačkoj osnovnoj stijeni.
pockets (minor depression up to 2 m) that were
formed in the limestone basic rock.

On the slopes of the exit portal, there are Na padinama izlaznog portala zastupljeni su
deluvial sediments represented by screes deluvijalni sedmenti predstavljeni siparima, koji
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
9
which are lessened by vegetation. su umireni vegetacijom.

3.1.1.2.4 Hydro-geological characteristics of 3.1.1.2.4 Hidrogeološke odlike terena


the terrain

Based on the hydrogeological properties and Na osnovu hidrogeoloških svojstava i funkcija


functions of the rock mass, structural type of stijenskih masa, strukturnog tipa poroznosti i
porosity and spatial position of hydro prostornog položaja hidrogeoloških pojava,
geological phenomena, it can be concluded može se zaključiti da istraživani dio terena u široj
that the investigated part of site in the wider zoni mosta Moračica izgrađuju srednje do
area of the bridge Moračica is built of medium dobro vodopropusne stijene pukotinsko -
to well permeable rocks of fracture - cavernous kavernozne poroznosti, predstavljene ispucalim i
porosity, as represented by fractured and u površinskom dijelu skaršćenim krečnjacima i
surface karstificated limestones and dolomite dolomitičnim krečnjacima kao i stijene
limestones, as well as rock joints of partly pukotinske i dijelom intergranularne poroznosti,
granular porosity represented by glacio-fluvial predstavljene glaciofluvijalnim konglomeratima i
conglomerate and sandy gravel. The valley pjeskovitim šljunkom. Dolinski oporci i stubovi
abutments and piers 1,2, 3, 4, and 5 will be 1,2, 3, 4 i 5 će biti fundirani u suvoj nadizdanskoj
footed in a dry above-aquifier zone through zoni kroz koju se odvija cirkulacija voda u
which circulation of waters take place in the vertikalnom pravcu.
vertical direction.

3.1.1.2.5 The review of climate conditions 3.1.1.2.6 Osvrt na klimatske uslove

Adriatic Sea and mountains in hinterland exert Na klimu ovog prostora utiče Jadransko more i
the influence on the climate of this area, so it planine u zaledju, tako da se može reći da je
can be said that the climate is Mediterranean klima mediteransko-planinska. Zato,
mountain climate. Therefore, northern winds preovladjuju sjeverni i južni vjetrovi. Najjači
and southern winds prevail. The strongest vjetrovi na ovom području su iz sjevernog
winds on this area blow from north. There are pravca. Postoje mjerne stanice samo u
measurement stations only in Podgorica and Podgorici i Kolašinu, pa je teško procjeniti
Kolasin, so it is difficult to estimate the actual stvarno stanje na području mosta.
condition on the area of bridge.

Average annual precipitation that are Za ovaj most su mjerodavne srednje godišnje
measured on meteorological station of Bioce padavine, koje su izmerene na meteorološkoj
are authoritative for this bridge (the average stanici Bioče i koje iznose 1290 mm. Medjutim,
annual precipitation is 1290mm). However, in oscilacije količina padavina su velike, i u
the terms of time and space, there are great vremenskom i u prostornom smislu. Velike su
variations of the amount of precipitations. promjene u zavisnosti od godine i u zavisnosti
There are big changes, depending on year and od reljefa. Najviše padavina izlučuje se, u
terrain. On average, the highest amount of prosjeku, krajem jeseni i početkom zime, a
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
10
precipitation occurs at the end of the autumn najmanje ljeti. Na osnovu ovog i drugih
and at the beginning of winter. The lowest pokazatelja konstatuje se da je zastupljen
amount of precipitation occurs during summer. izmijenjeno mediteranski pluviometrijski režim.
Based on this indicator and the other
indicators, it is concluded that there is a
changed Mediterranean pluviometric regime
prevailing on this area.

Mean annual temperature is a bit lower than Srednja godišnja temperatura je nešto niža od
15.5oC which is the temperature stated at the 15.5 ⁰
measurement station in Podgorica. The u Podgorici. Prosječan broj dana sa sniježnim
average number of days with snow cover that pokrivačem preko 1cm se kreće oko 10 dana.
is higher than 1cm is about 10.

3.1.1.2.7 The description of layout of the 3.1.1.2.7 Opis dispozicionog rješenja


structure, including the explanation of the konstrukcije sa objašnjenjem koncepta
concept

The layout is adopted on the basis of few Dispoziciono rješenje je usvojeno na osnovu
important input parameters: nekoliko važnih ulaznih parametara :

1) The route on the part of the bridge goes 1) Trasa na dijelu mosta prelazi preko veoma
over very high hollow, so the height of vertical visoke udoline, pa je visina nivelete iznad terena
alignment above the terrain determined main odredila glavne raspone u estetskom i
spans ( in terms of aesthetics, functionality and funkcionalno-tehnološkom smislu(4);
technology)

2) The position of canyon of river Moraca 2) Položaj kanjona rijeke Morače i


and main road, i.e., their relative position and magistralnog puta, tj. najpre, njihov medjusobni
sharp slope between them. Namely, the položaj i oštra kosina izmedju njih; Naime, kao
position of pier P2 in the area of road and river posledica usvojenih glavnih raspona,
is a result of adopted main spans that were pomijenutih u 1), i predvidjene tehnologije
mentioned under item 1) and the designed izvodjenja, date u 4), a koji diktiraju racionalan
construction technology that was mentioned odnos glavnih i bočnih raspona, došlo se do
under the item 4) which determine the ratio položaja stuba P2 u zoni puta i rijeke. U
between main spans and side spans. There razmatranju su bile dvije varijante, koje su
were two variants considered. The first variant odrijedjene, u prvoj varijanti, položajem stuba P2
was determined by the position of pier P2 izmedju puta i rijeke i, u drugoj varijanti,
between the road and the river. The second položajem P2 iznad puta. Obe varijante su
variant was determined by the position of pier razradjene do nivoa Glavnog projekta. Na
P2 above the road. Both variants were osnovu detaljne prethodne analize, utvrdjeno je
elaborated for the Main Design. The following da: prvo, postoje teškoće sa dispozicionim
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
11
is determined on the basis of detailed rješenjem koje podrazumeva stub sa temeljem
preliminary analysis: firstly, there are izmedju puta i rijeke, jer bi kosina iskopa bila
difficulties related to block plan that includes takva da bi imala za posledicu neophodnost
the pillar with the foundation between road and izrade devijacije magistralnog puta za vrijeme
river because the excavation slope would izvodjenja radova, česte prekide saobraćaja na
cause consequences such as the necessity to tom putu i ugroženu bezbjednost učesnika u
construct deviation of the main road during saobraćaju i izvodjača radova. Devijacija (pošto
construction, frequent traffic interruptions on je magistralni put u pitanju) bi morala imati takvu
that road as well as threatened safety of traffic geometriju, koja bi zahtijevala veliki obim radova
participants and contractor's workers. Due to na usecanju njene trase u strmu stijenu iznad
the fact that this is a main road, the deviation magistralnog puta. Drugo, razlozi da se ne usvoji
would request geometry that requieres large ovaj položaj su dati u 3). Sa aspekta obradjenog
scope of works related to cutting it's route into u ovoj tački, lokacija stuba iznad puta je mnogo
the steep rock above the main road. Secondly, povoljnija, zahteva daleko manje iskope, a
the reasons against the adoption of this prekidi saobraćaja će biti samo povremeni i
position are introduced in item 3). From the kratki.
aspect elaborated in this item, the position of
the pier above the road is much more
favorable, it requieres much smaller
excavations and the interruptions will be
temporary and short.

3) Geotechnical conditions; On the basis of 3) Geotehnički uslovi; Na osnovu detaljnih


detailed investigation works that were carried istražnih radova, koji su uradjeni za obe
out for both variants, it is determined that varijante, utvrdjeno je da je ispucalost i
jointing of rocks, cavernousity and the kavernoznost stijena, kao i postojanje proslojaka
existence of interbeds of clayey material inside glinovitog materijala u njima, na mjestu izmedju
of them on the location between the road and puta i rijeke, znatno veća nego što je
the river is significantly higher than the ones pretpostavljeno u Geotehničkom Idejnom
assumed in Preliminary Geotechnical Design projektu. To je zahtevalo spuštanje kote
Report. It requiered the foundation level to be fundiranja temelja na kotu 73.00. Ova činjenica
lowered to level 73.00. This fact caused je prouzrokovala znatno veću dubinu potrebnog
significantly higher depth of the excavation iskopa za temelj, što je izazvalo sve posledice
requiered for the foundation and this caused all pomenute u prethodnom poglavlju, u vezi sa
the consequences mentioned in the previous devijacijom magistralnog puta. Osim toga, ovako
chapter that are related to the deviation of spušten temelj je izložen uticaju rijeke Morače,
main road. Besides, this kind of lowered koja može, na duži vrijemenski period, izazvati
foundation is exposed to the influence of river dalju degradaciju temeljnog tla u zoni fundiranja
Moraca that can cause further degradation of stuba. Ovim bi sigurnost stuba bila ugrožena,
foundation soil in the zone of pillar foundation naročito zbog toga što su visoki stubovi veoma
during longer period of time. This would osetljivi na eventualne, čak i minimalne, rotacije
threaten the safety of the pillar, especially due temelja. Rješenje sa pozicioniranjem stuba P2
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
12
to to the fact that high pillars are very iznad puta je u povoljnijoj geotehničkoj sredini,
susceptible to possible foundation rotations ravnomjernijih karakteristika, čime se povećava
(even the minimal one). The design plan that cjelokupna sigurnost objekta.
includes the positioning of the pier P2 above
the road is in more favorable geotechnical
environment. It's properties are more uniform
and this improves overall safety of the
structure

4) The planned technologies of the 4) Predvidjene tehnologije izvodjenja;


construction: Balanced cantilever Tehnologija slobodne konzolne gradnje
construction determines the rational ratio odredjuje da racionalan odnos glavnih i bočnih
between main and side spans ranging from 0.6 raspona bude izmedju 0.6 i 0.7, kako je
and 0.7, as it was stated in the widely used naznačeno u najšire korišćenim francuskim
French guidelines for bridge designing “SETRA” smernicama za projektovanje
„SETRA“ (bridges that apply balanced mostova, koji se izvode konzolnom gradnjom.
cantilever construction). It exerted influence on To je uticalo na raspored raspona i stubova,
span arrangement and pier arrangement, as it kako je već rečeno u 2). Ovakav odnos se
was said in item 2). This ratio is adopted in usvaja radi što većeg umanjenja dijela
order to decrease the parts of structures next konstrukcije uz krajnje oporce, koji se izvode na
to the abutments that are constructed on the skeli. U ovom slučaju je to naročito značajno, jer
scaffold (as much as possible). In this su nagibi kosina u bočnim rasponima veoma
particular case, this is extremely important strmi, pa je postavljanje skele i njihovih temelja
because the slope gradients in the side spans otežano. To je posebno naglašeno u rasponu P5
are very steep, so the installation of scaffolds - A1. U finalnoj dispoziciji (varijanti), koja je data
and their foundations is more difficult. This is u ovom projektu, dijelovi mostovske
particularly emphasized in the span P5-A1. In konstrukcije, koji se izvode na skeli, su dužine
the final layout plan (variant) that was provided 24 m i 28 m. Radi ilustracije gore navedenog, u
in this Design, the lengths of parts of bridge tabeli ispod su dati primjeri mostova u svetu, koji
structure that are constructed on the scaffold su izvedeni konzolnim postupkom i za koje su
are 24m and 28m. The table below shows the dati odnosi glavnih i bočnih raspona.
examples of bridges in the world that are
constructed by the balanced cantilever method
in order to introduce the above mentioned
content. The ratio between main spans and
side spans are provided in the table as well.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
13
Main Side span
No. State Bridge name Ls/Lm
span(Lm) (Ls)
Humen bridge across
1 China 270m 150m 0.556
auxiliary shipping lane
Sutong bridge across
2 China 268m 137m 0.511
auxiliary shipping lane
3 Australia Gate way 260m 145m 0.558
4 China Garden Bridge 250m 137m 0.548
5 China Jialing Bridge 250m 146m 0.584
6 Canada Confederation 250m 165m 0.660
7 Japan Binmin Bridge 240m 140m 0.583
8 China Qiantang river bridge 232m 127m 0.547
9 America Houston 228m 114m 0.500
10 Australia Mooney 220m 130m 0.591
11 China Huanan Bridge 190m 110m 0.579
12 Australia holte yarra 173m 72m 0.416
13 Malaysia Second link bridge 165m 96m 0.582
Yellow river bridge at
14 China 160m 105m 0.656
Sanmenxia

No./ Br.
State/ Država
Bridge name/ Ime mosta
Main span/Glavni raspon
Side span/Bočni raspon

3.1.1.3 Design basis 3.1.1.3 Podloge za projektovanje

TOR Projektni zadatak

Employer’s Requierements related to Zahtevi za projektovanje Investitora


designing

Geodetic maps Geodetske podloge

Main Design of Route Glavni projekat trase

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
14
Main Geotechnical Design Glavni geotehnički projekat

Seismic study Seizmička studija

The conditions of authoritative institutions and Uslovi nadležnih organa i organizacija


organizations

The other Designs related to the bridge design, Ostali projekti, povezani sa projektom mosta,
such as: the Design of Construction kao što su: projekat organizacije i tehnologije
Organization and Technology, Drainage gradjenja, projekat odvodnjavanja, projekat
Design, Bridge Lightning Design (lightning on osvetljenja na mostu, u mostu i dekorativnog
the bridge, in the bridge and decorative osvetljenja samog mosta, projekat saobraćajne
lightning of the bridge itself), Traffic signalizacije i opreme i projekat instalacija na
Signalization Design and Bridge Installation mostu.
Design.

3.1.2 Technical requests 3.1.2 Tehnički zahtjevi

3.1.2.1 Elements of route 3.1.2.1 Elementi trase

Radius of circular curve on the part of the route Poluprečnik kružne krivine na dijelu trase ispred
in front of the bridge ………… 1054m mosta……………………….….1054 m

The length of circular curve on the Dužina kružne krivine na mostu….…..~27 m


bridge…~27m

The length of transition curve on the bridge … Dužina prelaznice na mostu…….…..~150 m


~150 m

The length of straight line on the bridge and Dužina pravca na mostu i iza mosta.1450 m
behind the bridge
1450m

The straight line on the bridge ………~781 m Pravac na mostu………………….…~781 m

Crossfall on the part of circular curve…. 4% Poprečni pad na dijelu kružne


krivine………………………………..……4%

Crossfall on the part of transition curve is Poprečni pad na dijelu prelaznice se mijenja od
changing, ranging from one sided crossfall of jednostranog pada od 4% do dvostranog od
4% to double sided crossfall of 2.5% 2.5%

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
15
Grade on the part of the bridge, in front of the Podužni pad na dijelu mosta i ispred i iza
bridge and behind the bridge mosta………………………….…….…..4%
4%

3.1.2.2 Typical cross section of the road on 3.1.2.2 Karakterističan poprečni presjek puta
the bridge na mostu

The total width of the bridge ……… 23.40m Ukupna širina mosta…….……..…….23.40 m

The width of both carriageways……… 7.70m Širina oba kolovoza…………….….…..7.70 m

The width of traffic lanes……………2x3.50m Širina saobraćajnih traka…….……..2x3.50 m

The width of edge lanes...... Širina ivičnih traka....…….…...……..2x0.35 m


2x0.35m

The width of pedestrian lanes………2x2.00m Širina pješačkih staza...….….….…..2x2.00 m

2.3 Typical longitudinal section of the road on 2.3 Karakterističan podužni presjek puta na
the bridge mostu

Spans ………………… 95+70+3x190+125m Rasponi…………..…95+170+3x190+125 m

The length of the bridge per axis … 960.19m Dužina mosta, osovinski……….…..960.19 m

The length of the bridge with flank walls … Dužina mosta, sa krilnim zidovima..988.01 m
988.01m

3.1.2.3 Abstract from Geotechnical 3.1.2.3 Izvod iz geotehničkog elaborata


Elaborate

Investigations which were carried out for the U geotehničkom elaboratu su detaljno data
design of the bridge and their results are istraživanja, koja su obavljena za potrebe
presented in details in Geotechnical Study. projektovanja mosta i njihovi rezultati. Na
Based on the analysis of exploration boreholes osnovu analize kartiranja istražnih bušotina,
mapping, the results of geophysical surveys rezultata geofizičkih istraživanja, presiometara
and pressuremeter and laboratory tests, it is kao i laboratorijskih ispitivanja definisano je da
defined that "C" category represents the rock „C“ kategorija predstavlja stijensku masu
mass of favorable and satisfactory povoljnih i zadovoljavajućih geotehničkih
geotechnical characteristics for the karakteristika za fundiranje mostovskih stubova.
foundations of bridge piers. Large part of the Zbog velikog podužnog nagiba terena i

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
16
foundation will be founded in geotechnical usvojenih ravnih temelja, veliki deo temelja će
environment "B" due to the large longitudinal biti fundiran i u geotehničkoj sredini „B“.
gradient of terrain and adopted flat spread Fundiranje u ovim slojevima je usvojeno zbog
foundation. Foundation in these layers is vekih opterećenja u temeljnim spojnicama, ali i
adopted because of larger loads in foundation zbog značaja mosta. Dubina fundiranja koje je
joint, but also because of the importance of the preporučena je 1.5 do 2 m u sloju „C“. Prema
bridge. The recommended depth of foundation GN 200 sloj „D“, u kome nije predvidjeno
is 1.5 to 2 m in class "C". According to GN 200, fundiranje, spada u V kategoriju, sloj „C“ i „B“ u
layer "D" which is not planned for funding VI kategoriju. Ova činjenica određuje i način
belongs to the category V, layer "C" and "B" iskopa, a u geo-elaboratu je preporučeno glatko
belong to the category VI. This fact determines miniranje. Krečnjačka stijena, u kojoj je
the excavation method and smooth predvidjeno fundiranje, ima veoma visoke
blasting is recommended in Geotechnical vrijednosti jednoaksijalne čvrstoće, koje se kreću
elaborate. The limestone rock mass which the od 6.5 do 9 Mpa. Sračunata granična nosivost je
foundations will be placed in, has a very high od 24.5 do 33 Mpa. Na osnovu granične
value of uniaxial strength, ranging from 6.5 to 9 nosivosti, dobijena je dozvoljena nosivost (sa
MPa. Computed ultimate bearing capacity faktorom sigurnosti 8), koja se kreće u opsegu
ranges from 24.5 to 33 MPa. Based on od 3.06 do 4.12 Mpa. U odnosu na maksimalna
ultimate bearing capacity, allowable bearing opterećenja, dobijeni faktor sigurnost temelja se
capacity is determined (with a safety factor of kreće od 2.37 do 10.3. Nakon provjere
8), which is in the range of 3.06 to 4.12 MPa. In slijeganja, zaključak je da ona praktično ne
relation to the maximum load, the resulting postoje.
safety factor for foundations ranges from 2.4 to
10.3. After checking the settlement, the
conclusion is that it practically does not exist.

Gradients of the excavation slopes and Nagibi kosina iskopa i formiranje bermi je
formation of berms are given in details in detaljno dato u geotehničkom elaboratu, a
geotechnical study and it is elaborated in razradjeno u grafičkoj dokumentaciji projekta. Za
graphic documentation of the design. Sprayed zaštitu kosina iskopa predložen je prskani beton
concrete with anchors and reinforcing mesh is sa ankerima i armaturnom mrežom. Za
proposed to protect the slope of the prikupljanje atmosferske i procedne vode,
excavation. Drainage channels in the predvidjeni su drenažni kanali u temeljnoj jami.
foundation pit are intended for collecting the
atmospheric water and seepage water.

The faults which are registered on terrain in Rasjedi, koji su registrovani na terenu, se u ovoj
this area are reflected as locally strong zoni reflektuju kao lokalno jače polomljene zone
fractured zones up to 1 m thick where the do 1 m debljine gdje su komadi dobro zglobljeni
pieces are well jointed, ie., fall in of the drilling tj. u bušotinama generalno nisu registrovana
tool is not registered in the boreholes. The propadanja pribora. Takođe rezultati
results of geophysical seismic survey also geofizičkih-seizmičkih istraživanja pokazuju da
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
17
shows that the speed of propagation of Vp brzine prostiranja Vp talasa u ovoj zoni
waves in this zone exceeds 2000 m / sec prevazilaze 2000 m/sec što svedoči da se radi o
which proves that this is terrain without sredini bez jače karstifikovanih, milonitiziranih i
significantly karstified, mylonitified and intezivnije ispucalih zona.
intensively fractured zones.

Based on analysis of available data for part of Na osnovu analize raspoloživih podataka za dio
the canyon of the Moraca River where kanjona rijeke Morače, na kojem je pozicioniran
"Moračica" bridge is positioned, it can be most "Moračica", može se argumentovano
arguably said that in the area of the konstatovati da u zoni same mikrolokacije ovog
micro-location of the bridge there were no mosta, kao i u neposrednoj okolini, tokom
registered or observed earthquakes with najmanje prethodnih pet vjekova, nijesu
intensity or magnitude above what is shown on registrovani ili osmotreni zemljotresi sa
the map of forecasted expected maximum intenzitetom, odnosno magnitudom iznad nivoa
magnitudes of earthquakes for representative koji je prikazan na prognoznoj karti očekivanih
return period of 100 years in the area of the maksimalnih magnituda zemljotresa za
micro-location of the bridge, as well as in the povratni reprezentativnan period od 100 godina.
immediate vicinity, for at least the past five U konkretnom slučaju mosta "Moračica" to je
centuries. In the specific case of the vrijednost koja se može izraziti maksimalnom
"Moračica" bridge, it is a value that can be magnitudom od 5.8 jedinica Rihterove skale, sa
expressed in a maximum magnitude of 5.8 maksimalnim dogođenim ubrzanjima na
Richter scale with the maximum acceleration osnovnoj stijeni predmetne lokacije od 1.05
that actually occurred at a relevant location of m/s2, dok očekivana maksimalno horizontalno
basic rock of 1.05m/s2. The expected uzbrzanje za tzv. projektni zemljotres, odnosno
maximum horizontal acceleration for so-called povratni period od 95 godina iznosi 0.94 m/s2,
designed earthquake or return period of 95 odnosno 1.99 m/s2 u slučaju tzv. maksimalnog
years is 0.94 m/s2 or 1.99 m/s2 in the case of zemljotresa, odnosno kod povratnog perioda od
so-called maximum earthquake, i.e., in the 475 godina. Ovaj nivo očekivanih maksimalnih
case of the return period of 475 years. This magnituda proporcionalan je i seizmogenom
level of expected maximum magnitude is potencijalu koji je utvrđen na osnovu analize
proportional to the seismogenic potential that dimenzije kartografisanih regionalnih i lokalnih
is determined on the basis of the analysis for tektonskih rasjeda na širem prostoru lokacije
dimension of mapped regional and local ovog mosta. Istovremeno, rezultati geoloških
tectonic faults in the wider area of the location proučavanja ovog regiona, ne ukazuju na
of the bridge. At the same time, the results of postojanje recentnih tektonskih aktivnosti većih
geological studies of the region, does not razmjera koji bi mogli izazvati zemljotrese iznad
indicate the existence of recent tectonic activity gornje granice magnitude utvrdjene za ovaj
on a larger scale, which could cause region.
earthquakes of magnitude above the upper
limit established for the region.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
18
3.1.2.4 Abstract from Hydrotechnical 3.1.2.4 Izvod iz Hidrotehničkog elaborata
elaborate

The water from the carriageway is collected by Voda sa kolovoza se prikuplja slivnicima koji se
the gullies which are joined in the pipes which priključuju u cijevi kojima se voda sa kolovoza
take the water from the carriageway to odvodi do separatora u kojima se prečišćava
separators that purify it before it is discharged prije ispuštanja u okolinu. Dakle, riječ je o
into the environment. So, this is a closed zatvorenom sistemu, putem plastičnih cijevi
drainage system that includes plastic pipes (PE-HD).
(PE-HD).

The gullies are set on the lowest part of the Slivnici su postavljeni na najnižem dijelu
carriageway in the line that is 20cm far from kolovoza, u liniji udaljenoj od ivičnjaka 20 cm, na
the curb. The gullies are set at each 10 m. The svakih 10 m. Voda se sliva ka njima poprečnim i
water interflows towards the gullies by podužnim padom kolovoza.
carriageway crossfall and grade.

The water from the bridge carriageway is Voda sa kolovoza mosta se prikuplja u podužne
collected into longitudinal drainage pipes in drenažne cijevi na 2 načina: prvi je dijelu mosta
two ways: the first water collecting is carried koji je u pravcu, a drugi na dijelu koji je u
out on the part of the bridge which is in straight prelaznici. Na dijelu mosta u pravcu, u
line and the other one is carried out on the part poprečnom presjeku, postoje 2 podužne
of the bridge which is in curve. There are 2 drenažne cijevi, koje su postavljene ispod
longitudinal drainage pipes on the part of the konzola nosača, obostrano. Podužni pad cijevi
bridge in straight line in cross section. These prati podužni pad mosta. Na dijelu mosta u
pipes are set under the cantilevers of girder on prelaznici, poprečni pad je na jednu stranu, pa je
both sides. The longitudinal grade of pipe dodata i drenažna cijev u sredini nosača. Pošto
follows the longitudinal grade of bridge. The cijev ispod lijeve konzole mosta produžava do
crossfall at the part of the bridge in the curve is početka mosta (obzirom da je podužni nagib
turned towards one side, so there is a drainage nivelete ka početku mosta), na ovom dijelu,
pipe added in the middle of the girder. postoje 3 drenažne cijevi u poprečnom presjeku
Considering the longitudinal grade of vertical mosta. Za ove cijevi su ostavljeni otvori u
alignment is turned towards the beginning of parapetnom zidu krajnjeg oporca A0. Dalje, u
the bridge, the pipe under left cantilever of the nasipu ispod prelazne ploče, ove cijevi su
bridge continues to the beginning of the bridge. zaštićene od uticaja slijeganja čeličnim cijevima
There are 3 drainage pipes in the cross section Ø603…4. U hidrotehničkom projektu je dat način
of the bridge on this part. There are apertures vešanja cijevi za konstrukciju. U ovom projektu
for these pipes left in parapet wall of the su dati slivnici.
abutment A0. These pipes are protected from
the influence of settlement by steel pipes
Ø603…4. The method of hanging of pipes to

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
19
the structure is provided in hydrotechnical
design. The gullies are provided in this Design.

3.1.2.5 The review of artistic aspect and 3.1.2.5 Osvrt na likovnu i estetsku stranu
aesthetical aspect of the plan and it’s fitting rješenja i njegovo uklapanje u ambijent
into the environment

From the aesthetic aspect of view, the ratio I u estetskom pogledu, odnos raspona i visine
between the span and the bridge height is mosta je optimalan. Sandučast poprečni presjek,
optimal. Box cross section with inclined side sa nagnutim bočnim stranama, promijenljive
ends of variable height cross section along the visine poprečnog presjeka duž raspona, koji je
span that is adopted due to reasons of static, usvojen iz statičkih razloga, djeluje ujedno i
looks aesthetically favorable as well. The estetski povoljno. Takodje i stubovi, koji su
pillars that are double shaped in order to dvojno oblikovani da umanje uticaj vjetra, daju
reduce the wind influence, provide mostovima transparentnost. Niski obalni stubovi
transparency to the bridge as well. From the ne narušavaju jedinstvenost mosta i ostalog dela
visual point of view, low abutments do not trase, u vizuelnom smislu. Cjelokupna silueta
disturb the integrity of the bridge and the rest of mosta se dobro uklapa u okolinu.
the part of the route. Whole silhouette of the
bridge fits well into the environment.

3.1.3 Technical description of bridge 3.1.3 Tehnički opis konstrukcije mosta


structure

3.1.3.1 The description of technical 3.1.3.1 Opis tehničkih karakteristika i


characteristics and bridge parameters, parametara mosta, sa objašnjenjem
including the explanation of construction konstruktivne koncepcije i
concept and static-construction concept statičko-konstruktivne koncepcije

The bridge is a continuous prestressed frame Konstrukcija mosta je kontinualna prethodno


structure of variable cross section. Three main napregnuta ramovska, promijenljivog poprečnog
central spans are slighthly higher than the first presjeka. Zbog gore pomenutog u tačci 1.2.3, u
central span P1-P2 due to the above vezi položaja stuba P2, tri glavna središnja
mentioned content in the item 1.2.3. The raspona su nešto veća nego prvi središnji, P1 -
attention was paid to the ratios of end spans P2. Pri odrijedjivanju ovog odnosa, vodilo se
and central spans between side spans during računa i o odnosima krajnjih i središnjih raspona
the defining of this ratio. This resulted in the sa bočnim. Tako se došlo do optimalnog odnosa
optimal ratio between end spans and central krajnjih i srednjih raspona, na početku mosta
spans, that is, 95/175=0.54 at the beginning 95/175=0.54 i 125/190=0.66 na kraju mosta i do
of the bridge and 125/190=0.66 at the end of glavnih raspona od 190 i 170 m. Ovakav odnos
the bridge and towards the main spans of raspona je pogodan za kontinualan ramovski
190m and 170m. This span ratio is favorable konstruktivni sistem, čija se mostovska
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
20
for continuous frame construction system konstrukcija izvodi metodom slobodne konzolne
whose bridge structure is constructed by the gradnje.
balanced cantilever method.

The piers P1-P5 establish rigid connection with Stubovi P1 – P5 su kruto vezani za konstrukciju,
the structure and abutments A0 and A1 are a krajnji oporci A0 i A1 preko ležišta. Na taj način
connected to the structure through bearings. su horizontalni uticaji raspodeljeni na više
This is how the horizontal impacts are divided stubova i umanjeni u odnosu na rješenje sa svim
onto a few piers and reduced comparing to the ležištima. Na ovaj način je dobijen system sa
plan that includes all the bearings. The system većom unutrašnjom rezervom nosivosti. Kruta
with larger inner spare bearing capacity is veza je, takodje, povoljna i sa stanovišta
obtained on this way. From the aspect of tehnologije izvodjenja. Ramovska konstrukcija,
construction technology, the rigid connection is zahtijeva i manje dimenzije temelja.
favorable as well. Frame structure also
requests smaller dimensions of foundation.

The bridge layout shown on the figures below Na osnovu svega do sada pomenutog, usvojena
is adopted on the basis of every content that je dispozicija mosta, prikazana na sledećim
has been mentioned so far. slikama

3.1.3.2 The superstructure of the bridge 3.1.3.2 Gornji stroj mosta

The cross section of the structure is double-cell Poprečni presjek konstrukcije je dvoćelijski,
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
21
box cross section of variable height along the sandučast, promijenljive visine duž raspona.
span. Thee width of the top slab of the main Širina gornje ploče glavnog nosača je 22.7m.
girder is 22.7m. The height of the girder above Visina nosača nad osloncem na stub P1 je 10.5
the support on the pier P1 is 10.5m. The height m. a iznad stubova P2, P3, P4 i P5 je 11.5 m.
of the girder above the support on piers P2, Visina grede u sredini raspona i iznad oslonaca
P3,P4 and P5 is 11.5m. The height of the na krajnje oporce je 3.8 m. Visina glavnog
beam in the middle of the span and above the nosača se mijenja prema paraboli stepena 1.8.
bearings (supports) on abutments is 3.8m. The Debljina donje ploče presjeka u polju A0 – P1 i
height of the main girder changes per parabola P5 – A1 varira od 30 cm kod oslonca na A0 (A1),
1.8. The thickness of bottom slab of the section do 120 cm kod oslonca na P1(P5). Debljina
in the field A0-P1 and P5-A1 varies, ranging donje ploče presjeka u poljima P1 – P2, P2 – P3,
from 30cm at support to AO (A1) to 120 cm at P3 – P4 i P4 – P5 varira od 30 cm u sredini
the support to P1 (P5). The thickness of bottom raspona do 120 cm kod oslonca na srednje
slab of the section in the fields P1-P2, P2-P3, stubove. Debljina donje ploče se mijenja takođe
P3-P4 and P4-P5 varies, ranging from 30cm at po paraboli stepena 1.8, a na vrhu stuba je
the middle of the span to 120cm at the support konstantna. Iznad oslonaca na krajnje oporce,
on middle piers. The thickness of bottom slab donja ploča je debljine 80 cm. Veze donje ploče i
changes per parabola 1.8. It is constant on the podužnih i poprečnih rebara su ojačane vutama.
top of the pier. The bottom slab above the Postoje tri debljine rebra sandučastog nosača
support on end abutments is 80 cm thick. The (65cm, 55cm i 45cm). Ova podjela odgovara
joints between bottom slab and longitudinal trima dužinama segmenta grede (3.0m, 3.75m i
and cross webs are strengthened with 4.50 m). Gonja ploča je konstantne debljine 30
haunches. There are three thicknesses of the cm. Debljina rebara baznih segmenata je 85 cm.
web of box girder (65cm, 55cm and 45cm). na baznom dijelu, iznad stuba su 4 poprečna
This division suits to three lengths of beam nosača, debljine 80 cm. Gornja ploča izmedju 1.
segments (3.0m, 3.75m and 4.50m). The i 2. i izmedju 3. i 4. je ojačana na 160 cm i
constant thickness of the top slab is 30cm. The predstavlja ujedno i devijator kablova. Izmedju 2.
thickness of web of base segments is 85 cm at i 3 rebra, ploča je 50 cm. Debljina rebara i
base part. There are 4 cross girders above the dimenzije vuta gornje ploče obezbjedjuju
pier and their thickness is 80cm. Top slab dovoljno prostora za smještaj ankera kablova.
between 1 and 2 and 3 and 4 is strengthened
to the thickness of 160 cm.It is cable deviator.
The thickness of the slab between 2 and 3 is
50cm. The thickness of the webs and
dimensions of the haunches of the top slab
provide enough space for the arrangement of
anchor cables.

There are short elements for transfer of Na mjestima oslanjanja konstrukcije na krajnje
horizontal wind forces (so called shear key) on oporce, na donjoj strani poprečnog nosača iznad
the places where the structure relies on stuba, nalaze se kratki elementi za prijenos
abutments, that is, on the bottom side of the horizontalnih sila od vjetra (tkzv. shear key) na
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
22
cross girder above the pier. oporce.

The inspection chambers are kept in all the U svim poprečnim nosačima su ostavljeni
cross girders. There are also inspection revizioni otvori. Iznad srednjih stubova su
chambers above middle piers left in the bottom ostavljeni i revizioni otvori u donjoj ploči za
slab for access from the pillars to the upper pristup iz stubova u gornju konstrukciju. Dužina
structure. The length of the cantilever of the konzole sandučastog nosača je 3.5m. Gornja
box girder is 3.5m. The top slab follows the ploča prati nagib kolovoza. Na krajevima mosta
gradient of the carriageway. There are su ojačane konzole, koje nose dilatacione
strengthened cantilevers carried by expansion spojnice, na cjelokupnoj širini presjeka. U
joints on the ends of the bridges along the svakom segmentu konstrukcije, prilikom
whole width of the section. During the izvodjenja, treba ostaviti 2 ventilaciona otvora
construction, there should be 2 ventilation Ø200 mm, u sredini segmenta, na 2 m visine od
shafts Ø200 mm kept in the each segment of donje ploče, po jedan u svakom spoljašnjem
the structure. They should be located in the rebru. Svi otvori u konstrukciji moraju biti
middle of the segment at 2 m height from the zaštićeni pocinkovanom čeličnom mrežom zbog
bottom slab (one in each outer web). All the ptica. Takodje, u svakom rasponu, u najnižoj
shafts in the structure must be protected with tačci, u sredini donje ploče, ostaviti drenažni
galvanized steel mesh because of the birds. otvor za ocjedjivanje eventualno dospjele vode
There must be a drain hole for the drain of unutar konstrukcije. Karakterističan poprečni
water that reached into the structure. It will be presjek konstrukcije je dat na slici ispod.
set in each span at the lowest point in the
middle of bottom slab. The typical cross
section of the structure is shown on the figure
below.

Comb layout arrangement of tendons Kombinovani raspored kablova

Internal tendons are 27Ø15.3 mm, 22 Ø15.3 Interni kablovi su 27Ø15.3 mm, 22 Ø15.3 mm,
mm, 19 Ø15.3 mm, 16 Ø15.3 mm and 12 19 Ø15.3 mm, 16 Ø15.3 mm i 12 Ø15.3 mm.
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
23
Ø15.3 mm. The tendons of the top slab and Kablovi gornje ploče i rebara se postavljaju i
webs are installed and stressed during the utežu tokom izvodjenja radova. Kablovi u gornjoj
construction works. The tendons in the top slab ploči su u tkzv. kombinovanom rasporedu. U
are in so called combined arrangement. svakom segmentu je predvidjeno sidrenje po 3
According to the plans, there will be anchorage kabla, po jedan uz svako rebro, naizmjenično sa
of 3 tendons in each segment, one next to lijeve i desne strane rebra, osim u presjecima
each web (alternating from left and right side of S17, S18 i S19, u kome se sidri 6 kablova, po 2
the web). This will not be applied in the uz svako rebro. Svi kablovi u gornjoj ploči se
sections S17, S18 and S19 because there will sidre u vutama. Kablovi u rebrima se povijaju na
be anchorage of 6 tendons (2 anchors next to dole i sidre u rebrima. Kablovi u donjoj ploči se
the each web). All the cables in the top slab utežu nakon spajanja nosača i oni se sidre u
are anchored in haunches. The cables in webs ankernim blokovima. I u gornjoj i u donjoj ploči
are bent down and anchored in webs. The su ostavljene cijevi za eventualne dodatne
cables in the bottom slab are stressed after the kablove. Cijevi kablova su plastične.
connecting of the girder. These cables are
anchored in the anchor blocks. The pipes for
possible additional cables are left in the top
slab and bottom slab. The pipes of the cables
are plastic.

Additional external cables 27Ø15.2 mm are U glavnim rasponima su predvidjeni dodatni


planned in main spans, there will be 4 eksterni kablovi 27Ø15.2 mm, po 4 u svakom
external cables in each field and 4 of them in polju i po 4 u svakom baznom komadu iznad
each serpent above middle pier. These srednjeg stuba. Ovi kablovi su rezervisani za
tendons are reserved for the bridge operation fazu eksploatacije mosta. U toku faze
stage. During the operation stage, the bridge eksploatacije biće prikupljane informacije o
deck stresses and deformations information naponima i deformacijama kolovozne ploče
shall be collected. When the stresses and mosta. Kada naponi i deformacije pređu
deformations exceed the designated values, projektovane vrijednosti, određeni broj
suitable numbers of external tendons shall be spoljašnjih kablova za PNP biće utegnut.
stressed appropriately. The tendons shall be Kablovi za PNP će se nabaviti kada to bude
procured when required and their stressing potrebno, a sile njihovog prednaprezanja biće
forces shall be limited to 0.65f. Cables are ograničene na 0.65 f. Ovi kablovi su ankerovani
anchored into strong cross girders-deviators u jake poprečne nosače – devijatore, iznad
above the pillars. The cables from the field and stubova. Kablovi iz polja i kablovi baznih
cables of serpents are overlapped on these segmenata se preklapaju na ovim devijatorima.
deviators. There are two kinds of deviators in U poljima postoje 2 vrste devijatora. Devijatori su
the fields. Deviators are cross beams in bottom poprečne grede u donjoj ploči, koje su na mjestu
slab which are strengthened with additional najveće promjene ugla kablova ojačane
cross girders on the place of biggest change of dodatnim poprečnim nosačima, povezanim sa
angles. Deviators are connected with side ribs bočnim rebrima i gornjom pločom. Lijevi i desni
and top slab. Left and right cable in each cell of kabl u svakoj ćeliji presjeka ima svoj poprečni
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
24
the section has it’s own cross girder. nosač.

Cable route is provided in typical points Trasa kablova je zbog obimnosti prikaza, data u
because of the large scope of table with karakterističnim tačkama, koje u potpunosti
precise positions of cables. Typical points odredjuju položaj kablova. Ostale tačke na
determine the position of cables completely. pravcu, izmedju datih tačaka, mogu se odrediti
Other points on straight line among the given tokom izvodjenja i fiksirati pomoću armature,
points can be defined during construction. koja je data u projektu.
These points can be fastened by the means of
reinforcement that is provided in Design.

Bridge deck is also transverselly prestressed Kolovozna ploča je i poprečno predapregnuta


with cables 3Ø15.3 mm on mutual distance of kablovima 3Ø15.3 mm na medjusobnom
75 cm (or even less than this). These cables rastojanju od 75 cm i manje. Ovi kablovi su
are adopted in order to eliminate completely usvojeni da bi se potpuno eliminisala mogućnost
the possibility of appearance of cracks in the pojave prslina u gornjoj zoni kolovozne ploče,
upper zone of bridge deck. This will increase čime se povećava trajnost konstrukcije.
the durability of the structure.

There are designed and constructive Armatura je proračunska i konstruktivna.


reinforcement. It is adjusted for passage of Prilagodjena je za prolazak cijevi kablova. Na
pipes of cables. Cable pipes will be priority on mjestima eventualne kolizije, cjevi kablova imaju
the places of possible collision, the prednost, armature se mora prilagoditi na licu
reinforcements have to be adjusted on the mjesta. U planu kablova je data i armatura za
spot. The reinforcement for fixing of the fiksiranje položaja cijevi kablova. Predvidjena su
positions of pipe cables is provided in layout of ojačanja na mjestima oslanjanja na ležišta,
cables. There is a strengthening planned on unosa sile prednaprezanja, tj. na mjestima kotvi,
the places of relying on bearings, places of na vezi ankernih blokova i ploče, devijatora, u
input of prestressing force as well as on the zoni ojačane gornje ploče na mjestu dilatacionih
positions of anchor bolts. The strengthening is spojnica, oko otvora. Pošto su zidovi za zaštitu
also planned on the connection of anchor od vetra ankerovani u beton pješačke staze,
blocks and slabs, deviators and in the zone of klasičan detalj sa bočnom armaturnom vezom
strengthened top slab on the position of kolovozne ploče i ivičnog vjenca nije dovoljan.
expansion joints around the opening. Since the Usvojena je dodatna vertikalna armaturna veza.
wind protection walls are anchored into the
concrete of pedestrian walkway, the common
detail that include side reinforcement joint of
deck slab and cornice is not enough.The
additional vertical joint is adopted.

3.1.3.3 The substructure of the bridge 3.1.3.3 Donji stroj mosta

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
25
The great height of piers, wind as dominant Velika visina stubova, vjetar kao dominantni
influence and rather big differences in the pier uticaj i relativno velike razlike u visini stubova su
heights caused kind, shape and law of change uslovile vrstu, oblik i zakon promjene po visini
per height of the cross section. Shorter piers poprečnog presjeka. Da bi se ujednačili podužni
P1 and P5 that would receive more significant uticaji na srednje stubove, kraći stubovi P1 i P5,
influences are less rigid in order to equalize the koji bi “navukli” veće uticaje, su manje krutosti, a
longitudinal influences on the middle piers. viši stubovi su veće krutosti do visine uklještenja
Higher piers are more rigid up to the height of kraćih, a dalje, do pune visine, iste krutosti kao i
rigid joints of shorter ones. Furthermore, the niži. Na taj način se dobija i estetski povoljno
high piers are rigid up to the full height, their rješenje, svi stubovi su bočno transparentni do
rigidity is the same as the rigidity of short ones. približno iste visine. Srednji stubovi P1 i P5 su
This is how the aesthetically favorable solution formirani od 2 sandučasta poprečna presjeka,
is accomplished, all the piers are laterally postavljenih paralelno po dužoj strani, poprečno
transparent up to the approximately same na pravac mosta. Oba presjeka su identična,
height. Middle piers P1 and P5 consist of 2 box dvoćelijska. Oblik presjeka je modifikovani
cross sections that are set parallely along the pravougaoni. Po visini, ukrućeni su
longer side, that is, transversely to the bridge horizontalnim rebrom, na polovini visine.
axis. Both sections are identical, that is, both Razdvojeni presjeci u poprečnom pravcu i
sections are two cell sections. The shape of aerodinamički povoljan oblik bočnih površina
the section is modified rectangular. The umanjuju uticaje vjetra na stubove. Na dužim
sections are stiffed with horizontal rib at the stranama je udubljenje, koje takodje umanjuje
half of the height. The sections which are uticaj vjetra, tako što objezbedjuje efikasno
separated in transverse direction and odvajanje vazdušnih vrtloga od površine stuba.
aerodynamically favorable shape of side areas Spoljašnje dimenzije ovih stubova su 15 x 3.5 m.
reduce the wind influence on the piers. There Debljine zidova su 80 cm i 170 cm, i konstantne
is a recess on the longer sides which allows su po visini. Na svim mjestima veze za
the efficient separation of air vortex and pillar horizontalne ploče (rebra) i medjusobno,
surface. External dimensions of these pillars predvidjene su vute. Iznad temelja i na vrhu,
are 15x3.5 m. The thicknesses of walls are 80 formirana je jedinstven pun presjek, visine 3 m.
cm and 170 cm. These thicknesses are Puni presjeci, kao i masivne vute, objezbedjuju
constant per height. There are haunches pravilan prijenos sila sa konstrukcije u stubove i
planned on all the places of connections for iz stubova u temelje. U gornjoj ploči se nalazi
horizontal slabs (ribs). There is a unique cross otvor za revizioni pristup u konstrukciju. U svakoj
section of 3 meter height above the foundation ćeliji presjeka su ostavljena po 2 naspramna
as well as on the top. Full sections and large ventilaciona otvora, na svakih 5 m visine. Na
haunches enable right force transfer from the dnu stuba, u najnižoj tačci, su ostavljeni i otvori
structure into the pillars and from the pillars za drenažu, prečnika 10 cm, radi odvoda
into the foundation. There is an inspection eventualne vode iz unutrašnjosti stuba. Ovi
manhole in the top slab. There are two otvori su u nagibu ka spoljašnjoj strani od 5%. U
opposite ventilation shafts left in each cell of stubu još postoje i reviziona vrata, stepenice sa
the section at each 5 m of height. There are ledjobranima i platformama za odmor na svakih

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
26
also drainage holes in the bottom of the pier at 10 m visine. Svi otvori u konstrukciji moraju biti
the lowest point. Their diameter is 10cm and zaštićeni pocinkovanom čeličnom mrežom zbog
they are left there to take away water that can ptica.
possibly appear from the inside of the pier. The
slope of these holes towards the exterior side
is 5%. There are also inspection doors, stairs
with safety hoops and rest platforms at each
10 m of height. All the openings in the structure
must be protected with galvanized steel mesh
because of the birds.

Cross section on the upper part of the pillars Poprečni presjek na gornjem dijelu stubova P2 –
P2-P4 is identic as the cross section of piers P4 je identičan kao i kod stubova P1 i P5. Dva
P1 and P5. Two box sections of the top part of sandučasta presjeka gornjeg dijela stuba se
the pillar connect into one unique cross section spajaju u jedinstven poprečni presjek donjeg
of the bottom part of the pillar. Outer dijela stuba. Spoljašnje dimenzije ovako
dimensions of modified rectangular cross formiranog, modifikovanog pravougaonog
section formed on this way are 17.14x11m. presjeka, su 17.14 x 11 m. Debljine zidova su
The thicknesses of walls are increased to 100 povećane na 100 cm, podužni zidovi i 120 cm,
cm, the thickness of longitudinal walls reaches bočni zidovi. U sredini je rebro, debljine 80 cm.
120 cm. There is a web in the middle, it’s Spoljašnje ivice presjeka zadržavaju nagibe i
thickness is 80cm. Outer edges of the sections žljebove, iste kao i na gornjem dijelu presjeka.
keep the slopes and notches which are the Kao i kod stubova P1 i P5, i ovde su puni
same as the one on upper part of the section. presjeci, debljine 3 m, na vrhu, dnu i prelazu
The sections here are also full sections, just izmedju dvije vrste presjeka. Revizioni otvori,
like the sections of piers P1 and P5. It’s vrata, revizione stepenice, ventilacioni i drenažni
thickness is 3 m at the top, bottom and otvori, se postavljaju na isti način kao i na P1 i
crossing between two kinds of sections. P5.
Inspection chambers, inspection doors,
inspection stairs, ventilation shafts and
drainage holes are set as the ones at pillars P1
and P5.

Main reinforcement of middle piers continues Glavna armatura srednjih stubova se nastavlja
with mechanical splicing whose bearing mehaničkim nastavcima, koji moraju imati veću
capacity must be higher than the bearing nosivost nego osnovni material armature.
capacity of main material of reinforcement. The Nastavci se postavljaju tako da ne bude više od
way of setting the splicing enables that there is 50% nastavljene armature u jednom presjeku.
no more than 50% of splice reinforcement in Nastavljanje je vezano za predvidjene segmente
one section. Splicing is connected to za izvodjenje.
construction segments which were planned.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
27
End abutments are massive. Considering that Krajnji oporci su masivni. Stubna platna su
wall sheets transfer the reactions from debljine 2.5 m, s obzirom da prijenose reakcije
structures whose spans are 95m and 125m, sa konstrukcija raspona 95 i 125 m. Pošto je
their thickness is 2.5m. Parapet wall is almost parapetni zid visine skoro 6 m, njegova debljina
6 m high, so it’s thickness is 80 cm. Sufficient je 80 cm. Dovoljna krutost parapetnog zida, kao
rigidness of parapet wall which is supporter for oslonca za dilatacionu spojnicu, je i preduslov
expansion joint is the precondition of it’s njene trajnosti. Na ovom zidu se nalaze kratki
durability. There are short elements on both elementi, obostrano, jedan za oslanjanje
sides of this wall. The purpose of one element prelazne ploče, a drugi dilatacione spojnice.
is the supporting of crossing slab, the purpose Parapetni zid je vezan za stubno platno jakom
of another one is supporting of expansion joint. vutom. Ova vuta i gornji dio stubnog platna
Parapet wall is connected to wall sheet by the formiraju skrivenu ležišnu gredu. Utezanjem
means of strong haunch. This haunch and betona grede uzengijama i vertikalnim
upper part of the wall sheet form hidden zategama, postiže se bolji prijenos sila iz
bearing beam. Ther better transfer of forces kvadera. Na ležišnoj gredi postoje 2 vrste
from bearing concrete cube will be achieved by kvadera. Kvaderi za prijenos vertikalnih sila i
stressing the beam concrete with stirrups and kvaderi za prijem horizontalnih sila, prije svega
vertical tie-rods. There are two kinds of bearing od vetra. Kvaderi za prijem horizontalnih sila su
concrete cubes on the bearing beam: bearing visine oko 140 cm, što je diktirano veličinom
cubes for transfer of vertical forces and bearing potrebnih ležišta. Ova visina je odredila i visinu
cubes for receiving of horizontal forces (wind kvadera za prijem vertikalnih sila. Visina kvadera
forces, primarily). The height of bearing cubes je takva da su naponi zatezanja usled lokalnih
for receiving of horizontal forces is about napona pritiska ispod ležišta, primljeni jakom
140cm and this is determined by the size of the armaturom u samim kvaderima. Ne prenose se
necessary bearings. This height also defined u ležišnu gredu.
the height of bearing cubes for the receiving of
vertical forces. The height of the bearing cubes
enables the strong reinforcement in bearing
cubes to receive the tensile stress caused by
local compressive stress under the bearing.
The tensile stress is not transferred into
bearing beam.

Wing walls of the end abutments are 50 cm Krilni zidovi krajnjih oporaca su debljine 50 cm,
thick. Part of these walls are standing walls, delimično stojeći, a delimično viseći. Viseća krila
part of them are hanging walls. It all depends su različite dužine na lijevoj i desnoj strani, u
on terrain gradient and possibility of forming of zavisnosti od nagiba terena i mogućnosti
slope round heads. The walls are strengthened formiranja kegli. Zbog dužine, zidovi su ojačani
with beams because of the length. There are gredama. Na gornjim ivicama krilnih zidova se
cantilevers on top edges of wing walls that nalaze konzole, koje nose pješačku stazu i
carries the pedestrian walkways and instalacione kanale u njima, istog presjeka kao i

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
28
installation channels inside it (with the same na mostu. Ove konzole djeluju statički povoljno
section as the one on the bridge). These na krila, jer ukrućuju gornju ivicu. Prelazna ploča
cantilevers have statically favorable influence je dužine 3.7+2.5 m, i postavlja se u nagibu 10%
on wings because they stiffen the top edge. u odnosu na nagib nivelete. Ispod ploče se
The length of crossing slab is 3.7+2.5m and it izvodi podložni beton.
is installed at the gradient of 10% in the
relation to gradient of vertical alignment. Plain
concrete is constructed under the slab.

There are protection walls on the bearing Na ležišnoj gredi su zaštitni zidovi (“maske”), koji
beam. They do not allow unauthorized person onemogućavaju pristup neovlašćenim licima u
enter the area around bearings and expansion prostor oko ležišta i dilatacionih spojnica. Pristup
joints. Authorized person can access the area ovlašćenim licima je omogućen vratima u
through the doors in protection walls and maskama i pristupnim stepenicama. Radi
access stairs. Bottom surface is shaped in two eventualnog prodora vode u prostor za reviziju u
direction slope by the means of slope concrete okviru obalnih oporaca, donja površina je
due to possible water penetration into the betonom za pad oblikovana u dvostranom padu,
inspection area within the abutments. It is bočno, ka otvorima u maskama. Prednja gornja
side-shaped towards the apertures in face površina ležišne grede je u nagibu ka parapetu,
cover walls. The front top area of bearing beam tj. ovom kanalu.
is in gradient towards the parapet.

3.1.3.4 Foundations 3.1.3.4 Temelji

Considering the geotechnical conditions, S obzirom na geotehničke uslove odabrano je


shallow foundation is chosen. All the pillars are plitko fundiranje. Svi stubovi su fundirani u
founded in limestone rock, except the pillar P3 krečnjačkoj stijeni, osim stuba P3, koji je
which is funded in terrace sediments, fundiran u terasnim naslagama,
conglomerates. According to the konglomeratima. Prema preporukama u
reccomendations from geotechnical elaborate, geotehničkom elaboratu, usvojeno je da temelji
it is adopted for the foundations to be located budu minimum 1 – 2 m u geotehničkoj sredini
in geotechnical environment marked with “C” označenoj sa “C”. Zbog velikog podužnog i
for at least 1-2m. The depths of founding of poprečnog nagiba terena, dubine fundiranja
edges of foundation towards the hill are very ivica temelja ka brdu su veoma velike. Iako su
high due to great longitudinal gradient and dozvoljeni naponi izuzetno visoki, čak i za
cross gradient of the terrain. Although the krečnjak, odredjivanju dimenzija temeljnih stopa
allowed stresses are extremely high even for se pristupilo sa velikim stepenom sigurnosti, jer
the limestone, high degree of safety was je stena ispucala i može biti lokalno nepovoljna.
applied during the defining of dimensions of
footing because the rock is cracked and it can
be locally unfavorable.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
29
Benched foundations of middle piers provide Stepenasti temelji srednjih stubova obezbjedjuju
safe and uniform transfer of forces from pier siguran i ravnomjeran prijenos sila iz stuba u tlo.
into the soil. The gradient of force transfer is in Nagib prijenosa sile je u skladu sa važećim
accordance with valid regulations. The propisima. Dimenzije temelja stubova P1 i P5 su
dimensions of foundations of piers P1 and P5 30x26 m, a stubova P2 – P4 33x26 m. Ukupna
are 30x26m and the dimensions of piers P2-P4 visina svih temelja je 7.5 m. Sve stepenice
are 33x26m. The total height of all the temelja, kao i odstojanje ivice stuba ii vice
foundations is 7.5m. The height and width of all temelja, su 2.5 m visine i širine. Ispod temelja je
the foundation stairs and distance of pillar predvidjen sloj podložnog betona, debljine 20
edge and foundation edge are 2.5m. There is cm širine veće od temelja za po 20 cm.
an underlayer concrete under the foundation
whose thickness is 20 cm.It’s width is larger
than foundation for 20 cm.

Bigger parts of foundations of end piers are set Temelji krajnjih stubova su svojim većim dijelom
under the embankment. There are 2 reasons postavljeni ispod nasipa. Ovakav položaj je
why this position is more favorable: the povoljniji zbog dva razloga: radi oslanjanja
purpose of the relying of standing wing walls stojećih krilnih zidova i radi uravnoteženja
and the purpose of balancing of influences uticaja sa konstrukcije i od pritiska tla. Na taj
exerted from structure and soil pressure. On način je kontrolisano i eventualno slijeganje, da
that way, eventually settlement is also bude ravnomjerno. Gornja površina temelja je u
controlled to be uniform. The upper area of the podužnom nagibu. Visina temeljne stope je 2.5
foundation is at longitudinal gradient. The m, u presjeku uz stubno platno. I kod ovih
height of footing at the section beside the wall temelja je podložni beton 20 cm.
sheet is 2.5m. The thickness of underlayer
concrete that is applied at these foundations is
20cm as well.

3.1.4 Static calculation 3.1.4 Statički proračun

3.1.4.1 Loads 3.1.4.1 Opterećenja

Loads and load combinations are applied on Opterećenja i njihove kombinacije su uzete
the basis of “Rulebook on technical norms for prema “Pravilniku o tehničkim normativima za
defining of values of bridge loads”, odrijedjivanje veličine opterećenja mostova”,
requierements of TOR and valid regulations. prema zahtjevima Projektnog zadatka i važećih
The section of the girder is symmetrical, so propisa. Presjek nosača je simetričan, pa od
there are no torsional impacts exerted by stalnih opterećenja nema torzionih uticaja.
permanent loads. “Midas” engineering Programski paket “Midas” omogućuje nanošenje
software enables applying of permanent loads stalnog opterećenja po fazama izvodjenja. Ona
per construction stages. It includes self-weight, obuhvataju sopstvenu težinu, dodatno stalno

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
30
additional permanent load, prestressing and opterećenje, prednaprezanje i uticaje tečenja i
influences of creep and shrinkage.The input skupljanja. Ulazni podaci, koji su korišćeni u
data which are used in the program for programu za kablove za prednaprezanje su:
prestressing tendons are: ultimate tensile granična čvrstoća na istezanje je fpk=1860MPa,
strength fpk=1860MPa, adopted prestressing usvojene sile prednaprezanja nijesu veće od
forces are not higher than 0.75fpk=1395MPa, 0.75fpk=1395MPa, stopa relaksacije kablova za
relaxation rate of prestressing tendons is 2.5% prednaprezanje je 2.5%, a modul elastičnosti
and the elasticity modulus is 195000 MPa. 195000MPa. Koeficijent trenja je μ=0.2, a
Coefficient of friction is μ=0.2 and coefficient of koeficijent uticaja trenja usled nepredvidjenih
friction impact due to loss coefficient voltage krivina je k=0.002 rad/m. Uticaji od tečenja i
per unit length is k=0.002 rad/m. The skupljanja su uzeti prema propisima CEB-FIB
infleunces of creep and shrinkage are applied 1990, koji ovaj fenomenen tretiraju gotovo
in accordance with regulations of CEB-FIB identično kao i BAB 87. Pokretno opterećenje
1990 which treat this phenomenon on almost je šema V600+300 za mostove I kategorije. Za
the same way as regulations BAB 87. Live load ovakve raspone, dinamički factor je 1.0.
is V600+300 for first category bridges. Opterećenja od tečenja i skupljanja tokom
Dynamic factor for these spans is 1.0. The load eksploatacije objekta se računaju programski.
of creep and shrinkage during the structure Uticaji od vjetra su uzeti u skladu za zahtjevima
exploitation is calculated by program. The wind važećih standarda JUS.UM1.110-113 i, zbog
influences applied are in accordance with značaja mosta, prema Evropskim propisima za
requests of valid standards JUS.UM1.110-113 uticaje od vjetra u podužnom pravcu na
and European regulations for wind influences konstrukciju mosta.
in longitudinal direction to bridge structure (due
to importance of the bridge).

Seismic load are applied in accordance with Opterećenja od zemljotresa su uzeta prema EN
EN 1998-2 and this is in compliance with TOR 1998-2 što je u saglasnosti sa ProjektnIm
and Detailed Seismic Study. Earthquake zadatkom i Detaljnom seizmičkom studijom.
T=475 god. and T=95 god was considered. Razmatran je zemljotres T=475 god. i T=95 god.
Maximum earthquake acceleration for return Za zemljotres povratnog perioda od 95 godina
period of 95 years is 0.096g. As for the za maksimalno ubrzanje se uzima 0.096g. Što
earthquake of return period of 475 years, se zemljotresa povratnog perioda od 475 godina
maximum acceleration is 0.203g.As for the tiče, za maksimalno ubrzanje se uzima 0.203g,
possible maximum effect of action E, the Za vjerovatni maksimalni efekat dejstva E može
following can be applied: se uzeti:

1.0EQ x +0.3EQ y +0.3EQ z 1.0EQ x +0.3EQ y +0.3EQ z


0.3EQ x +1.0EQ y +0.3EQ z 0.3EQ x +1.0EQ y +0.3EQ z
0.3EQ x +0.3EQ y +1.0EQ z 0.3EQ x +0.3EQ y +1.0EQ z

Since the soil the structure is founded in is Pošto je tlo u kome je fundiran objekat stijena,
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
31
rock, type A soil is adopted. Behaviour factor usvojena je kategorija tla “A”. Faktor ponašanja
q=1 is adopted due to importance of the je zbog značaja mosta usvojen q=1.0. Faktor
bridge. Importance factor is 1.3 and damping značaja 1.3 i faktor prigušenja 5%.
factor is 5%.

Load combinations are determined in Kombinacije opterećenja su odrijedjene prema


accordance with Rulebook for bridges. Safety Pravilniku za mostove, a koeficijenti sigurnosti
coefficient for dimensioning of reinforced za dimenzionisanje armirano betonskih
concrete sections are determined on the basis presjeka, prema Pravilniku za beton i armirani
of Rulebook for concrete and reinforced beton. U slučaju analize glavnog nosača, stuba i
concrete. As for the analysis of main girder, temelja u fazi izvodjenja, u obzir se uzima
pillar and foundation during the construction najgori mogući scenario, a to je otpadanje
stage, the worst possible case is taken into “krletke” na jednoj strani ili otpadanje segmenta
consideration, that is, falling of the form nosača.
traveller on one side or falling of the girder
segments.

(1) FT’- falling of of one side of form traveler (1) FT’ –otpadanje jedne strane “krletke”

(2) A- the weight of girder section (2) A – težina presjeka nosača

(3) W-wind load during the construction stage. (3) W –opterećenje vjetrom u fazi izvodjenja
Double part of dynamic reaction is taken into
U slučaju da se dogodi otpadanje presjeka
consideration in the case the girder section or
nosača ili “krletke”, uzima se u obzir dupli dio
form traveler fall off. Therefore, there are 2FT
dinamičke reakcije. Stoga, u kombinaciji
and 2A in load combination.
opterećenja postoje 2FT i 2A.

Combinations for operation phase are created Kombinacije za fazu eksploatacije su formirane
for 2 cases: for bridge structure and za 2 slučaja, za mostovsku konstrukciju, kao za
prestressed structures (PB 71) as well as for prednapregnute konstrukcije (PB 71), i za
piers and other elements made of reinforced stubove i ostale armirano betonske elemente.
concrete. There are also two groups of Za armirano betonske elemente su takodje
combination for reinforced concrete elements formirane dvije grupe kombinacija, kada stalno
(as permanent load exerts favorable and opterećenje djeluje povoljno i nepovoljno (BAB
unfavorable influences BAB 87). 87).

Active soil pressure for determination of Kod krajnjih oporaca je korišćen aktivni pritisak
influence on all the movable structure tla za odrijedjivanje uticaja na sve pomerljive
elements and checking of global factors was elemente konstrukcije i provjeru globalnih
applied at end abutments. The soil pressure at faktora. Za dimenzionisanje stubnog platna je
rest was applied for dimensioning of wall sheet upotrebljen pritisak tla u miru, zbog činjenice da
due to the facts that the wall sheet is rigid and je platno veoma kruto, a stub je fundiran na

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
32
that the pillar is founded on the rock. stijeni.

3.1.4.2 Structure modelling 3.1.4.2 Modeliranje konstrukcije

Structure model is created and calculated in Model konstrukcije je napravljen i sračunat u


program package “Midas”. The whole structure programskom paketu “Midas”. Modelirana je
without end abutments was modelled. It is a cjelokupna konstrukcija, bez krajnjih oporaca.
line model consisted of 461 elements which Model je linijski, sastavljen od 461 elementa,
are connected with nods. Pillar segments and povezanih čvorovima. Stubni i gredni elementi
pier segments are modelled in accordance with se modeliraju prema svojim stvarnim svojstvima.
their actual properties. The properties of Svojstva krutosti se definišu u odnosu na
rigidness are determined in relation to the momente i sile u odnosu na 3 ose lokalnog
moments and forces due to 3 axis of local koordinatnog sistema štapova: i uvijanje usled
coordinate system of members. Shear torsion smicanja i efekti torzije su obuhvaćeni u
and torsion effects are included in the analysis analizama, kao i aksijalne deformacije i
as well as axial deformation and flexural deformacije pri savijanju.
deformations.

Cables as elements of system are also U model su uneti i kablovi kao elementi sistema.
enetered into model. The materials and their Definišu se materijali i njihova svojstava, koja su
properties which are changeable are defined. vremenski promenljiva. Po predvidjenim
The phases are given to the model on the stvarnim fazama izvodjenja se modelu dodjeljuju
basis of actual phases which are planned. The faze. Svakoj fazi se definiše dužina trajanja i koji
runtime of each phase is determined. It is also elementi i opterećenja se uključuju (ili isključuju)
defined which elements of load are included or u toj fazi. Uključivanje elemenata od betona je
exluded during this phase.The inclusion of povezano sa vremenski zavisnim efektima
concrete elements is related to time dependant tečenja i skupljanja, koji su obuhvaćeni
effects of creep and shrinkage which are programom. Vremenski zavisna svojstva betona
included in the program. Time dependant se utvrdjuju na osnovu vlažnosti sredine i
properties of concrete are defined on the basis dimenzija poprečnog presjeka.
of humidity of environment and dimensions of
cross section.

After the construction stages have been Nakon modeliranja faza izvodjenja, konstrukcija
modeled, the structure is stepped through time će “zakoračiti kroz vrijeme” do dana 3650-og da
to day 3650 to allow all time dependent effects bi se omogućilo svim vremensko zavisnim
to occur. It is also essential in statically efektima da se dogode. U statički neodredjenim
indeterminate structures to sum up all konstrukcijama je takodje krucijalno sumirati sve
locked-in forces that result from various stages “nepromjenljive sile” koje potiču iz različitih faza
of structural systems until day 10,000. konstruktivnih sistema do dana 10
Additional loads are placed on the structure 000-og. Dodatna opterećenja se smještaju na
(such as live load, temperature gradientand konstrukciju (na primer, pokretno opterećenje,
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
33
support settlement, as appropriate), and temperaturni gradijent, slijeganja stubova) i
analyzed for initial (at end of construction) and analiziraju za početne (na kraju izvodjenja) i
final conditions at day 3650. konačne uslove na dan 3650-ti.

Finite Element Method (FEM) is used for the Metoda konačnih elemenata se koristi za
structural analysis of MORACICA Bridge. The strukturnu analizu mosta MORAČICA.
structure is separated into small 3-dimensional Konstrukcija se razdvaja na male
elements. The model is formulated based on trodimenzionalne elemente. Model se formira na
construction sequence of MORACICA Bridge, osnovu redoslijeda izvodjenja mosta
taking into account of nonlinear factors such as MORAČICA, (uzimajući u obzir nelinearne
P-Delta effect, to analyze the changes of faktore kao što su P-Delta efekti) kako bi se
internal stress and deformation in different analizirale promjene unutrašnjeg napona i
stages. deformacije u različitim fazama.

Generally, the distributions of axial forces, Uopšteno govoreći, raspodijela aksijalnih sila,
bending moments and vertical shear forces are momenata savijanja i vertikalnih sila smicanja se
calculated by an elastic analysis assuming the proračunava elastičnom analizom pod
concrete to be uncracked and unreinforced pretpostavkom da je beton bez prslina i
( due to these loadings on the structural nearmiran (upravo zbog ovih opterećenja). Pune
members).The full flanges may be taken as flanše mogu biti uzete kao efektivne u analizi
effective in analyzing of the structure. konstrukcije. Iz tog razloga, čitava ploča mosta
Therefore, the entire deck slab is modeled as se modeluje kao linijski element da bi se
single line member in order to minimize the minimalizovala veličina modela konačnog
size of finite element model. elementa.

The piers are fixed on to the girder with elastic Stubovi su kruto vezani za nosač elastičnim
springs, with very high stiffness of all oprugama, kojima je data veoma visoka krutost,
connection characteristics. Bottoms of the Pier po svim karakteristikama veze.. Plitki temelji se
P1~P5 are applied with spread foundation, na donjem dijelu stuba P1, P2, P3, P4 i P5
all-direction constrain of the foundation base vezuju konstrejnovima za stub u svim pravcima,
are applied with fixed constrain simulation .2 sa ustaljenom simulacijom konstrejna. Dva
bidirectional movable bearings and one ležišta pokretna u dva pravca i jedno poprečno
transverse wind-resistance bearing are ležište za prijem poprečnih sila od vjetra se
installed at Abutment A0 and A1. postavljaju na oporcima A0 i A1.

End abutments are calculated in Tower Obalni oporci su sračunati u programskom


programme package. It is a space model paketu “Tower”. Model je prostorni, sastavljen
consisted of surface elements and beam od površinskih i grednih elemenata. Uticaji sa
elements. The influences from the structure konstrukcije su preneti iz modela u „Midas-u“.
are taken from model created in “Midas”. Materijali i geometrijske karakteristike
Materials and geometrical characteristics odgovaraju stvarnim karakteristikama. Linijski
matches actual properties. Line constraints are konstrejnovi su upotrebljeni za povezivanje osa
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
34
applied for the connecting of slab axis because ploča, radi realnijeg modeliranja.
of more real modelling.

3.1.4.3 Result of Girder Analysis 3.1.4.3 Rezultati analize nosača

1) Bridge structure 1)Mostovska konstrukcija

The stresses per all the phases for Za faze izvodjenja, u rezultatima proračuna su
construction stages are provided in calculation dati naponi po svim fazama. Sa dijagrama se
results. It can be seen on the diagram that vidi da nisu prekoračene dozvoljene vrijednosti.
allowed values are not exceeded. Two Nakon toga su analizirane dvije moguće
possible extreme situations that can occur ekstremne situacije u toku izvodjenja, opisane u
during the construction are analyzed after that. dijelu 4.1 Opterećenja konstrukcije. Razmatrana
These situations are described in section 4.1 je situacija u kojoj su maksimalne konzole na
“Structure loads”. The situation when maximal obe strane stubova P1 i P3. Uzeto je u obzir
cantilevers are on both sides of piers P1 and opterećenje vjetrom, pad segmenta grede sa
P3 is considered. The wind load, fall of beam jedne strane i uticaji viseće oplate, tako da su za
segment from one side and influences of proračun korišćene sljedeće kombinacije
hanging formwork are considered, so the opterećenja, CBS-2: SC+FT+PR+SK+W i
following load combinations were used for CBS-3: SC+FT+PR+SK+W+2FT’+2A.
calculation: CBS-2: SC+FT+PR+SK+W i Provjereni su glavni normalni naponi i glavni
CBS-3: SC+FT+PR+SK+W+2FT’+2A. Main naponi zatezanja i utvrdjeno je da su u
normal stress and main tensile stress are dozvoljenim granicama.
checked and it is confirmed that they do not
exceed allowed values.

Extreme values of normal pressure stress for U fazi eksploatacije, za merodavne kombinacije
controlling load combinations during opterećenja, ekstremne vrijednosti normalnih
exploitation phase are 18.18 MPa on the napona pritiska su 18.18 MPa na donjoj ivici
bottom edge of the section and 18.48 on the presjeka i 18.48 na gornjoj. Naponi zatezanja su
top edge of the section. Max. tensile stresses 0 MPa (potpuno prednaprezanje). Glavni naponi
are 0.76 MPa and this means that there is no zatezanja su max. 0.76 MPa, što znači da nije
need for reinforcement. potrebno osiguranje armaturom.

Maximum deflection of live load is 49mm and Ugibi od pokretnog opterećenja su max. 49 mm i
minimum deflection of live load is 22mm. The min. 22 mm (nadvišenje). Ugibi tokom
deflections that appear during the construction izvodjenja, su dati po fazama, ali oni su
are provided per phases, but they are only orjentacioni. Tokom izvodjenja, specijalna
approximate. Spatial supervision company will kompanija za nadzor će kontrolisati i provjeravati
control and check the elevation of beam kote (nivelaciju) segmenata grede. Svojstva
segments during construction. The properties betona se vremenom mijenjaju. Mogu se
of concrete change as the time passes. They korigovati za sastav betona (na primer, agregat
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
35
can be adjusted for concrete composition (for krečnjaka), stopu otvrdnjavanja i temperaturu
example, limestone aggregate), concrete okoline.
hardening rate and temperature of
environment.

Safety factors against failure in typical sections Koeficijenti sigurnosti od loma u karakterističnim
have high values. presjecima imaju visoke vrijednosti.

The structure calculation in transverse Proračun konstrukcije u poprečnom pravcu je


direction is carried out on three typical section uradjen na 3 karakteristična modela presjeka:
models: S1 (the thickness of web is 65cm), S1 (debljina rebra je 65cm), S14 (debljina rebra
S14 (the thickness of web is 55cm), S24 (the je 55cm), S24 (debljina rebra je 45cm). U gornjoj
thickness of web is 45 cm).Safety factors ploči, kao prethodno napregnutoj, su provjereni
against failure, appearance of cracks and naponi, koeficijenti sigurnosti od loma i pojave
stresses are checked in top slab which has prslina. Rebra i donja ploča su dimenzionisani
been previously prestressed. Webs and kao armirano betonski elementi i dobijena je
bottom slab are dimensioned as reinforced računska armatura presjeka. Provjereni su i
concrete elements and design reinforcement of naponi smicanja.
section is obtained. The shear stresses are
checked as well.

2) Pillars 2) Stubovi

Typical sections on all middle piers, top, Za stanje eksploatacije, dimenzionisani su


bottom and place of section change on pillars karakteristični presjeci na svim srednjim
P2-P4 are dimensioned for exploitation stubovima, na vrhu, dnu i na mjestu promjene
conditions. The shear stresses are checked as preseka na stubovima P2 – P4. Provjereni su
well. There is no need for design reinforcement naponi smicanja. Ni na jednom stubu nije
on any of the pillars. Crack calculation for potrebna računska armatura. Proračun prslina
controlling load combinations proved that za merodavne kombinacije opterećenja je
apertures are satisfactory and do not exceed pokazao da su otvori zadovoljavajući i u
allowable limits. granicama dozvoljenih.

P delta analysis is carried out by finite element Metodom konačnih elemenata je izvršena
method. Secondary effects are considered on P-delta analiza, a sekundarni efekti su uzeti u
the basis of P-delta analysis. obzir na osnovu analize P-delta.

After the analysis is carried out, middle piers Nakon toga, srednji stubovi su provjereni i za
are checked for construction stage as well. fazu izvodjenja.

The reinforcement reqiered in wall sheets of Potrebna armatura u stubnim platnima krajnjih
end abutments is minimal. The other elements oporaca je minimalna. Ostali elementi su
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
36
are dimensioned on the basis of results dimenzionisani prema dobijenim uticajima.
obtained. Safety coefficients for overturning Koeficijenti sigurnosti na klizanje i preturanje su
and sliding are satisfied. zadovoljeni.

3) Foundations 3) Temelji

Dimensioning was carried out for foundations Za temelje srednjih stubova je radjeno
of middle piers. The soil stress for all dimenzionisanje i provjera napona na tlo za sve
controlling load combinations is checked for merodavne kombinacije opterećenja, za fazu
exploitation phase and construction stage. The eksploatacije i za fazu izvodjenja. Temelji su
foundations are dimensioned for flexure and dimenzionisani na savijanje i smicanje. Prilikom
shearing. Reduction of part of the force odrijedjivanja sile smicanja, uzeta je u obzir
(reactive load) which directly “flows” into the redukcija dijela sile (reaktivnog opterećenja),
pillar was considered during the defining of koja se direktno “uliva” u stub. Maksimalni
shear force. There are maximum soil stresses naponi na tlo su na stubu P3, središnji oko 0.63
on the pillar P3, average soil stresses are MPa, a ivični oko 1.3 MPa, što je daleko manje
about 0.63 MPa and edge soil stresses are od dozvoljenih 8 MPa. Za sve srednje stubove je
about 1.3 MPa. This is far less than the provjerena sigurnost na klizanje i preturanje, što
allowed 8 MPa. The safety coefficients for je naročito, i prije svega, bitno za fazu
overturning and sliding are checked for all izvodjenja.
middle piers. This is particularly important for
construction stage.

The foundations of end abutments are Temelji krajnjih oporaca su armirani minimalnom
reinforced with minimal reinforcement. The armaturom. Dobijena slijeganja opravdavaju
settlements obtained justify the adopted usvojenu krutost zamjenjujućih elastičnih
stiffness of replacing elastic soil support in the oslonaca tla u modelu. Naponi na tlo krajnjih
model. The stresses of the soil of end stubova su daleko ispod dozvoljenih vrijednosti i
abutments are far beyond the allowed values iznose 0.4 MPa, središnji, 0.52 MPa ivični od
and it’s value is 0.4 MPa. Edge stress of soil of kombinacije stalnog i dopunskog opterećenja i
combination of permanent load and additional 0.92 MPa ivični od kombinacije stalnog
load is 0.52 MPa. Edge stress of permanent opterećenja i zemljotresa.
load and earthquake combination is 0.92MPa.

4) Bearings and expansion joints 4) Ležišta i dilatacione spojnica

The tables that include reqiered properties of U statičkom proračunu su date tabele za
bearing per forces and strains are provided in zahtijevanim karakteristikama ležišta, po silama i
static calculation. Maximum displacements po pomjeranjima. Maksimalna pomjeranja,
increased with 1.2 factor on the basis of Bridge uvećana faktorom 1.2 po Pravilniku za mostove,
rulebook are 411mm on the position of su 411 mm na mjestu oporca A0 i 727 mm na
abutment A0 and 727 mm on the position of
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
37
abutment A1. mjestu oporca A1.

3.1.5 The description of other bridge 3.1.5 Opis ostalih elemenata mosta
elements

3.1.5.1 Bearings 3.1.5.1 Ležišta

All the bearings are installed on bearing Sva ležišta su postavljena na kvadere, radi lakše
concrete cubes for the purpose of easier zamjene i pristupačnosti. Na krajnjim oporcima
replacement and accessibility. The chamber je izmedju završetka glavnog nosača i parapeta
for inspection of bearing is formed on the end formirana komora za pregled ležišta. Sva ležišta
abutments between the closure of main girder za prijem vertikalnih sila su sferna, pomjerljiva u
and parapet. All the bearings for receiving of svim pravcima. Ležišta za prijem horizontalnih
vertical forces are spherical bearings and they sila su sa spriječenim pomjeranjima u
are movable in all directions. Moving in vertical vertikalnom pravcu. Potrebne sile, pomjeranja i
direction of the bearings for receiving of rotacije za usvajanje su date u statičkom
horizontal forces have been prevented. proračunu i na crtežu. Na crtežu su prikazana
Requered forces, movings and rotations for usvojena ležišta, ali mogu biti usvojena i druga,
adoption are provided in the static calculation koja zadovoljavaju uslove iz tabele.
and drawing. The bearings adopted are shown
on the drawing, but the other bearings that
meet the conditions from the table can be
adopted as well.

3.1.5.2 Expansion joints 3.1.5.2 Dilatacije

Expansion joints are set on the structure Dilatacije se postavljaju na krajevima


closures, that is, main girder closures. konstrukcije – glavnog nosača. Oslanjaju se na
Expansion joints rely on reinforced sections of ojačane presjeke završetka glavnog nosača i
main girder closures and parapet closure. The parapeta. Na osnovu maksimalnih vrijednosti
expansion joint DS480 at the abutment AO and pomjeranja, usvojena je dilataciona spojnica
expansion joint DS800 at the abutment A1 are DS480 na oporcu A0 i DS800 na A1. S obzirom
adopted on the basis of maximum values of na dimenzije konstrukcije spojnice, ista je data u
strain. Considering the dimensions of grafičkoj dokumentaciji, jer odrijedjuje oplatu i
expansion joint structure, it is provided in armaturu dijelova oporca i glavnog nosača, u
graphic documentation because it defines the koje se ugradjuje. Komora na krajnjim stubovima
formwork and reinforcement of parts of služi za pregled dilatacionih spojnica sa donje
abutments and main girders it is installed in. strane. Moraju biti otporne na na moguća
The purpose of the chamber on end abutments oštećenja pri održavanju puteva čistačima
is checking of the expansion joints from bottom snijega.
side. They have to be resistant to possible
damage that can occur during the road
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
38
maintenance with snow cleaner machine.

3.1.5.3 Cone slopes 3.1.5.3 Kegle

The bridge is in the embankment at it’s Na početku, most je u nasipu, pa krilni zidovi
beginning, so the wing walls follow the gradient prate nagib kegle. Kegle na oporcu A0 su u
of cone slope. Final grade slope of the cone završnom nagibu 1:1.5, a na A1, 1:1.25. Kegle
slopes at abutment A0 are 1:1.5. Final grade se oblažu betonskim pločama, debljine 12 cm,
slope of cone slope is 1:1.25. Cone slopes are dimenzija u osnovi 50x50 cm. Zalivanje spojnica
encased in concrete slabs whose thickness is elastičnom smesom, npr. bitumenom. Podloga
12 cm and it’s dimensions in the base are ovih ploča mora biti elastična, npr. u sloju
50x50cm. There is a sealing of joints with nabijenog pijeska. Obloga se oslanja na temelje
elastic mixtures (such as bitumen). The obloge od nabijenog betona.
bedding of these slabs have to be elastic one
(i.e. , in the layer of compacted sand). The
covering relies on foundations of covering build
of compacted concrete.

3.1.5.4 Cornices and concrete in median 3.1.5.4 Ivični vijenci i beton u razdjelnom
strip pojasu

Cornices are integral part of the concrete of Ivični vijenci su integralni dio betona pješačke
pedestrian walkway. The windscreen girder is staze. U ovaj beton su ankerovani nosači
anchored into this concrete. The fence of vjetrobrana. U beton pješačkih staza je još
pedestrian walkway and guardrail are also ankerovana i ograda pješačke staze i odbojna
anchored into the concrete of pedestrian zaštitna ograda. U beton razdjelnog pojasa su
walkways. The pillars of bridge lightning are ankerovani stubovi osvetljenja mosta. U beton
anchored into the concrete of median strip. se postavljaju cijevi za provodjenje instalacija na
The pipes for passage of bridge installations mostu. Svakih 25 – 30 m u betonu se postavlja
are installed into the concrete. There will be an revizioni šaht. Gornja površina betona pješačkih
inspection chamber at each 25-30 m in the staza i razdelnog pojasa se izvodi u nagibu od
concrete. The top surface of concrete of 4% ka kolovozu.
pedestrian walkways and median strips is
constructed in the gradient of 4% towards the
carriageway.

3.1.5.5 Transition slab and gravel wedge 3.1.5.5 Prelazna ploča i šljunčani klin

The length of both transition slabs is Obje prelazna ploče su dužine 3.70+2.5 m.
3.70+2.5m. The gradient of top surface is 10% Nagib gornje površine je 10% u odnosu na nagib
in relation to the gradient of vertical alignment nivelete puta. Po širini, prostire se izmedju
of the road. It extends between the cantilevers konzola krilnih zidova, od kojih je dilatirana 2 cm.
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
39
of wing walls across the width (dilated Preko cjelokupne gornje površine se produžava
transition slab of 2cm). The waterproofing from hidroizolacija sa kolovozne ploče. Izvodi se
bridge deck continues along the whole upper preko sloja podložnog betona, debljine 10 cm.
surface. Waterproofing is carried out across Vezana je za parapet krajnjeg stuba armaturom
the whole top surface of underlayer concrete u gornjoj zoni presjeka ploče. Ploča se postavlja
whose thickness is 10cm. Waterproofing is preko šljunčanog klina, koji se izvodi uz krajnje
connected to the parapet of abutment through stubove, 1 m vertikalno od kraja prelazne ploče i
the reinforcement in the upper zone of the slab dalje pod nagibom do linije iskopa temelja stuba.
section. The slab is installed across the gravel Materijal za klinove mora biti kao i za tampon.
wedge which will be constructed next to the Nabijanje najvišeg sloja se vrši do 70 MPa, a
abutment 1 m vertically from the end of svakog slijedećeg 10 MPa manje, ali ne manje
transition slab and it will be continued under od 30 MPa.
the gradient up to the excavation line of pillar
foundation. Material of wedges has to be the
same as the one for base. The compaction of
the top layer will be carried out up tp 70MPa. It
will be decreased for 10MPa for every next
compaction, but it will not be lower than 30
MPa.

3.1.5.6 Waterproofing and drainage 3.1.5.6 Hidroizolacija i odvodnjavanje

The waterproofing of bridge deck has to be Hidroizolacija ploče mosta mora biti kvalitetna i
very good and it should cover whole top treba da pokriva cjelokupnu gornju površinu
surface of bridge deck between cornices. The kolovozne ploče izmedju ivičnih vjenaca. Mjesta
positions of connection of safety concrete veze zaštitne odbojne betonske ograde za
guardrail and bridge deck should be treated kolovoznu ploču treba posebno obraditi, kao i
particularly, as well as part around holes in the dio oko otvora u ploči za slivnike i oko
slab for gullies and around expansion dilatacionih spojnica. Ova hidroizolacija se
joints.This waterproofing will be extended to produžava i na prelazne ploče. Predvidjena je
transition slabs, too. Designed waterproofing is prskana MMA hidroizolacija. Radi trajnosti
sprayed MMA. There will be small tubes left for hidroizolacije, ispod asfalta, ostavljaju se
drainage of seepage water that can reach cevčice za odvodjenje procedne vode, koja
through the cracks in asphalt in order to može dospeti kroz prsline u asfaltu. One ujedno
achieve the durability of waterproofing. Their služe i kao zaštita od pojave unutrašnjih
purpose is also the protection against the pritisaka vazduha, koje mogu razoriti strukturu
phenomenon of internal air pressure, which asfalta..
can destroy asphalt structure.

The waterproofing should be accepted and Hidroizolacija treba da bude prihvaćena i


approved by Employer. odobrena od strane Investitora.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
40
The drainage of meteoric water from Odvodnjavanje meteorske vode sa kolovoza je
carriageway is provided in separate elaborate, dato u posebnom elaborate, iz koga je na
from which is given extract, on beginning of the početku ovog izveštaja, dat izvod. Ovdje ćemo
report. We will only mention that there are pomenuti samo da su u ovom projektu dati
gullies, their position and arrangement slivnici, njihov položaj i raspored. Sva voda se
provided in this Design. All the water collects poprečnim i podužnim padom skuplja u
into the gullies by crossfall and grade and it is slivnicima i dalje vodi podužnim drenažnim
discharged out of the bridge by longitudinal cjevima, postavljenim ispod konzole glavnog
drainage pipes which are set under the nosača sa niže strane, van mosta.
cantilever of main girder at lower side.

3.1.5.7 Traffic signalization and equipment 3.1.5.7 Saobraćajna signalizacija i oprema

The bridge is equipped with H2-W4 type safety Most je opremeljen sa zaštitnom odbojnom
fence and galvanized steel fence of pedestrian ogradom tipa H2-W4, po Standardu MEST EN
walkways (in accordance with MEST EN 1317 i čeličnom pocinkovanom ogradom
1317).It is elaborated in separated study. It is pješačkih staza. Obradjena je u posebnom
necessary to put the board with the name of elaboratu. Ispred i iza mosta je potrebno
the bridge in front of the bridge and behind the postaviti tablu sa imenom mosta.
bridge.

3.1.5.8 The lighting of the bridge deck, the 3.1.5.8 Osvetljenje kolovoza mosta,
interior of girder and decorative lighting osvetljenje unutrašnjosti nosača i
dekorativno osvetljenje

These three designs are provided in special Ova tri projekta osvetljenja su data u posebnom
design. Here, we will only mention that the projektu. Ovdje će se pomijenuti samo da je
attention will be paid to the position and tokom izvodjenja obratiti pažnju na položaj i
requiered outer dimensions of parts for relying potrebne gabarite dijelova za oslanjanje opreme.
of equipment.

3.1.5.9 Windscreens 3.1.5.9 Vjetrobrani

Windscreens are elaborated in special Design. Dati su u posebnom projektu.

3.1.6 Materials of bridge structure 3.1.6 Materijali konstrukcije mosta

All the concretes belong to BII category. Svi betoni su kategorije BII.

Main girder, aerated concrete C42/53 (MB 50), Glavni nosač, aerirani beton C42/53 (MB 50),
V-8, M-200, frost resistance and salt resistance V-8, M-200, otpornost na mraz i so “1”.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
41
“1”.

Middle piers and bearing beams: aerated Srednji stubovi i ležišne grede, aerirani beton
concrete C38/47 (MB 45), V-8, M-200. C38/47 (MB 45), V-8, M-200.

Abutments with wing walls: aerated concrete Krajnji stubovi sa krilnim zidovima, aerirani
C25/32 (MB 30), V-6, M-150. beton C25/32 (MB 30), V-6, M-150.

Cornices with concrete safety fences and Ivični vijenci sa zaštitnim betonskim odbojnim
bearing concrete cubes: aerated concrete ogradama, i kvaderi, aerirani beton (C33/42) MB
(C33/42) MB 40, V-8,M-200. Frost resistance 40, V-8, M-200, otpornost na mraz i so “0”.
and salt resistance “O”.

Bearing concrete cubes, aerated concrete Kvaderi, aerirani beton C42/53 (MB 50), V-8,
C42/53 (MB 50), V-8, M-200, frost resistance M-200, otpornost na mraz i so “0”.
and salt resistance “0”.

Foundations, C25/32 (MB 30), V-6, M-100. Temelji, C25/32 (MB 30), V-6, M-100.

Transition slabs, C25/32 (MB 30), V-6,M-150. Prelazne ploče, C25/32 (MB 30), V-6, M-150.

Foundations of cone slope linings, concrete Temelji obloge kegle, beton C17/21 (MB 20).
C21/26 (MB 25).

Underlayer concrete C17/21 (MB 20) Podložni beton C17/21 (MB 20).

Reinforcement B500B for whole structure. Armatura B500B za cjelokupnu konstrukciju.

According to EN 10138, cables belong to class Kablovi su klase Y1860, prema EN 10138,
Y1860. Nominal diameter is 15.2 mm and nominalnog prečnika 15.2 mm, niske relaksacije.
relaxation rate is low. The pipes of the cables Cijevi kablova su plastične.
are plastic.

Steel elements on the bridge, such as Čelični elementi na mostu, kao rukohvati na
handrails on safety fences and cantilevers for odbojnim ogradama i konzole za nošenje
carrying of the installations, are all made of hot instalacija su od toplo cinkovanog čelika S235.
dipped galvanized steel S235.

3.1.7 Review of construction 3.1.7 Osvrt na tehnologiju izvodjenja


technology

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
42
3.1.7.1 Excavation and slope protection 3.1.7.1 Iskop i zaštita kosina

According to Geotechnical Elaborate, the Materijal u kome se vrši iskop je, prema
material the excavation is carried out in has geotehničkom elaboratu, veoma povoljnih
favorable properties. Since the characteristic of karakteristika. Pošto je karakteristika ovih
these karstified terrain is the existence of local karstnih terena postojanje lokalnih pukotina
cracks filled with clayey material, the actual ispunjenih glinovitim materijalima, prilikom
condition should be determined on the spot iskopa, na licu mjesta, treba utvrditi stvarno
during the excavation. The way of excavation stanje. U zavisnosti od stvarnog stanja, treba
should be determined depending on actual odrediti način iskopa, mehanički ili miniranjem. U
condition (mechanical excavation or blasting). slučaju miniranja, ono treba da bude bez
In the case of it’s use, the blasting should be poremećaja okolnih slojeva. Miniranje nije
carried out without disturbance of surrounding dozvoljeno na 1 m oko temelja.
layers. It is not allowed to carry out blasting at
1 m around the foundation.

The ditches for drainage of meteoric water U temeljnim jamama i oko njih su predvidjeni
during construction are planned in foundation jarkovi za odvodjenje meteorske vode tokom
pits and around them. The excavation is izvodjenja. Iskop je privremen. Treba raditi
temporary. The backfilling should be carried nasipanje čim se završi deo stuba i to bude
out immediately after the part of the pillar is moguće. U grafičkoj dokumentaciji je dat plan
completed. There is a plan of excavation for iskopa za svaki pojedinačni stub i oporac.
each individual pillar and abutment in graphic
documentation.

3.1.7.2 Foundations 3.1.7.2 Temelji

Shallow foundations should be constructed in Plitki temelji treba da budu izvedeni tako da udju
a way that enables them to enter geotechnical u geotehnički sloj “C” oko 2 m, kako je gore već
layer “C” for about 2 m (as it is mentioned pomenuto. Kvalitet temeljne spojnice treba da
above). Geotechnical engineer should approve potvrdi geotehničar. Temelji se izvode preko
the quality of foundation joint. The foundations sloja podložnog betona, debljine 20 cm. Ovaj
will be conctructed over the layer of underlayer sloj je širi od temelja za po 20 cm. Temelji se
concrete whose thickness is 20cm. This layer izvode u oplati. Armaturne šipke Ø32, duže od
is wider than foundation for 20 cm. The 12 m se nastavljaju mehaničkim nastavcima –
foundations will be constructed in the konektorima. Prilikom izvodjenja je potrebno
formwork. Rebars Ø32 that are longer than 12 obezbjediti dovoljan zaštitni sloj.
m continue with mechanical joints-
connectors.It is necessary to provide sufficient
protective layer during construction.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
43
3.1.7.3 Pillars 3.1.7.3 Stubovi

Considering the height and consistency of Srednji stubovi se izvode u kliznoj skeli i oplati, s
outer dimensions, middle piers are constructed obzirom na visinu i konstantnost spoljašnjih
in sliding scaffold and formwork. The segment gabarita. Dužine segmenata su oko 6 m u
length is about 6m in each sequence of svakom potezu betoniranja. Na svakom
concreting. Survey inspection of formwork nastavku betoniranja treba predvideti geodetsku
should be planned before each sequel of kontrolu oplate, da bi se održala vertikalnost
concreting in order to keep pillar verticality. stubova. Armaturne šipke Ø32, duže od 12 m se
Rebars Ø32 which are longer than 12 m are nastavljau mehaničkim nastavcima –
continued with mechanical splicing- konektorima. Prilikom izvodjenja je potrebno
connectors. It is necessary to provide sufficient obezbjediti dovoljan zaštitni sloj. Tokom
protective layer during the construction. It is izvodjenja predvideti stepenište i lift za pristup
necessary to plan stairs and elevators for the nivoima gradnje. Toranjski kran mora biti dobro
purpose of access to construction stages. ankerovan za već izgradjene dijelove stuba.
Tower crane must be anchored well to the Nakon izvodjenja krajnjeg stuba A01 zatrpati
parts of pillar that have already been built. prednji dio iskopa do kote postojećeg terena,
After the abutment A01 is constructed, front prije početka radova na glavnom nosaču.
part of excavation will be backfilled up to the
level of actual terrain before the
commencement of works related to main
girder.

3.1.7.4 Main girder-bridge deck 3.1.7.4 Glavni nosač – kolovozna ploča

It is constructed by “balanced cantilever Izvodi se metodom “slobodne konzolne gradnje”.


method”. The construction starts with the Gradnja počinje izgradnjom baznog segmenta,
construction of basic segment above all the iznad svih srednjih stubova. Gradnja ovih
middle piers. The construction of these segmenata se odvija na posebnoj skeli i oplati.
segments is carried out on the special scaffold Radi postizanja zahtijevane geometrije, skela se
and formwork. The scaffold must be mora prednapregnuti prije betoniranja. Nakon
prestressed before concreting in order to očvršćavanja betona, utežu se podužni kablovi,
achieve requested geometry. After the uklanja skela i oplata baznog komada i postavlja
concrete hardening, longitudinal tendons are viseća skela i oplata – tkzv. “krletka”, obostrano.
prestressed, the formwork and scaffold of base Tako počinje konzolna gradnja, istovremeno sa
segment are removed. Hanging scaffold and svih 5 srednjih stubova. Svaki slijedeći segment
so called “form traveler” is installed on both se izvodi u visećoj skeli i oplati, uteže nakon
sides. This is how cantilever construction očvršćavanja i zatim se krletka pomera na
starts: it starts from all 5 middle pillars at the mjesto slijedećeg segmenta. Zatim se izvode
same time. Each next segment is constructed dijelovi glavnog nosača u krajnjim rasponima,
in hanging scaffold and formwork. It is koji se liju na skeli, postavljenoj na terenu.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
44
prestressed after the hardening and the form Viseća skela se pomera u sredinu raspona,
traveler is then moved to the position of next postavlju kontrategovi Q=480KN na krajeve i
segment. Parts of main girders in end spans betoniraju se završni segmenti raspona P2 – P3
are constructed afterwards. End spans are i P3 – P4. Uklanjaju se kontrategovi i, nakon
cast on scaffold that is installed on the site. postizanja 90% čvrstoće betona, utežu podužni i
The hanging scaffold moves to the middle of poprečni kablovi. Zatim se istim postupkom
the span, the counterweights Q=480KN are set zatvaraju rasponi P1 – P2 i P4 – P5, s tom
at the ends of spans. The final span segments razlikom što je Q=3000KN. Na kraju konstrukcija
of pillars P2-P3 and P3-P4 are concreted. The se kompletira zatvaranjem polja u bočnim
counterweights are then removed. Longitudinal rasponima. Prilikom postavljanja kablova, cijevi
tendons and transverse tendons are treba dobro učvrstiti na dovoljno gustom
prestressed after the concrete reaches 90% of rastojanju, da ne dodje do nedozvoljenih
it’s strength. The spans P1-P2 and P4-P5 are odstupanja od projektovanog položaja. Posebno
closed by the means of same procedure. The obratiti pažnju i razraditi redosled postavljanja
only difference is that Q=3000KN. The kablova i armature u segmente prije početka
structure is then completed with the closure of radova na svakom. Projektom su predvidjene i
fields in side spans. The pipes should be rezervne cijevi, u koje se, tokom izvođenja,
strenghtened enough at the sufficient distance mogu ubaciti dodatni kablovi, ako bude
in order to avoid non-allowed deviation from potrebno.
designed position. Special attention should be
paid to arrangement of tendons and
reinforcement into the segments before work
on each one of them starts.The sequence of
arrangement of tendons and reinforcements
should be elaborated as well. In design is
predicted additional pipes for cables, in which,
during construction, can be placed cables, if
need.

3.1.7.5 Review of environmental protection 3.1.7.5 Osvrt na mere za zaštitu životne


measures during the construction sredine tokom izvodjenja

The protection of environment is a topic of Zaštita životne sredine je predmet posebnog


special elaborate that is being prepared as part elaborata koji se radi u okviru projekta trase.
of route design.

3.1.8 Measures and solutions related 3.1.8 Mjere i rješenja za obezbjedjenje


to providing of structure durability trajnosti objekta

The durability of concrete is provided by the Trajnost betona je obezbjedjena i samim


selection of typical cross section (i.e., closed odabirom tipa poprečnog presjeka, zatvorenog
box section). The exposed outer surface of this sandučastog. Ovakav presjek ima malu izloženu
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
45
section is small, so the influences of external spoljašnju površinu, pa su uticaju spoljašnje
environment are reduced to a minimum. sredine svedeni na minimum.

Aerated waterproofing concretes that meet U cilju obezbjeđenja trajnosti objekta


valid regulations are designed in order to projektovani su aerirani i vodonepropusni betoni
provide the durability of the structure. Ensured prema važećim propisima. Obezbjeđenjem
waterproofing will result in compact concrete. vodonepropusnosti se dobija kompaktan beton,
Concrete will be protected against influence of a aeriranjem odnosno obezbjeđenjem uvučenog
frost or frost and salt by aerating , that is, vazduha i sadržaja pora u betonu od 3-5% beton
providing 3-5% of content of sucked air and se štiti od dejstva mraza ili mraza i soli. Za
pores in concrete. Appropriate waterproofing obezbjeđenje trajnosti su projektovane
brands and resistance brands against odgovarajuće marke vodonepropusnosti i marke
influence of frost are designed for providing of otpornosti prema dejstvu mraza. Takođe su
durability. Protective layers of reinforcement projektovani propisni zaštitni slojevi armature i
and tendons that meet regulations are kablova. Zaštitni slojevi za kablove su
designed as well. The minimum designed projektovani min 8 cm, a za armaturu za
thickness of protective layers for tendons is 8 rasponsku konstrukciju i kvadere 4,5 cm, za
cm. Minimum designed thickness of protective stubove, prelazne ploče i zaštitne odbojne
layer for span structure and bearing concrete ograde 4 cm, za temelje i šipove 5,0 cm.
cubes is 4,5 cm. Minimum designed thickness
of protective layers for pillars, transition slabs
and safety fence is 4cm. Minimum designed
thickness of protective layers for foundations
and piles is 5,0cm.

Important condition for providing of durability is Važan uslov za obezbjeđivanje trajnosti je


waterproofing of bridge. The attention should hidroizolacija mosta. Treba obratiti pažnju na
be paid to it’s selection and conditions for njen odabir i na uslove za njenog izvodjenja.
carrying out of waterproofing. This is Posebno oko otvora u ploči i slivnika.
particularly important for the area around holes
in slab and gully.

Expansion joint devices and bearings which Takodje, treba odabrati dilatacione naprave i
meet the requierements related to durability ležišta, koja zadovoljavaju uslove trajnosti i
and stability should also be selected. postojanosti.

The durability of metal parts on the structure is Trajnost metalnih dijelova na konstrukciji se
achieved by the means of hot dip galvanizing. postiže toplim cinkovanjem.

3.1.9 The review of bill of quantities 3.1.9 Osvrt na predmjer i predračun


radova

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
46
Review of quantities of major structural Pregled količina glavnih konstruktivnih materijala
materials per squere meter of bridge area is po kvadratnom metru mosta je dat u tabeli ispod:
given in table bellow:

Superstructure/ Substructure/
Item/ Unit/ Superstructure/ Substructure/ Total/
Glavni nosač donji stroj
pozicija jedinica Glavni nosač donji stroj ukupno 2 2
per/po m po/per m
Concrete m3 29899.08 63980.2 93879 1.33 2.85
Reinforcement kg 4971657 9657922.8 14629580 221.19 429.68
Cables kg 2055319.1 - 2055319 91.44 -
2
Area of bridge A = (961.22+959.88)/2* 22476.87 m

3.1.10 The list of applied laws, general 3.1.10 Spisak korišćenih Zakona,
regulations, technical regulations, opštih i tehničkih propisa, normativa i
normatives and standards standarada

Službeni list of SFRJ No.1/91 Pravilnik o tehničkim normativima za


određivanje veličina opterećenja mostova
(Official Gazette of SFRJ 1/91)
Rulebook of technical normatives for defining
magnitude of bridge load

Official Gazette of SFRJ No.11/87 Pravilnik o tehničkim normativima za beton i


armirani beton

Rulebook of technical normatives for concrete


and reinforced concrete PBAB 87

Official Gazette of SFRJ No.51/71 Pravilnik o tehničkim merama i uslovima za


prednapregnuti beton

Rulebook of technical measures and conditions


for pre-stressed concrete

Official Gazette of SFRJ No.15/90 Pravilnik o tehničkim normativima za temeljenje


građevinskih objekata

Rulebook of technical normatives for foundation


of structures

Official Gazette of SFRJ No.20/92 Pravilnik o tehničkim normativima za


eksploataciju i redovno održavanje mostova

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
47
Technical guidelines for operations and regular
maintenance of bridges

Official Gazette of SFRJ No.18/92 Pravilnik o tehničkim normativima za beton i


armirani beton u objektima izloženim
agresivnom dejstvu sredine Technical guidelines
for concrete and reinforced concrete in the
structures exposed to aggressive environment

CEB-FIP 1990 CEB-FIP MODEL CODE 1990 deign code

EN 1337-1/3/5:2000/2005/2005 Structural bearings

EN 10080:2005 European Standards for Concrete


Reinforcement

EN 10138:2000 European Standards for Pre-stressing Steel

MEST EN 1998-2:2012 Eurokod 8: Projektovanje seizmički otpornih


konstrukcija - Dio 2: Mostovi

Eurocode 8 - Design of structures for earthquake


resistance - Part 2: Bridges

Direkcija za puteve Federacije Bosne i Smjernice za projektovanje puteva, izgradnju,


Hercegovine, Sarajevo i Javno preduzeće " održavanje i nadzor, Sveska I: Projektovanje,
Putevi Republika Srpska", Banja Luka, 2005. Deo 2: PROJEKTOVANJE MOSTOVA,

Road Directorate of Federation of Bosnia and Guidelines for road design, construction,
Herzegovina, Sarajevo and Public Company maintenance and supervision, Volume I: Design,
"Republika Srpska Roads", Banja Luka, 2005. Part 2: DESIGNING BRIDGES

Prepared by: Ličina Željko, dipl.inž.građ.

Liu Huatu, dipl.inž.građ.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
48
Wang Maoqiang dipl.inž.građ.

3.2 Technical and technological 3.2 Tehničko i tehnološko rešenje


solutions

3.2.1 Layout of the structure which 3.2.1 Prikaz strukture čija je izgradnja
will be constructed planirana

Refer to attachment 1 Prilog br. 1

3.2.2 Construction working days 3.2.2 Radni dani za izvođenje


konstrukcije

In accordance with ER Sub-Clause 6.1 and U skladu sa podtačkom 6.1 Zahtjeva


contract Sub-Clause 8.3, the Contractor Poslodavca i podtačkom 8.3 Ugovora, Izvođač
should identify works and resources calendars radova treba da odredi radove i resurse prema
(including all Holidays periods and weather trajanju odnosno vremenski. Radovi na
conditions which are at the Contractor's risk izgradnji konstrukcije Mosta Moračica izvodiće
and other Contractor time risks). We will se svakog radnog dana (poštujući sve
perform the construction works for the praznike prema zakonu), a na osnovu
Moracica Bridge every working day. Based on vrijemenskih uslova u različitim oblastima,
the weather in different districts, the MS in Tehnologija izvođenja radova u različitim
different season, and all statutory Holidays, we godišnjim dobima, poštujući sve praznike
will use construction work days every year for prema zakonu, koristićemo sve radne dane
Moracica Bridge construction as the table. prema rasporedu za izgradnju Mosta
Contractor will consider 5 weather influence Moračica. Izvođač će za period od januara do
days every month from January to March and marta po 5 dana mesečno smatrati za
2 weather influence days every month from vremenski nepovoljne dane, a za period od
April to December. aprila do decembra po 2 dana mesečno.

Table/Talbe 3.2-1 Construction work days every year / Radni dani izvodjenja konstrukcije
Structure Effective Weather and
name / Annual / work days / influence days / Remark /
Naziv Godisnje Efektivni Praznicni Primjedbe
konstrukcije radni dani nepovoljni dani

Moracica 2016 273 18(2*9) 291

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
49
Bridge/ Most 2017 332 33(3*5+2*9) 365
Moračica
2018 332 33(3*5+2*9) 365

2019 106 17(3*5+2*1) 123

3.2.3 List of machinery and 3.2.3 Spisak mašina i opreme


equipment

The machinery and equipment in the list below Mašine i oprema navedeni u tabeli biće
are used in all the process of Moracica Bridge korišćeni u procesu izvođenja Mosta
construction. Moračica.

Table/Talbe 3.2-2 List of machinery and equipment / Spisak mašina i opreme

Serial Machinery and


Production Quantity
numb/ equipment name / Specifications Remark /
capacity / /
Serijski Naziv mašina I / Specifikacije Primjedbe
Kapacitet Količina
broj opreme
Large Mashinery /
1
Velika mašinerija
3 3
1.1 Excavator / Bager VOLVO 1.0m ,1.9 m 7
1.2 Loader / Utovarivač LOVOL ZL50 5t 4
Truck crane /
1.3 ZOOMLION 25t 2
Dizalica
Truck crane /
1.4 ZOOMLION 50t 1
Dizalica
Crawler crane /
Dizalica na
1.5 ZOOMLION 50t/80t 2
gusenicama

Truck concrete
3
1.6 pump / Pumpa za ZOOMLION 65 m /h 2
beton
1.7 Dumper / Damper 12.7t 5
Flat truck /
1.8 Kamionza transport 12t 2
armaturnih šipki
Tower crane /
1.9 TC7035B-16 250t.m 5
Toranjskadizalica
Cantilever formwork
1.10 5
/ Konzolna oplata
Hydrolic climbing
formwork /
1.11 5
Hidraulična
penjajuća oplata
gantry crane /
1.12 MH10-32 10t 2
dizalica za
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
50
Serial Machinery and
Production Quantity
numb/ equipment name / Specifications Remark /
capacity / /
Serijski Naziv mašina I / Specifikacije Primjedbe
Kapacitet Količina
broj opreme
pomeranje oplate
Construction
1.13 elevator / Gradilišni ZOOMLION 2*2000kg 5
lift
Trailer concrete
pump / Pumpa za
3 3
beton zavelike 112 m /h ,82 m /h,47
1.14 ZOOMLION 5
količine betona I za
3
m /h
betoniranje na
velikim visinama
1.15 concrete spreader HGY24-3 R=24m 2
Concrete mixer / 3
1.16 10 m 6
Mikser za beton
Asphalt truck /
1.17 12t 6
Kamion za asfalt
1.18 Roller / valjak 7t-26t 3
Power rammer /
1.19 mašina za zbijanje 12-40kN 3
tla
Light-duty
2 Machinery / Mašine
malog kapaciteta
Aircompressor / 3
2.1 3.2 m /min 4
Kompresor
Generator /
2.2 400kW,200kW,75kW 4
Generator
Rebar cutting
machine / Mašina
2.3 Φ6-Φ40mm 5
za sečenje
armaturnih šipki
RebarThreading
machine / Mašina
2.4 24-26r/min 4
za vezivanje
armaturnih šipki
Tensioning
equipment / 250 KN,500
2.5 14
Oprema za KN,650KN
prednaprezanje
Roofbolter / Mašina
2.6 za bušenje rupaza 0-90r.p.m 4
ankere
2.7 Fan / Ventilator 2*75 KW 4
Welding machine /
2.8 100-500A 8
Mašina za varenje
Steel bending
machine / Mašina
2.9 5-40r/min 4
za savijanje
armaturnih šipki
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
51
3.2.4 Construction process and 3.2.4 Proces izgradnje i tehnologija
methods izgradnje

3.2.4.1 Preparations 3.2.4.1 Pripreme

Construct access roads for geological Izgradnja pristupnih puteva za geološka


exploration, and then build access road A4,A7 istraživanja, a zatim izgradnja pristupnih
and temporary steel bridge for construction of puteva A4 i A7, kao i privremjenog čeličnog
bridge. Complete one camp, transformer mosta za igradnju glavnog mosta.
stations, warehouse, Steel structure Kompletiranje kampa, trafostanica, skladišta,
manufactory, reinforcement processing pogona za čelika, armiračkog pogona,
manufactory, storage,crusher plant and magacina i fabrike betona.
concrete batching plant.

3.2.4.2 Main works 3.2.4.2 Glavni radovi

The Bridge will be constructed in sequences Most će se izvoditi postupno kako je navedeno
as stated below: survey and setting out earth u nastavku: geodetsko obijelježavanje
work of foundation pit& dewatering system zemljani radovi za iskop temeljnih jama i
reinforcement and formwork construction sistem odvodnjavanja armirački i tesarski
concrete work construction of substructure radovi betonski radovi izgradnja donjeg
construction of bearing construction of stroja izrada ležišta izgradnja gornjeg stroja
superstructure pre-stressing and grouting prednaprezanje i injektiranje snopova užadi
works construction of bridge deck system and izrada kolovozne konstrukcije i postavljanje
ancillary facilities. instalacija.

Description of construction methods: Opis metoda izgradnje:

Survey and setting out: Firstly, finishing the Ⅰ Geodetsko obijelježavanje i iskolčavanje:
survey control network. Secondly, according to Najpre se kompletira kontrolna geodetska
design drawings of structures calculate for mreža. Zatim se prema crtežima iz Glavnog
each feature point coordinates and elevation. projekta konstrukcije sračunavaju koordinate i
Lastly, survey and check the coordinates and kote svih elemenata. Posle toga slijedi
elevation on site with total station and water geodetsko obijelježavanje i provera koordinata
level. na gradilištu totalnom stanicom i kota
nivelirom.

Earth work of foundation pit&dewatering Ⅱ Radovi na iskopu temeljne jame i sistem


system: The excavation will be done manually odvodnjavanja: Iskop će biti izveden ručno ako
for small and shallow areas or excavation je manjeg obima i plići ili bagerom ako je velći i

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
52
machine for large and deep areas. Prepare dublji. Pre izvođenja iskopa slijedi priprema
the access road and construction platform pristupnog puta i platforme. Zatim sledi
before construction. Then survey points to be geodetsko obijelježavanje radi kontrole.
settled for quality control. Mark the excavation Obijelježava se granice iskopa i rova prema
boundary for each foundation and trench crtežima iz Glavnog projekta. Zatim se vrši
according to the design drawings. Excavate all iskop temeljne stope prema granicama iskopa
the foundation footing following the boundary i geodetskim tačkama kako se ne bi iskopalo
and survey points to avoid over excavation. više nego što je potrebno. Ono što se više
Over excavation is to be backfilled with iskopa biće zatrpano materijalom koji bude
qualified materials. Open excavation method odobren. Biće usvojena metoda otvorenog
shall be adopted. The catchwater will be iskopa. Oko temeljne jame biće izveden kanal
performed around the foundation pit in order to za vodu kako bi se zaštitila privremjena
proctect the temporary slope. Excavations kosina. Iskopi će se izvesti sa padom kosine
will be executed with slope ratio of 1:0.15. In 1:0.15. U međuvremjenu, uradiće se zaštita
the meantime the temporary slope protection privremjenih kosina. Kada se dođe do
will be constructed. When reaching the design projektovane kote dna temeljne jame, ako je
bottom elevation of foundation pit, the well potrebno koristiće se bunari za odvođenje
point dewatering will be employed if vode. Radna snaga će izravnati i očistiti dno
necessary. Manpower will level and clear the temeljne jame. Iskopan materijal biće odvezen
bottom of foundation pit. The excavated do privremjene deponije, teda se kasnije može
material will be dumped to the temporary koristiti kao materijal za zatrpavanje.
disposal area so later it will be used as a Zatrpavanje treba izvoditi u slojevima i taj
backfilling material. Backfilling should be materijal treba zbijati odgovarajućim ravnim
carried out by layers and compacted by a vibratorom ili drugom odobrenom mašinom za
suitable flat vibrator or other approved zbijanje, prema Specifikacijama.
compaction plant as per Specifications.

Reinforcement and formwork construction: Ⅲ Armirački i tesarski radovi: Armatura treba


The reinforcement should be placed and da bude postavljena iodžavana u položaju koji
maintained in the position shown on the je dat na crtežima. Takođe armaturne šipke
drawings. Also rebars shall be tied together biće povezane prekaljenim žicama , kako bi se
using annealed iron wire sat intersection formirali kruti armaturni sklopovi koji će
points, to form rigid cages that will maintain zadržati položaj kako ne bi došlo do krivljenja
their position without distortion or twisting ili uvrtanja za vreijeme livenja I zbijanja
during the placing and compaction of the betona. Oplata će biti dobro zatvorena I
concrete. Formwork shall be sufficiently tight pritegnuta tako da se spriječi curenje
to prevent leakage of grout or cement paste. cementne paste kroz nju. Sve površine oplate
All surfaces of formwork and embedded I ugrađenog materijala moraju biti očišćene od
materials shall be cleaned of any accumulated bilo kakvog maltera od prethodnog betoniranja
mortar or grout from previous concreting and I bilo čega pre nego što počne betonaža
of all matter foreign material before concrete is predmetnog elementa.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
53
placed in them.

Concrete work: All concrete shall be Ⅳ Betonski radovi: Beton će se zbijati


consolidated by vibration, spading, rodding or vibriranjem ili lopatama tako da se sav beton
forking so that the concrete is thoroughly ugradi oko armature i eventualno ugrađenih
worked around the reinforcement and around elemenata. Vremenski interval između slojeva
the embedded items. The time interval betoniranja ne smije prekoračiti momenat
between concrete layers shall not exceed početka vezivanja betona. Na gradilištu će se
initial setting time. keep on site a complete voditi zapisnik o betoniranju gde će se unositi
record of the works showing the time and date datum i vrijeme betoniranja za sve radove.
when concrete is placed in each part of the Takođe vodosnabdijevanje će biti
work. Water system shoud be provided to obezbijeđeno. Biće obezbijeđena njega
ensure sufficient water supply. And final curing betona koja će trajati nekoliko dana za
shall be continued for days in the case of konstruktivne elemente konstrukcije. Ako je
structural concrete. If necessary, the concrete potrebno, beton će se prekrivati polietilenskim
will be covered with polyethylene sheeting folijama za vrijeme njege.
during the final curing.

Construction of substructure: it will be Ⅴ Izgradnja donjeg stroja: ovi elementi


constructed with automatic climbing formwork formiraće se pomoću automatske viseće
from Chinese company. The first pouring is 6.1 oplate koja je proizvod kineske kompanije.
m. The standard height of pouring is 6 m. Prvo segment betoniranja je na visini od
Construction process is as follows, removal of 6.10m. Standardna visina jednog segmenta
form and platform after the concrete reaches betoniranja je 6.0m. Proces izgradnje je
the strength; installation of climbing formwork slijedeći: demontaža oplate i platforme nakon
hanging and formwork body; installation of što beton prve faze dostigne potrebnu
anchor parts; steel banding; form assembly; čvrstoću pri pritisku; montaža viseće oplate;
concrete pouring for the next frame. postavljanje ankera; postavljanje dodatnih
armaturnih šipki za fiksiranje oplatne
konstrukcije; montaža oplate narednog takta
betoniranja; betoniranje narednog takta.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
54
Machining stiff Preparation / priprema
framework,
reinforcement
Installation of scaffold / montaža skele
and
embedded
Installation of stiff framework, reinforcement and embedded part / montaža
part /
ukrućenja, armature I delova koji ugrađuj
ukrućenje,
armature I Construction for first segment of pier / izrada prvog segmenta stuba
delovi koji se
ugrađuju
Concrete for first segment of pier / betoniranje prvog segmenta stuba

Concrete curing / nega betona

Remove formwork and install climbing formwork / uklanjanje oplate I montaža viseće oplate

Installation of stiff framework, reinforcement and embedded part for 2nd segment / montaža
ukrućenja, armature I delova koji ugrađuj za drugi segment

Installation of formwork for 2nd segment / montaža oplate za drugi segment

concrete for 2nd segment / betoniranje drugog segmenta

concrete curing / nega betona

continue construction form 3th to17th segment / nastavak izgradnje za 3-17.segment

change the climbing frame / promena okvira viseće oplate

Installation of stiff framework, reinforcement and embedded part for 18th segment /
montaža ukrućenja, armature I delova koji ugrađuj za 18.segment

Installation for formwork of 18th segment /montaža oplate za 18.segment

concrete for 18th segement / betoniranje 18.segmenta

construction continue untill the last segment / nastavak izgradnje do poslednjeg segmenta stuba

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
55
close andA removeBthe C the
climb D
remove the lower E closeF and
pouring / formwork rail / anchor shoe and pouring /
zatvoriti i izliti and set the obesiti climb the bracket / zatvoriti i izliti
beton anchor ?ine ukloniti donju beton
shoe/ukloniti anker-glavu i
oplatu i obesiti konzolu
postaviti
anker-glavu

Construction of bearing: There is 3 pieces of VI. Izrada ležišta: Na svakom obalnom


bearing on each abutment. Considering the stubu postoje tri tipa ležišta. Uzimajući u obzir
external conditions, also transverse wind spoljašnje uslove, biće postavljena i ležišta za
resistance bearings will be set up. prijem poprečnih uticaja vetra.

Construction of superstructure: Moracica Ⅶ Izgradnja gornjeg stroja: Most Moračica


Bridge consists of 6 spans, 95 m + 170 m + ima šest raspona,
190m × 3+125 m. The lengths of concrete 95m+172m+190mx3+125m. Dužina jednog
casting for the cantilever are 3.5m, 4.0m or takta konzolnog betoniranja biće 3.50m, 4.0m
4.5m, and 2.0m for closure segment. ili 4.50m, i 2.0m za završni segment. U
Combined with continuous beam structural skladu sa zahtjevima iz projekta i sa
characteristics and design requirements, the konstruktivnim karakteristikama kontinualne
superstructure cast-in-situ continuous beam gradnje, process izgradnje gornjeg stroja
construction process is as shown below: 0# kontinualnog nosača livjenog na licu mjesta je
segment bracket erection 0# segment slijedeći: podizanje konzolne konstrukcije za
construction balance cantilever processing izgradnju segmenta 0# izrada segmenta 0#
install and preload balance cantilever 1~n# balansiranje konzolne konstrukcije probno
segment construction side span bracket opterećenje konzolne konstrukcije izrada
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
56
erection Side span bracket cast-in-situ segmenta 1#-n# podizanje konzolne
section mid span closure side span closure konstrukcije za izgradnju bočnog raspona
Before formwork elevation adjustment, izgradnja bočnog raspona livjenog na licu
monitoring team undertakes structural analysis mjesta završni srednji raspon završni bočni
and calculation according to construction raspon prije podešavanja oplate na
results of last section, and then notifies in određenoj visini, tim za monitoring priprema
advance what the formwork elevation of the statičku analizu i proračun prema rezultatima
next section should be according to the izgradnje poslijednjeg segmenta, i nakon toga
standard. unapred saopštava na kojoj bi visini trebalo
postaviti oplatu narednog segmenta prema
standardima.

Construction sequence Redoslijed u izgradnji:

MATE? EVO
PODGORICA

A1

A0

P1 P5

P4
P2 P3

MATE? EVO
PODGORICA

A1

A0

P1 P5

P4
P2 P3

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
57
PODGORICA Q MATE? EVO
Q Q Q Q
Q Q Q Q
Q
T T A1
T T
A0

P1 P5

P4
P2 P3

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
58
Construction of 0# segment / izrada nultog segmenta

Form traveler machining / Form traveler assembled/ montaža konzolne skele


proizvodnja konzolne skele

Installation of reinforment / ugrađivanje


armature Machining the
st
reinforcement of 1
segment / proizv. armature
za 1.segment
Installation of prestressing duct /
ugradnja cijevi za prenaprezanje (PNP)

Survey before concreting /


geodetski snimak prije st
Concrete for 1 segment / betoniranje1.segmenta
betoniranja

Survey after concreting / geod. snimak nakon betoniranja

Concrete curing / nega betona

Survey before prestressing / Prestressing and grouting / PNP i injektiranje


geod. snimak prije PNP

Survey after prestressing / geod. snimak nakon PNP

Fix the elevation of formwork after calculation / fiksirati oplatu


na određenoj visini nakon proračuna

Move form traveler to 2nd segment / pomeranje konz. skele do


2.segmenta

Construction continue until closure section / izgradnjase


nastavlja do završnog segmenta

Remove form traveller / uklanjanje konzolne skele

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
59
Pre-stressing and grouting works: The Ⅶ Prednaprezanje I injektiranje snopova
high-strength steel strand φ 15.20, Ryb = užadi: Za prednaprezanje podužnih
1860MPa, will be used for longitudinal prednapregnutih segmenata koristiće se
pre-stressing segment. The tension of snopovi užadi φ15.20, fpk = 1860MPa. Sila
pre-stressing shall be controlled to 0.75 Ryb. prednaprezanja sračunava se prema 75%fpk.
The anchorage device to be used consists of Tipovi kotvi koje se koriste su T15-3, T15-12,
type T15-3, T15-12, T15-16, T15-19, T15-16, T15-19, T15-22 i T15-27.
T15-22and T15-27. The tensioning shall be Prednaprezanje će se kontrolisati silom
controlled by tension force and extension prednaprezanja i veličinom izduženja snopova
quantity. The tension force is the chief užadi. Sila prednaprezanja je osnovni faktor
controlling factor and the actual extension of kontrole a stvarna izduženja užadi treba
strand should be meeting the standard zadovolje zahtjeve iz standarda. Ako je razlika
requirements. If the difference is too big, veoma velika, primjeniće se odgovarajuće
appropriate measures shall be taken for mijere. Tehnologija vakuum injektiranja
treatment. The technology of vacuum grouting primjenjuje se za duže snopove užadi koji
is used for longer tendon with multiple curves. imaju puno vertikalnih krivina.

Construction of bridge deck system and Ⅸ Izrada kolovozne konstrukcije i postavljanje


ancillary facilities: the construction of bridge instalacija: izrada kolovozne konstrukcije biće
deck system and others will be excuted with izvjedena uobičajenom metodom. Nakon
the common method. Firstly,the sidewalk will izrade gornjeg stroja, najpre će se početi sa
start with movable scaffold after izradom pešačke staze pomoću pokretne
superstructure construction. In the meantime, skele. U međuvrijemenu, postavljaće se
the waterproof will be performed. Secondly, hidroizolacija; drugo, postavljanje elastične
install the safety steel barrier ,wind protection odbojne ograde, zaštite od vetra i postavljanje
strip and railing on the embedded parts of pešačke ograde na pešačkoj stazi; treće,
sidewalk; Thirdly, work for the drainage izrada sistema za odvodnjavanje pokretnom
system with movable scaffold; fourthly,the skelom; četvrto, asfaltiranje i dodatni radovi
asphalt concrete and related work will be vezani za asfaltiranje; poslijednje, probno
constructed;Lastly,have a loading.test for opterećenje mostovske konstrukcije.
bridge

3.2.5 Conception of materials,devices 3.2.5 Koncept materijala , uredjaja i


and other resources transportation ostalih sredstava transporta

i Cement:It will be transported from local to Cement: Biće transportovan od skladišta do


the site by carrier vehicle.Also cement tanker gradilišta vozilima. Takođe će tanker za
can transport from Serbia and Croatia. cement biti transportovan iz Srboje ili
Hrvatske.

ii Macadam, sand: Will be transported from Makadam, pijesak: Biće transportovan sa

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
60
local sand & stone borrow area to the site by lokalnog pozajmista pijeska I kamena do
carrier vehicle. gradilišta vozilima.

Iii Water reducer, accelerator: will be Plastifikator, akcelerator. Biće transportovani


transported from local to the site by carrier sa lokalnog skladišta do gradilišta vozilima.
vehicle.

Iv Steels (steel plate, H-form steels, steel pipe, Čelik (čelične ploče, H-čelični profili, čelične
steel wire mesh, bolts and rebar): will be cijevi, čelične mreže, ankeri I armaturne šipke)
transported from Serbia and China or Turkey biće transportovani iz Srbije i Kine ili Turske
to the site by Bar port, then deliver to the site preko luke Bar, a zatim dovezeni na gradilište
by carrier vehivle.. kamionima.

v Waterproof board, geotextile: will be Hidroizolacijone ploče, geotekstil: biće


transported from Italy to Bar port though ocean dovoženi iz Italije do luke Bar preko mora
shipping, then transported from bar port to the brodovima, a zatim iz luke Bar kamionima na
site by carrier vehicle. gradilište.

Vi Drainage pipe material : will be transported Materijal za drenažne cijevi: biće


from Serbia to the site by carrier vehicle. transportovan iz Srbije do gradilišta
kamionima.

Vii strand and anchor (prestressing Snopovi užadi za prenaprezanje I kotve


equipment): will be transport from China with (oprema za prednaprezanje): biće
containers to Bar port, then deliver to the site transportovani iz Kine u kontejnerima do luke
by carrier vehivle. Bar, a zatim na gradilište dostavljeni
kamionima.

viii Fuel oil : will be transported from Gorivo: biće transportovano iz Crne Gore I
Montenegro and surrounding countries to the okolnih zemalja do gradilišta kamionima.
site by carrier vehicle.

ix Equipment: : will be transported from Oprema: biće transportovana iz Crne Gore I


Montenegro and China to the site. Kine do gradilišta.

3.3 Design of preliminary and 3.3 Projekat prethodnih I pripremnih

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
61
preparatory works radova

3.3.1 Concept of relocation and/or 3.3.1 Koncept izmještanja ili


demolition of existing structures uklanjanja postojećih elemenata

There are two 10KV High Voltage Electric Postoje dva dalekovoda na stacionažama km
Wires at chainage K5+100 and K7+600, they 5+100 i km 7+600, u upotrebljivom su stanju
are in use condition but need be removed. ali moraju biti uklonjeni. Na površini na kojoj se
There is no resident house in construction gradi autoput nema stambenih objekata.
corridor.

3.3.2 Concept of internal roads, 3.3.2 Koncept puteva za internu


connection to the external roads and upotrebu na projektu, veza sa
access roads spoljnim putevima i pristupnim
putevima

There are 2 new access roads and 1 new Postoje dva nova pristupna puta I jedan
temporary steel bridge connect all working site privrejeni čelični most koji povjezuju cijelo
and batching plant. Access road a4 connects gradilište kao I fabriku betona. Pristupni put a4
state highway M2 with abutment A0, P1 and povezuje magistralni put M2 sa obalnim
P2, the access road a7 connects the rest parts stubom A0, I stubovima P1 I P2, pristupni put
of Moracica Bridge with concrete batching a7 povjezuje ostale dijelove Mosta Moračica
plant and Moracica Camp, the temporary steel sa fabrikom betona i kampom Moračica, a sam
bridge connects access roads a4 and a7. privremjeni čelični most povjezuje pristupne
puteve a4 I a7.
All roads and structures Mentioned earlier see
attachment 1. Koncept svih puteva je u sledecem crtezu:

3.3.3 Concept of water supply and 3.3.3 Koncept vodosnabdijevanja i


power supply napajanja elektricnom energijom

The water demand is supplied by underground Voda se dobija iz podzemne vode iz bunara na
water from a well at Moracica Camp, and river kampu Moračica, i iz riječne vode iz reke
water from Moraca River. Two power Morača. Dva agregata će snabdijevati
generators will supply the power demand gradilište strujom tokom pripremnih radova, a
during preparatory period, then the Bridge potom će trafostanice na gradilištu mosta biti
construction site transformers will be priključene na trafostanicu 400kVA na
connected with 400KVA High Voltage stacionaži km 6+740, na trafostanicu 630kVA
transformer at chainage K6+740, 630KVA na stacionaži km 7+120, i na još jednu
High Voltage transformer at chainage K7+120, trafostanicu 630kVA koja se nalazi na kampu
and one more 630KVA High Voltage Moračica, sve one će snabdijevati strujom
transformer which is in the Moracica Camp will cijelo gradilište Mosta Moračica kao i fabriku

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
62
supply power for the Moracica Camp and betona.
concrete batching plant, power-net will cover
all working site for the Moracica Bridge.

3.3.4 Concept of positioning and 3.3.4 Koncept pozicioniranja i lokacija


location of plant fabrike betona

The Moracica Camp is located at chainage Kamp Moračica nalazi se na stacionaži km


K7+000 right side of the Bridge. There are 7+000 sa desne strane budućeg mosta, U
concrete batching plant, one steel reinforced okviru kampa Moračica postoje fabrika betona,
processing steel plateau, one steel shed plato za pripremu armaturnih šipki, armirački
warehouse, one steel structure processing pogon, a deponija za odlaganje otpadaka
shed are located around the Moracica Camp, nalazi se na stacionaži km 7+100 sa leve
the dump area is located at chainage K7+100 strane budućeg mosta.
left side of the Bridge.

3.3.5 Design of temporary settlement 3.3.5 Projekat privremenih naselja sa


with the facilities objektima

Refer to attachment 2 Prilog br. 2

3.3.6 Site organization scheme 3.3.6 Shema organizacije gradilišta

In order to stop unauthorized person, animals U cilju spriječavanja ulaska nepoznatih lica,
and vehicles entering the construction area, kao i životinja I vozila na gradiliste, gradilište
the Moracica Bridge construction site is full Mosta Moračica biće ograđeno osim spojnih
surrounded by fence except the connections tačaka sa pristupnim putevima. Na gradilištu
with access roads. At least two security offices će postojati najmanje dvije čuvarske kućice.
work at site.

The water demand for concrete batching plant Fabrika betona snabdijeva se vodom iz
is supplied by underground water from a well podzemne vode iz bunara na kampu
at Moraica Camp, the water demand for bridge Moračica, a voda za potrebe izgradnje mosta
construction site is supplied by river water obezbijeđuje se iz rijeke Morače, voda će biti
from Moraca River. the water will pumped direktno pumpana iz rijeke do svakog dela
directly from river to each working site. Two gradilišta. Dva agregata snabdijevaće
power generators will supply the power gradilište strujom kada je javno snabdijevanje
demand when the public power is shortly privremeno prekinuto, glavno snabdijevanje
stopped, the main power supply is by two strujom je putem dve trafostanice 400kVA i
transformers 400KVA and 630 KVA which are 630kVA koje se nalaze na stacionažama km
located at chainage K6+740 and K7+120. 6+740 i km 7+120.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
63
The warehouse, oxygen room, explosive Skladište, prostorija sa kiseonikom, skladište
storage house, generator places will be za eksplozivne uređaje i generatori biće
equipped withthe fire extinguishers. snabdeveni aparatima za gašenje požara.

Refer to attachment 3 Prilog br. 3

Time-Distance see attachment 4 Vreme --Razdaljina Prilog br.4

3.3.6.1 Access road and temporary traffic 3.3.6.1 Pristupni put i privremena
signalization saobraćajna signalizacija

Separate Designs within preparatory works Za pristupni put i privremenu saobraćajnu


are prepared for access road and temporary signalizaciju su urađeni posebni projekti u
traffic signalization. These Designs are okviru pripremnih radova. Ovi projekti su
approved by Supervisor. Company odobreni od strane nadzornog organa.
"Geoprojekt Perišić" prepared Elaborate on Elaborat saobraćajne signalizacije je uradila
Traffic Signalization and this Elaborate is firma "Geoprojekt Perišić" I odobren je I od
approved by competitive Agency for traffic of strane nadležne Direkcije za saobraćaj Crne
Montenegro. The excerpts from this Design Gore. U prilogu ovog projekta se prilažu izvodi
are attached in the Appendix of this Design: iz ovih projekata I to:

Layout of access road see attachment 5 Situacija pristupnog puta Prilog br. 5

Traffic signal see attachment 6 Saobraćajna signalizacija, Prilog br. 6

3.4 Time, money and resource 3.4 Planiranje vremena, troškova i


planning resursa

3.4.1 Conception of materials, electric 3.4.1 Koncept materijala, električnog


power and other resources napajanja i drugih resursa

The main material for Moracica Bridge is Glavni materijal za Most Moračica uglavnom je
almost purchased in Montenegro; the part nabavljen u Crnoj Gori; dio koji se ne može
which Montenegro cannot supply will be naći na crnogorskom tržištu biće kupljen u
purchased from the countries around. okolnim zemljama. Gradilište Moračica biće
Moracica camp will be supplied with the sand snabdijeveno pijeskom, I drobljenim
and crushed stone material by the site Crusher materijalom iz drobilišnog pogona Mrke.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
64
Plant Mrke.

Construction power: Power generators supply Struja na gradilistu: Agregati će biti


construction power during preparatory period, snabdijevani tokom pripremnih radova, a
then the construction transformers will be potom će trafostanice biti priključene na dve
connected with two main transformers glavne trafostanice 400kVA i 630kVA koje se
400KVA and 630 KVA which are located at nalaze na stacionaži km 6+470 i km 7+120.
chainage K6+740 and K7+120.

Water on construction site: the construction Voda na gradilistu: Voda na gradilištu biće
water demand is pumped to construction site ispumpavana iz rijeke Morače I bunara na
from Moraica River and a well in the Moracica kampu Moračica.
camp.

3.4.2 Planing of works 3.4.2 Plan radova

3.4.2.1Static plan in terms of labor and 3.4.2.1Plan angažovanja radne snage i


Machinery for Moracica Bridge masina na Moracica mostu

Table/Talbe 3.4-1 Works planning of Moracica Bridge/ Planirani radovi Moracica Most

Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

S2 pier
1 construction / S2
stub

foundation
2016.03.15~201 Dumper,Excavator,Loader/Damper,R
1.1 excavation/iskop 12
6.08.12 ovokopac,Utovarna
temelja

crane,Flat truck,Truck concrete


pump,Reabr cutting machine,Rebar
foundation bender machine,Reabr threading
2016.08.13~201
1.2 construction/izvo 35 Machine/Kran,Ravni kamion,Kimion
6.10.11
djenje temelja sa pumpom za betoniranje,Masina za
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
65
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

armature

crane,Tower crane,Creeping
formwork,Flat truck,Truck concrete
pump,Reabr cutting machine,Rebar
bender machine,Reabr threading
Machine,Trailer concrete
pier shaft
2016.10.12~201 pump/Kran,Toranjski kran,Mobilna
1.3 ( 150.5m)/Izrad 40
7.09.15 oplata,Ravni kamion,Kimion sa
a stuba(150.5m)
pumpom za betoniranje,Masina za
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature,Prikolica sa betonskom
pupom

crane,Tower crane,Flat truck,Reabr


cutting machine,Rebar bender
machine,Reabr threading
0# concreting
Machine,Trailer concrete
above the
2017.09.16~201 pump/Kran,Toranjski kran,Ravni
1.4 braket/0# 40
7.11.19 kamion,Masina za secenje
betoniranje
armature,Masina za spajanje
nultog segmenta
oplate,Masina za ispravljanje
armature,Prikolica sa betonskom
pumpom

balance crane,Tower crane,Cantilever


cantilever formwork,Flat truck,Reabr cutting
execution ( 22 machine,Rebar bender
segments ) machine,Reabr threading
2017.11.20~201 Machine,Tensioning equipment,Trailer
1.5 /Izvodjenje 64
8.10.12 concrete pump/Kran,Toranjski
slobodnih
konzolnih kran,Kantiliver oplata,Ravni
segmenata (22 kamion,Masina za secenje
segments) armature,Masina za spajanje
oplate,Masina za ispravljanje

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
66
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

armature,Oprema za
zatezanje,Prikolica sa betonskom
pupom

S3 pier
2 construction/S3
stub

foundation
2016.04.04~201 Dumper,Excavator,Loader/Damper,R
2.1 excavation/iskop 12
6.05.03 ovokopac,Utovarna
temelja

crane,Flat truck,Truck concrete


pump,Reabr cutting machine,Rebar
bender machine,Reabr threading
foundation
2016.05.04~201 Machine/Kran,Ravni kamion,Kimion
2.2 construction/izvo 35
6.07.02 sa pumpom za betoniranje,Masina za
djenje temelja
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature

Concrete,Rebar,crane,Tower
crane,Creeping formwork,Flat
truck,Truck concrete pump,Trailer
pier shaft
2016.07.03~201 concrete pump,bridge construction
2.3 ( 158.5m)/Izrad 40
7.07.12 team /Kran,Toranjski kran,Mobilna
a stuba(158.5m)
oplata,Ravni kamion,Kimion sa
pumpom za betoniranje,Prikolica sa
betonskom pumpom

0# concreting crane,Tower crane,Flat truck,Reabr


above the cutting machine,Rebar bender
2017.07.13~201 machine,Reabr threading
2.4 braket/0# 40
7.09.15 Machine,Trailer concrete
betoniranje
nultog segmenta pump/Kran,Toranjski kran,Ravni
kamion,Masina za secenje

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
67
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

armature,Masina za spajanje
oplate,Masina za ispravljanje
armature,Prikolica sa betonskom
pumpom

crane,Tower crane,Cantilever
formwork,Flat truck,Reabr cutting
balance
machine,Rebar bender
cantilever
machine,Reabr threading
execution ( 22
Machine,Tensioning equipment,Trailer
segments )
2017.09.16~201 concrete pump/Kran,Toranjski
2.5 /Izvodjenje 64
8.08.18 kran,Kantiliver oplata,Ravni
slobodnih
kamion,Masina za secenje
konzolnih
armature,Masina za spajanje
segmenata (22
oplate,Masina za ispravljanje
segments)
armature,Oprema za zatezanje,
Prikolica sa betonskom pumpom

S4 pier
3 construction/S4
stub

foundation
2016.03.25~201 Excavator,Dumper,Loader/Rovokopac
3.1 excavation/iskop 12
6.07.22 ,Damper,Utovarna
temelja

crane,Flat truck],Truck concrete


pump,Reabr cutting machine,Rebar
foundation bender machine,Reabr threading
construction 2016.07.23~201 Machine/Kran,Ravni kamion,Kimion
3.2 35
/izvodjenje 6.09.20 sa pumpom za betoniranje,Masina za
temelja secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature

3.3 pier shaft 2016.09.21~201 40 crane,Tower crane,Creeping

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
68
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

( 152m)/Izrada 7.08.25 formwork,Flat truck,Truck concrete


stuba(152m) pump,Reabr cutting machine,Rebar
bender machine,Reabr threading
Machine,Trailerconcrete
pump/Kran,Toranjski kran,Mobilna
oplata,Ravni kamion,Kimion sa
pumpom za betoniranje,Masina za
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armaure, Prikolica sa betonskom
pumpom

crane,Tower crane,Flat truck,Reabr


cutting machine,Rebar bender
machine,Reabr threading
0# concreting
Machine,Trailer concrete
above the
2017.08.26~201 pump/Kran,Toranjski kran,Ravni
3.4 braket/0# 40
7.10.29 kamion,Masina za secenje
betoniranje
armature,Masina za spajanje
nultog segmenta
oplate,Masina za ispravljanje
armature,Prikolica sa betonskom
pumpom

crane,Tower crane,Cantilever
formwork,Flat truck,Reabr cutting
balance machine,Rebar bender
cantilever machine,Reabr threading
execution ( 22 Machine,Tensioning equipment,Trailer
segments ) concrete pump/Kran,Toranjski
2017.10.30~201
3.5 /Izvodjenje 64 kran,Kantiliver oplata,Ravni
8.09.21
slobodnih kamion,Masina za secenje
konzolnih armature,Masina za spajanje
segmenata (22 oplate,Masina za ispravljanje
segments) armature,Oprema za
zatezanje,Prikolica sa betonskom
pupom

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
69
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

S5 pier
4 construction/S5st
ub

foundation
2016.04.30~201 Excavator,Dumper,Loader/Rovokopac
4.1 excavation/iskop 12
6.09.11 ,Damper,Utovarna
temelja

crane,Flat truck,Truck concrete


pump,Reabr cutting machine,Rebar
foundation bender machine,Reabr threading
construction 2016.09.21~201 Machine/Kran,Ravni kamion,Kimion
4.2 35
/izvodjenje 6.11.19 sa pumpom za betoniranje,Masina za
temelja secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature

crane,Flat truck,Truck concrete


pump,Tower crane,Creeping
formwork,Reabr cutting
machine,Rebar bender
machine,Reabr threading Machine,
pier shaft Trailer concrete pump./Kran,Ravni
2016.11.20~201
4.3 ( 78m)/Izrada 40 kamion,imion sa pumpom za
7.06.12
stubat(78m) betoniranje,Toranjski kran,Mobilna
oplata,Masina za secenje
armature,Masina za spajanje
oplate,Masina za ispravljanje
armature, Prikolica sa betonskom
pumpom

crane,Flat truck,Truck concrete


0# concreting
2017.06.13~201 pump,Tower crane,Reabr cutting
4.4 above the 40
7.08.16 machine,Rebar bender
braket/0#
machine,Reabr threading
betoniranje
Machine,Trailer concrete
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
70
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

nultog segmenta pump./Kran,Ravni kamion,Kimion sa


pumpom za betoniranje,Toranjski
kran,Masina za secenje
armature,Masina za spajanje oplate,
Masina za ispravljanje armature,
Prikolica sa betonskom pumpom

crane,Flat truck,Tower
crane,Cantilever formwork,Reabr
balance
cutting machine,Rebar bender
cantilever
machine,Reabr threading
execution ( 22
Machine,Tensioning equipment ,
segments )
2017.08.17~201 Trailer concrete pump./Kran,Ravni
4.5 /Izvodjenje 64
8.07.09 kamion,Toranjski kran,Kantiliver
slobodnih
oplata,Masina za secenje
konzolnih
armature,Masina za spajanje
segmenata (22
oplate,Masina za ispravljanje
segments)
armature,Oprema za zatezanje,
Prikolica sa betonskom pumpom

S1 pier
5 construction/S1st
ub

foundation
2016.11.26~201 Excavator,Dumper,Loader/Rovokopac
5.1 excavation/iskop 12
7.04.26 ,Damper,Utovarna
temelja

crane,Flat truck,Truck concrete


pump,Reabr cutting machine,Rebar
foundation
bender machine,Reabr threading
construction 2017.04.27~201
5.2 35 Machine/Kran,Ravni kamion,Masina
/izvodjenje 7.06.25
za secenje armature,Masina za
temelja
spajanje oplate,Masina za ispravljanje
armature

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
71
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

crane,Flat truck,Truck concrete


pump,Tower crane,Creeping
formwork,Reabr cutting
machine,Rebar bender
machine,Reabr threading
pier shaft Machine,Trailer concrete
2017.06.26~201
5.3 ( 51m)/Izrada 40 pum./Kran,Ravni kamion,Kimion sa
7.11.29
stuba(51m) pumpom za betoniranje,Toranjski
kran,Mobilna oplata,Masina za
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature,Prikolica sa betonskom
pumpom

crane,Flat truck,Truck concrete


pump,Tower crane,Reabr cutting
machine,Rebar bender
machine,Reabr threading
0# concreting
Machine,Trailer concrete
above the
2017.11.30~201 pump/KranRavni kamion,Kimion sa
5.4 braket/0# 40
8.02.02 pumpom za betoniranje,Toranjski
betoniranje
kran,Masina za secenje
nultog segmenta
armature,Masina za spajanje
oplate,Masina za ispravljanje
armature,Prikolica sa betonskom
pumpom

crane,Flat truck,Tower
balance
crane,Cantilever formwork,Reabr
cantilever
cutting machine,Rebar bender
execution ( 22
2018.02.03~201 machine,Reabr threading
5.5 segments ) 64
8.10.23 Machine,Tensioning equipment,Trailer
/Izvodjenje
concrete pump./Kran,Ravni
slobodnih
kamion,Toranjski kran,Kantiliver
konzolnih
oplata,Masina za secenje
segmenata (22
armature,Masina za spajanje
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
72
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

segments) oplate,Masina za ispravljanje


armature,Prikolica sa betonskom
pumpom

O1 abutment
6 construction/O1
obalni stub

crane,Flat truck,Truck concrete


pump,Excavator,Reabr cutting
machine,Rebar bender
machine,Reabr threading
abutment
2017.04.27~201 Machine,Dumper, Loader./Kran,Ravni
6.1 construction/Izra 21
7.12.22 kamion,Kimion sa pumpom za
da obalnog stuba
betoniranje,Rovokopac,Masina za
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature,Damper,Utovarna

crane,Truck concrete pump,Flat


truck,Reabr cutting machine,Rebar
bender machine,Reabr threading
Machine,Tensioning equipment,Trailer
side section
concrete pump/Kimion sa pumpom za
concreting/betoni 2018.07.30~201
6.2 30 betoniranje,Ravni kamion,Masina za
ranje prve 8.11.26
secenje armature,Masina za spajanje
sekcije
oplate,Masina za ispravljanje
armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

O2 abutment
7 construction/O2
obalni stub

7.1 abutment 2016.09.12~201 21 crane,Flat truck,Truck concrete

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
73
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

construction/Izra 7.05.09 pump,Excavator,Reabr cutting


da obalnog stuba machine,Rebar bender
machine,Reabr threading
Machine,Dumper/Kran,Ravni
kamion,Kimion sa pumpom za
betoniranje,Rovokopac,Masina za
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature,Damper,Utovarna

crane,Truck concrete pump,Flat


truck,Reabr cutting machine,Rebar
bender machine, Reabr threading
side section
Machine,Tensioning equipment /
concreting/betoni 2018.07.30~201
7.2 20 Kran,Kimion sa pumpom za
ranje prve 8.11.26
betoniranje,Ravni kamion,Masina za
sekcije
secenje armature,Masina za spajanje
oplate,Masina za ispravljanje
armature, Oprema za.

Flat truck,Reabr cutting


machine,Rebar bender
machine,Reabr threading
S2-S3 span
Machine,Tensioning equipment,Trailer
closure segment
2018.10.13~201 concrete pump/Ravni kamion,Masina
8 placing/S2-S3 30
8.11.11 za secenje armature,Masina za
povezivanje
spajanje oplate,Masina za ispravljanje
konstrukcije
armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

S3-S4 span Flat truck,Reabr cutting


closure segment machine,Rebar bender
2018.10.13~201
9 placing/S3-S4 30 machine,Reabr threading
8.11.11
povezivanje Machine,Tensioning equipment,Trailer
konstrukcije concrete pump/Ravni kamion,Masina

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
74
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

za secenje armature,Masina za
spajanje oplate,Masina za ispravljanje
armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

Flat truck,Reabr cutting


machine,Rebar bender
machine,Reabr threading
S1-S2 span
Machine,Tensioning equipment,Trailer
closure segment
2018.10.28~201 concrete pump/Ravni kamion,Masina
10 placing/S1-S2 30
8.11.26 za secenje armature,Masina za
povezivanje
spajanje oplate,Masina za ispravljanje
konstrukcije
armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

Flat truck,Reabr cutting


machine,Rebar bender
machine,Reabr threading
S4-S5 span
Machine,Tensioning equipment,Trailer
closure segment
2018.10.28~201 concrete pump/Ravni kamion,Masina
11 placing/S4-S5 30
8.11.26 za secenje armature,Masina za
povezivanje
spajanje oplate,Masina za ispravljanje
konstrukcije
armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

Flat truck,Reabr cutting


01-S1 span machine,Rebar bender
closure segment machine,Reabr threading
2018.11.12~201 Machine,Tensioning equipment,Trailer
12 placing/O1-S1 30
8.12.11 concrete pump/B,Ravni
povezivanje
konstrukcije kamion,Masina za secenje
armature,Masina za spajanje
oplate,Masina za ispravljanje

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
75
Labour
NO/ Project Items/ Duration/ (person)/ machine(set) /Masinerija
Br. Stavke projkta Trajanje radnici (set)
(osobe)

armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

Flat truck,Reabr cutting


machine,Rebar bender
machine,Reabr threading
S5-02 span
Machine,Tensioning equipment,Trailer
closure segment
2018.11.12~201 concrete pump/Ravni kamion,Masina
13 placing/S5-O2 30
8.12.11 za secenje armature,Masina za
povezivanje
spajanje oplate,Masina za ispravljanje
konstrukcije
armature,Oprema za
zatezanje,Prikolica sa betonskom
pumpom

Construction od
bridge deck
system and
2018.12.12~201
14 ancillary 30 crane,Flat truck/Kran,Ravni kamion
9.04.23
facilitie/Izrada
ploce I pomocnih
objekata mosta

2019.04.24~201
15 loading test 12
9.04.26

3.4.2 Transportation plan of material 3.4.2 Plan transporta mašina I opreme


and machine

Transport of materials and equipment that are Transport materijala i opreme koji su u
owned by the company will be carried out with vlasništvu firme će se obavljati sa odredišta
its own transport vehicles. When we are sopstvenim prevoznim sredstvima. Kada je reč
talking about machines, any remaining o mehanizaciji, sva preostala oprema će se
equipment will be transported by trucks to the transportovati pomoću niskonosećih prikolica
construction site. Regarding oil, which will be do gradilišta. Kada je reč o gorivu, koja će se

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
76
used for machinery and other equipment, the koristiti za mašine i drugu opremu, taj
transportation will be executed by cisterns. transport će se obavljati cisternama.
Reinforcement mesh, reinforcing bars of Armaturne mreže, armaturne šipke raznih
different profiles, beams, anchors, and all profila, čelični nosači, ankeri i sav ostali
other materials will be transported to the site materijal će se do gradilišta transportovati
by trucks, while the certain transport will be pomoću šlepera i kamiona, dok će se
carried out using excavator depending on the unutrašnji transport vršiti pomoću bagera u
length of transport. zavisnosti od dužine transporta.

When we talk about some specific devices, Kada se govori o nekim posebnim uređajima,
their transport from suppliers to the njihov transport od dobavljača do gradilišta će
construction site will be carried out by vehicles se vršiti pomoću specijalnih vozila koja su
which are equipped for that type of work. This opremljena za tu vrstu posla. Taj materijal će
material will be kept in special storage for that se čuvati u specijalnim magacinima za to vrstu
type of work. qualified for that type of work. posla i od strane osoblja koje je kvalifikovano
za tu vrstu radova.

Hydraulic formwork will be transported from Hidradulične oplate će se transportovati od


the container to the construction site by trucks. magacina do gradilišta pomoću kamiona.

When we talk about concrete, it will be Kada je reč govori o betonu, taj transport
transported from the site batching plant to the vršiće se od fabrike betona do mosta pomoću
bridge by concrete mixer. automiksera.

3.5 Study on occupational safety 3.5 Studija o bezbjednosti na radu

3.5.1 General data on construction 3.5.1 Osnovni podaci o građevinskim


works for the phase of preliminary radovima za fazu pripremnih radova
works

For execution of new, i.e. reconstruction of the Za izgradnju novih, odnosno rekonstrukciju
existing access roads following construction postojećih pristupnih saobraćajnica na
works shall be executed on the site: gradilištu će se izvoditi sljedeći građevinski
radovi:

• cutting of trees and bushes • odstranjivanje grmlja i drveća

• topsoil stripping • iskop humusa

• material excavation • iskop materijala

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
77
• transport of the excavated material • odvoženje iskopanog materijala

• excavation of steps i.e. stepped cutting of • iskop stepenica tj stepenasto zasijecanje


field on steep terrain terena na strmim terenima

• execution of embankment • izrada nasipa

• transport and backfilling of the material • dovoženje i nasipanje materijala

• preparation of the subgrade of the road • uređenje planuma tj. posteljice puta

• embankment layers compaction • nabijanje slojeva nasipa

• execution of the lower bearing layer made • izrada donjeg nosećeg sloja od
of unbounded material i.e. blanket course nevezanog materijala, odnosno tamponskog
sloja

• execution of the upper bearing layer • izrada gornjeg nosećeg sloja

• execution of the wearing layer. • izrada habajućeg sloja.

For dumps formation, whose purpose is Za formiranje deponija, čija je svrha odlaganje
disposal of the surplus of material which shall viška materijala koji će se javiti u procesa
be resent over execution of excavation works, iskopnih radova., na gradilištu će se izvoditi
following construction works shall be executed sljedeći građevinski radovi:
at the site:

• cutting of trees and bushes • odstranjivanje grmlja i drveća

• topsoil stripping and material excavation • iskop humusa i materijala

• transport of the excavated material • odvoženje iskopanog materijala

• execution of subgrade as well as of the • uređenje planuma tj. posteljice kako same
dump itself and accompanying road deponije tako I pripadajućeg puta

• execution of the lower bearing layer made • izrada donjeg nosećeg sloja od
of unbounded material i.e. blanket course nevezanog materijala, odnosno tamponskog
sloja

For execution of camps with accompanying Za izgradnju kampova sa pratećim sadržajima


contents for accommodation of the employees za smještaj zaposlenih izvodiće se sljedeći
following construction works shall be građevinski radovi:
executed:
• odstranjivanje grmlja i drveća
• cutting of trees and bushes
• iskop humusa i materijala
• topsoil stripping and material excavation
• odvoženje iskopanog materijala

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
78
• transport of the excavated material • uređenje planuma tj. posteljice

• execution of subgrade • izrada donjeg nosećeg tamponskog sloja


zone za parkiranje i saobraćajnica u sklopu
• execution of the lower bearing layer made
kampa
of unbounded material i.e. blanket course

• carpentry works for the necessities of • tesarski radovi za potrebe izgradnje


camp construction kampa

• reinforcement works for the necessities of • armirački radovi za potrebe izgradnje


camp construction kampa

• concreting of foundations, recreation • betoniranje podložnih betona, temelja,


polygons rekreacionih poligona

• assembly works • monterski radovi

• asphalting of parking lots and roads within • asfaltiranje parking zona I saobraćajnica u
the camp sklopu kampa

For construction i.e. assembly of the concrete Za izgradnju, odnosno montažu fabrike
factory, asphalt base and facility for stone betona, asfaltne baze i postrojenja za
crushing following construction works shall be drobljenje izvodiće se sljedeći građevinski
executed: radovi:

• cutting of trees and bushes • odstranjivanje grmlja i drveća

• topsoil stripping and material excavation • iskop humusa i materijala

• transport of the excavated material • odvoženje iskopanog materijala

• execution of subgrade • uređenje planuma tj. posteljice

• execution of the lower bearing layer made • izrada donjeg nosećeg tamponskog sloja
of unbounded material i.e. blanket course zone za manevar teretnih vozila i pripadajućih
saobraćajnica

• carpentry works for the necessities of • tesarski radovi za potrebe izgradnje


foundation and other bearing elements temelja i drugih nosećih elemenata
construction

• reinforcement works for the necessities of • armirački radovi za potrebe izgradnje


foundation and other bearing elements temelja i drugih nosećih elemenata
construction

• concreting of foundations and other • betoniranje podložnih betona, temelja i

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
79
bearing elements drugih nosećih elemenata

• assembly works • monterski radovi

For construction of drainage and sewage Za izgradnju vodovodne i kanalizacione


infrastructure following construction works infrastrukture izvodiće se sljedeći građevinski
shall be executed: radovi:

• digging of canals for pipe placement • kopanje kanala za polaganje cijevi,

• reinforcement, carpentry and concrete • armirački, tesarski i betonerski radovi na


works on construction of manholes, pools etc. izgradnji šahtova, bazena i sl.

• placement of the pipes, i.e. canals • Zatrpavanje cijevi, odnosno kanala.

3.5.2 Construction pits, works under 3.5.2 Građevinske jame, radovi pod
ground, tunnels and earth works zemljom, tuneli i zemljani radovi

Over works in construction pits, underground Kod radova u građevinskim jamama, pod
of in tunnels, following protective measures zemljom ili u tunelima moraju se preduzeti
have to be undertaken: slijedeće sigurnosne mjere:

• use corresponding supporting • koristiti odgovarajuće potporne –


constructions or embankment; razuporne konstrukcije ili nasip;

• remove dangers from falling of persons, • otkloniti opasnosti od pada osoba,


material or object or dangers of floods; materijala ili predmeta ili opasnosti od poplava;

• ensure constant opening of all work • osigurati konstantno provjetravanje svih


places in order to ensure that the workers mjesta rada u toj mjeri da se radnicima osigura
have proper air quality; primjerena kvalitet vazduha;

• enable the workers to move to a safe área • omogućiti radnicima, da se sklone na


in case of fire or water and material sigurno područje u slučaju požara ili prodora
penetration. vode ili materijala.

• Before commencement of digging, • Prije početka iskopavanja, moraju se


measures should be undertaken to see and preduzeti mjere da se uoči i smanji na
decrease to the minimum measure possible najmanju moguću mjeru svaka opasnost
any type of danger caused by underground uzrokovana od podzemnih el.kablova i drugih
el.cables and other installations. instalacija.

• Safety roads of excavation have to be • Moraju se osigurati sigurni putevi u i iz


ensured. mjesta iskopavanja.

• Lots of soil, material and transport • Hrpe zemlje, materijali i prijevozna vozila
vehicles have to be at safe distance from the moraju biti na sigurnoj udaljenosti od

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
80
construction pits. građevinskih jama.

• If this cannot be ensured, obstacles • Ako se to ne može osigurati, moraju se


such as fences should be placed. postaviti zapreke u vidu ograda, odbojnika i
slično.

Excavator Bager

Before an excavator enters into site, it is Prije nego što bager uđe na gradilište
necessary to perform examination of its potrebno je da se izvrši ispitivanje njegove
stability, and on the ruins to examine stabilnosti, a na ruševinama da se naročito
especially possible existence of basements, ispita eventualno postojanje podruma, tunela,
tunnels, gas lines, pipelines, cables etc. gasovoda, vodovoda, kablova i sl.

For works, excavator should be placed onto Za rad, bager treba da se postavi na
planned surface and to be firmed for avoiding isplaniranu površinu i da se učvrsti radi
the unpredicted and unwanted movement. For izbjegavanja nepredviđenog i neželjenog
firming coasters are used which are borne pomjeranja. Za učvršćivanje se koriste
along the excavator as its constant equipment. podmetači koji se nose uz bager kao njegova
It is forbidden to put objects under excavator stalna (inventarska) oprema. Zabranjeno je da
caterpillars some object which are found or se pod gusjenice bagera stavljaju predmeti koji
available. se slučajno zateknu ili nađu pri ruci.

In case that during works any underground U slučaju da se u toku rada otkriju bilo kakve
communication is discovered, works are podzemne komunikacije, radovi obavezno
obligatorily stopped and it is obligatory to treba da se obustave i da se preduzmu
undertake corresponding measures for odgovarajuće mjere radi dobijanja uputstva
obtaining measures for obtaining instructions kako da se dalje postupi.
on how to act furtherly.

Properly made stairs with handrail have to Za penjanje u kabinu ili na radnu platformu
exist for climbing into the cabin or onto the bagera mora da postoje propisno urađene
work platform of the excavator. stepenice sa rukohvatom.

Over excavator working with electro drive, Pri radu bagera sa električnim pogonom
turning on of the engine has to be performed puštanje motora treba da se izvodi polako,
easily, gradiantly and to monitor over amper postepeno i pri tome da se prati preko
meter that the electricity power is not ampermetra da jačina struje ne prekorači
surpassing allowed boundary (marked with red dozvoljenu granicu (označenu crvenom
line). crtom).

Taking off of the implemented protections Zabranjeno je skidanje ugrađenih zaštita za


during work of the excavator is forbidden. vrijeme rada bagera.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
81
When electro engines are overheated, when Kada se elektromotori prekomjerno zagriju,
there is a bad supply of oil and sparkles on kada postoji loš dovod ulja i varničenje na
contacts, excavator should be turned off and kontaktima, treba da se prekine rad bagera i
electrician should be called. If melting fuses of da se pozove električar. Ako topljivi osigurači
the electro engine are burned, they can be elektromotora pregore, oni smiju da se
replaced only when the electricity is shut zamijene samo kada se isključi struja, pri
down, over which it is forbidden to use none čemu je zabranjeno da se za zamjenu koriste
corresponding ‘’cartridges’’. neodgovarajući „patroni“.

On the excavator with engine with internal Na bageru sa motorom sa unutrašnjim


burning it is forbidden to keep containers with sagorjevanjem zabranjeno je držanje sudova
fuel. After providing the reservoir with fuel, sa gorivom. Posle snabdijevanja rezervoara
engine must be whipped well. It is forbidden, sa gorivom motor treba obavezno brižljivo da
also, to smoke or use open fire when checking se izbriše. Zabranjeno je, takođe, da se kod
the level over filling the reservoir, to spread fire provjere nivoa goriva pri punjenju rezervoara
near the excavator and to watch the excavator koristi otvorenim plamenom i da se puši, da se
with torchlights – open fire. raznose ugarci (vatra) u neposrednu blizinu
bagera i da se osmatra bager sa primjenom
buktinja za osvjetljenje – otvoreni plamen.

Normal rules do not allow anybody to cross Ustaljena pravila ne dozvoljavaju da se prolazi
and to be between the walls of the trench and i da se nalazi između zida rova i bagera bilo
excavator; to stand in front of the arrow, ko; da bilo ko stoji ispod strijele, kašike, na ivici
spoon, on the edge and in the bottom of the i u podnožju rova; da se strana lica nalaze u
trench; that outsiders are in radius of the arrow radijusu dejstva strijele plus 5 m (opasna
works plus 5m (dangerous area). zona).

Distance between the cabin of the excavator Rastojanje između kabine bagera sa čeonom
with frontal spoon and trench should be at kašikom i rova treba da bude najmanje 1 m;
least 1m; such distance over fall of the trench takvo isto rastojanje pri radu bagera sa
with deep spoon should be up to the limit of dubinskom kašikom treba da bude do granice
possible prism of landslide. moguće prizme klizanja zemljišta

Over working with the excavator, excavator Pri radu sa bagerom bageristi je zabranjeno:
worker is forbidden to:

• to change distance of the arrow with - da mijenja raspon strijele sa napunjenom


loaded spoon; kašikom;

• to perform load and discharge works with - da izvodi utovarne i istovarne radove sa
flat spoon; ravnom kašikom;

• to start mechanisms for rolling meanwhile - da stavlja u pogon mehanizme za


the spoon is digging; okretanje za vrijeme kopanja kašike;

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
82
• to perform regulating of the breaks, - da izvodi regulisanje kočnica, zamjenu
change of gears, cleaning of the spoon etc. zupčanika, čišćenje kašike i dr. pri podignutoj
when the spoon is lifted; kašici ;

• to lift and move with sheave of the - da podiže i premješta lopatom bagera
excavator small material, beams, boards and sitan materijal, grede, daske i ostale predmete.
other objects.

Load of soil into the truck should be performed Utovar zemlje u kamion treba da se izvodi sa
from the back or the side, in any case not over strane ili iza, a nikako preko kabine vozača. Pri
driver’s cabin. Over load truck driver is oblige utovaru vozač kamiona dužan je da izađe iz
to step out of the cabin and to wait for the load kabine i da sačeka utovar na bezbjednom
from the safe distance. rastojanju .

Descending of the excavator down the falls is Spuštanje bagera niz padove sopstvenim
permitted only if the excavator is in the first hodam dozvoljava se samo sa prvom brzinom
gear, connection is turned on and engine as kretanja, uključenom spojnicom i motorom.
well.

Electro equipment of the excavator should be Električni pribori bagera treba da se koriste u
used according to the rules on protection from duhu sa pravilima zaštite od električne struje.
the electricity.

During moving of the excavator, arrow is Za vrijeme premještanja bagera strijela treba
supposed to be placed in the direction of da se postavi u pravcu kretanja, a kašika da se
movement, and the spoon to be lifted for a podigne na visinu najmanje 0,5 m od zemlje.
height minimum 0.5m from the ground.

Possibility of an excavator to cross over Mogućnost prelaza bagera preko mostova


bridges should be checked first with a predhodno treba da se provjeri proračunom i
calculation and to be performed with da se obavi uz odgovarajuću organizaciju .
corresponding organization.

Each excavator should have a visible plate on Svaki bager treba sa obije strane da ima dobro
both sides stating: vidljivu tablicu sa natpisom:

Forbidden retention in the movement area of Zabranjeno zadržavanje u zoni kretanja


the excavator bagera

Prior to commencement of the excavator work, Prije nego što počne sa radom bagera
excavator worker has to mark it with bagerista mora to da označi zvučnim
continuous sound signals which are well ustaljenim signalima koji se dobro čuju.
audible.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
83
Managing the excavator can only be allowed Rukovanje bagerom može da se dozvoli samo
to persons who have the right to such osobama koje imaju pravo na rukovanje.
handling. It can only be a person that is older Pravo na rukovanje bagerom može da dobije
than 18 years, is he is familiar to excavator samo osoba starija od 18 godina, ako je
handling (passed exam). upoznata sa rukovanjem bagerom (položen
ispit).
If there is some break down discovered during
the works of the excavator, which jeopardize Ako se na bageru, u toku rada, otkriju kvarovi
safety at work, the excavator has to be koji ugrožavaju sigurnost u radu, rad bagera
stopped until the break down is removed. mora da se zaustavi sve dok se kvar ne
otkloni.

If during works the excavator worker notice Ako u toku rada bagerista primjeti zaposlene u
employees in dangerous area, he is obliged to opasnoj zoni, obavezan je da ih opomene, pa
notify them, and if the employees stay in the ako i pored njegove opomene zaposleni
dangerous area after thus, he must stop the ostanu u opasnoj zoni, mora da zaustavi
excavator. bager.

While the excavator is working it is forbidden Za vrijeme rada bagera zabranjeno je:
to do the following:

• retention of the employees on the - zadržavanje zaposlenih na bageru;


excavator,

• execution of any kind of repairs, - izvođenje bilo kakvih popravki,


lubrication or adjustment on the excavator; podmazivanja ili podešavanja na bageru;

• climbing on the excavator and descending - penjanje na bager i silaženje sa njega;


from it;

• disturbing the excavator worker with - odvraćanje pažnje bageriste nepotrebnim


unnecessary conversations; razgovorima;

• letting inside of the cabin other people, - puštanje u kabinu drugih lica, a posebno
especially children. djece.

3.5.3 Main construction works 3.5.3 Građevinks radovi

PROTECTIVE MEASURE IN METAL MESH MJERE ZAŠTITE PRI RADU SA


WORKS ARMATURNOM MREŽOM

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
84
Work on unloading, loading, transfer and Radu na istovaru, utovaru, prenosu i
preparation, straightening, cutting and pripremi, ispravljanju, sječenju i
bending, continuing and installation of savijanju, kontinuiranju i montaži armature,
concrete iron, to be used for reinforced koja se koristi za armirano-betonske elemente
concrete elements (reinforcement works) (armaturni radovi) ne može se pristupiti:
cannot be accessed:

1. With long hair, if is not connected or 1. Sa dugom kosom, ako nije vezana ili
covered with a cloth cap prekrivena platnenom kapom

2. With a loose or unbuttoned clothed or 2. Sa labavom ili otkopčanom odjećom ili bez
unclothed odjeće

3. Without protective shoes and gloves 3. Bez zaštitnih cipela i rukavica

When loading or unloading reinforcement Kada se utovara ili istovara armatura


cargo with crane, cargo is previous release sa dizalicom, teret se prethodno
from remained fittings and forcibly pulling out oslobodi od preostalih fitinga i nasilno
from the crowd is not allowed. izvlačenje iz gomile nije dozvoljeno.

Reinforcement bars are provided from Armaturne grede se obezbeđuju od pada


dropping during lifting by binding to the frame tokom podizanja vezivanjem za ram

Employees who perform tying steel ropes on Zaposleni koji obavljaju vezivanje čelične
the crane hook, must be removed to a safe užadi na kuku krana, moraju se ukloniti na
distance before it begins to cargo is raised. bezbjednu udaljenosti prije nego što se
započne sa dizanjem tereta.

The presence of persons in the area round the Zabranjeno je prisustvo osoba na području
building site where the armature is transmitted okolo gradilišta gdje se prenosi armature
is prohibited

During the rectification reinforcement is Tokom rektifikacije (korekcije) armature


prohibited to touch the device with rollers on zabranjeno je dodirivati uređaj sa valjcima na
the track for the stretch. stazi za rastezanje.

During tensile reinforcement on the track must Tokom armature u zategnutoj zoni zabranjeno
not be employees or other persons or objects je prisustvo zaposlenih ili drugih lica ili
or materials. predmeta ili materijala.

During installation and bonding reinforcement, Tokom instalacije i spajanja armature,


the employee must have a secure support and zaposleni mora imati siguran oslonac i siguran
a safe path for the movement during work. put za kretanje tokom rada.

A free end of the wire which is related fittings is Slobodan kraj žice koji je vezan za fitinge je

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
85
folds or folding of. Electric cables under omotan ili nabran. Električni kablovi pod
voltage must not be laid over the armature, or naponom ne smiju biti postavljeni iznad
placed so that they can come to contact with armature, ili postavljeni tako da mogu da dođu
reinforcement. u kontakt sa armaturom.

Reinforcement machines and electrical Evidencija na gradilištu se vodi o mašinama za


installations on the land and buildings where armaturu i električnim instalacijama na zemlji i
the preparation of reinforcement must be objektima, gdje se priprema armature mora
regularly inspected and maintained good redovno provjeravati i održavati u ispravnom
working order on what are kept records on stanju.
site.
Metalnim šipkama za izradu armature kao i
Metal rods for making reinforcement as well as gotove armature moraju se ispitati i prema
finished reinforcement have to be checked dimenzijama postaviti na gradilište tako da rad
and toward the dimensions placed on sa njima ne izaziva opasnost po zaposlene.
construction site so that work with them does
not cause danger to employees.
Ispravljanje, sječenje, savijanje i drugi rad na
Straightening, cutting, bending and other work
obradi armaturnih šipki mora se izvršiti
on the processing of reinforcement rods, must
posebno za tu izabranu lokaciju na gradilištu,
be performed, the particular, for that selected
sa odgovarajućim uređajima i alatima da bi se
location on construction site, with appropriate
preduzele odgovarajuće mere zaštite
devices, and tools to take appropriate
predviđene važećim propisima o zaštiti i
protective measures foreseen by the
zdravlju na radu pri obradi i radu sa metalom.
applicable regulations on safety and health at
work in the processing and metal working.

With the laying of the reinforcement can Sa polaganjem armature se može početi tek
commence until after the execution of nakon sprovođenja odgovarajućih zaštitnih
appropriate protective measures in the mjera iz propisa o zaštiti na radu u
regulations on work safety in construction. građevinarstvu.

WORK SAFETY MEASURES DURING MJERE ZAŠTITE PRI BETONIRANJU


CONCRETING

Concrete works are considered to be Betonski radovi obuhvataju prevoz, prenos na


transportation, transmission on facility and the objektu i ugradnju svježeg betona i njegu o
incorporation of fresh concrete, and concrete betonu tokom starenja u oplati.
care during aging in plating.

Before the start of concreting perform to Prije početka betoniranje vrši se priprema za
prepare for the safe operation of employees bezbedan rad zaposlenih i to:
and that is:

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
86
• At the edges over which there may be a • Na ivicama preko kojih može doći do
decline in area over 1m deep raises protective pada u oblast preko 1m dubine postavlja se
fence; zaštitna ograda;

• Above the reinforcement paths are placed • Iznad armature postavljaju se staze za
for the hand transmission or transport concrete ručni prenos ili transport betonske mase i
mass and movement of employees; kretanje zaposlenih;

• Working floors for receiving fresh • Radni podovi za prijem svježeg betona,
concrete when the vessels transferred by kada se spremnici prenose dizalicom, radni
crane, working floors for a throw weight in the podovi za ubacivanje u oplatu, staze za
plating, paths for the movement of employees kretanje zaposlenih i ugrađivanje i nivelisanje
and the embedding and leveling the surface of betonske površine, staza i radnih spratova, ne
concrete, paths and working floors, should not bi trebalo da se oslanjaju na armaturu, već
rely on reinforcement, but must have their own moraju da imaju svoj oslan postavljen na
reliance placed on the plating; oplati;

• Sharp peaks or edge of connecting and • oštri vrhovi ili ivica za povezivanje i drugi
other parts of the reinforcement are removed, djelovi armature se uklanjaju, pokrivaju ili
covered or folding; savijaju;

• Cleaning of formwork and reinforcement • čišćenje oplate i armature od


from dirt and debris with water orcompressed prljavštine i šuta sa vodom ili
air, performed so not to come to harm komprimovanim vazduhom se vrši tako da ne
employees or persons working near, due to dođe do povrede zaposlenih ili lica koja rade u
the impact of rejected particles or subject; blizini, zbog uticaja odbačenih djelića ili
predmeta;

• When concreted at night or when day light • Kod betoniranje noću ili kada dnevna
is not enough, raises the electric lights that svjetlost nije dovoljna, koriste se električna
should provide brightness of at least 250 lx, svjetla koja bi trebalo da obezbijede
where concrete is embedded, and a minimum osvjetljenje od najmanje 250 lx, tamo gdje
of 120 lx at the access and paths; se beton ugrađuje i minimum 120 lx na prilazu
i stazama;

• Electrical installation for embedding • Električne instalacije za ugradnju betona


concrete must have transmission voltage at moraju imati prenosni napon najviše 42 V i
most 42 V, and a portable lamp with its prenosnu lampu sa pokretnim kablovima do 24
movable cables up to 24 V. V.

• At construction of larger distance (halls, • Izgradnja većih dužina (hala,mostova,


bridges, etc.) are performed geodetic itd.) se izvodi geodetski

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
87
• observation of deflection, and behavior of • posmatranje ugiba (deformacija) i
scaffold structure in causing the load by ponašanje konstrukcije skele pri opterećenju

• embedding fresh concrete; • postavljanje svežeg betona;

• Concreting begins only on the orders of • Betoniranje počinje tek po nalogu


managers of works or the responsible rukovodioca radova ili odgovornog lica koje on
employee designated by him odredi

• At the concreting implemented are the • Pri betoniranju se sprovode sljedeće mere
following measures of safety and health at zaštite i zdravlja na radu:
work:

• Vessels for the transport of fresh concrete • Spremnici za prevoz svježeg betona
which is carries the crane must not be kranom ne smiju se prenositi iznad glava
transmitted over the heads of employees; zaposlenih;

• Acceptance of the courts with a concrete • Prihvatanje spremnika sa betonskom


mass which hanging on the hook of crane is masom koji vise na kuki dizalice se vrši
done by using safety ropes to guide, and when pomoću sigurnosnih konopaca za vođenje, a
operator of crane from his working place is not kada rukovaoc kranom sa svogradnog mjesta
able to follow the movement of loads, routing nije u stanju da prati kretanje tereta,
performed by a trained person – signalman. usmjeravanje vrši obučena osoba - signalista.

• Lowering to operating floor must be • Spuštanje do radnog poda mora se izvršiti


carried out without hitting and swinging, and bez udara i ljuljanja, a razdvajanje kuke krana
unbundling of a crane hook may occur only se vrši tek nakon što je spremnik u stabilnom
after the court is in a stable position; položaju;

• The court must not be overloaded with • Spremnik ne smije da bude pretovaren sa
concrete mass; betonskom masom;

• During embedding concrete mass by • Tokom ugrađivanja betonske mase


vibrator, employee must be firmly leaning, not pervibratorom, zaposleni se mora čvrsto
to lose balance when the needle of vibrator oslanjati da ne izgubi ravnotežu kada igla
plunges in the concrete mass; pervibratora uroni u betonsku masu

• When a fresh concrete mass delivers on • Kada se svježa betonska masa


the place of installation with concrete pump, it isporučuje na mjesto ugradnje sa
must always be control validity of continuation, betonskom pumpom, uvijek se mora
especially flexibility hose and pipelines, as well kontrolisati ispravnost nastavka, posebno
as connection flexibility hose for pipeline; fleksibilnog crijeva i cjevovoda, kao i poveznog
fleksibilnog crijeva za cjevovod;

• Flexible hose must not be harshly • Fleksibilno crijevo ne smije biti oštro
bandaged, neither when handling scrollable povezano, ni prilikom rukovanja namotanim
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
88
carrier pipelines, that may in return journey to prenosnim cijevima, jer može da se vrati i
reject an employee; udari zaposlenog;

• During concreting and washing, flexible • Prilikom betoniranja i pranja,


hose must not be directed at employees; fleksibilno crijevo ne smije biti
usmereno na zaposlene;

• When receiving concrete mass vehicle • Kada prima betonsku masu mješalica ne
mixer, must not discharged the weight from smije prazniti težinu iz bubnja dok se metalni
drum until a metal groove do not fixed and žlijeb ne fiksira i osigura od naglih pokreta;
ensure from the sudden movement;

• Before than approaches sprinkling built-in • Prije nego što se pristupi prskanju
concrete mass, remove the electrical ugrađene betonske mase, uklonite električnu
installation which was used during concreting; instalaciju koja je korištena tokom betoniranja;

• Violent stripping formwork from concrete • nasilno skidanje oplate od betonskih


surfaces by crane, is prohibited. površina dizalicom je zabranjeno.

• Disposal of materials and other means to • odlaganje materijala i drugih


work in places that are not designated for that sredstava za rad na mjesta koja nisu
is prohibited. Materials, which are disposed, za to predviđena je zabranjeno. Materijali
transferred and transported on pallets, stored koji se odlažu, prenose i prevoze na paletama,
on a specially prepared surface that is skladište se na specijalno pripremljenoj
horizontal, flat, and clean and has sufficient površini koja je horizontalna, ravna i čista i
solidity to avoid bending or subsidence under posjeduje dovoljnu čvrstinu da se izbegne
the weight of. savijanje ili slijeganja pod težinom.

• Storage of building materials on pallets is • Stovarište građevinskog materijala na


set to such a distance from the road and paletama je postavljeno na takvoj udaljenosti
passes that in the case of a demolition shall od puta i prolaza da u slučaju rušenja neće biti
not be endangered passers-by and traffic, and ugroženi prolaznici i saobraćaj i obezbijeđen je
ensuring the access of persons who do not pristup licima koja ne rade u skladištu.
work in warehouse.

• During lifting, transfer and transport of the • Tokom podizanja, prenosa i prevoza
freely of complex (are not insured baskets, slobodno složenih (nisu osigurani korpama,
frames, or otherwise) materials on pallets, okvirima, ili na drugi način) materijala na
employees who serve need to get away to a paletama, zaposleni koji rade treba da odu na
distance greater than the reach of the highest udaljenost veću od domašaja najvišeg
element in the event of overturning or falling elementa u slučaju prevrtanja ili pada sa visine
from heights and must be ensure that other i moraju osigurati da se druge osobe ne nalaze
persons are not found in the danger zone. u opasnoj zoni.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
89
• The substrate on which the employee is • Podloga po kojoj se zaposleni kreće da bi
moving to serve the stirrer should be adjusted se služio mješalicom mora biti podešena tako
so that the employee does not raise the da zaposleni ne diže prekomjeran teret na nivo
excess cargo on level of 1.2 m and the short od 1.2 m na udaljensotl najviše do 1.5 metara.
papers up to 1.5 meters at most. When Prilikom pripreme mehaničke mješavine,
preparing mechanical mixture (mortar) during (maltera) tokom rada bubnja mješalice
motion the drum mixer prohibited is: zabranjeno je:

• Hand pouring the mixture components • Ručno sipati sadržaj mješavine iz vreće,
from a bag, bucket and other vessel, directly kante i druge posude direktno u bubanj;
into the opening drum;

• Inserting objects into the hole and tools • Ubacivanje predmeta u otvor pomoću
kept by hand, cleaning and other works; alata, a ne rukom, čišćenje i drugi radovi;

• Hitting hard objects for parts mixers. • Udaranje tvrdim predmetima po djelovima
mješalice.

• When due to needs of working process • Kada je zbog potrebe posla potrebno
looked into drum necessarily used protective pogledati u bubanj, obavezno koristiti zaštitne
goggles. naočare.

• Turning on the agitator in electric drive, if • Uključivanje mješalice u električni pogon,


not implemented proper protection against ukoliko nije sprovedena odgovarajuća zaštita
electric shock - is forbidden od strujnog udara, je zabranjeno.

• Approaches and passes to all workplaces • prilazi i prolazi do svih radnih mjesta gdje
where is work performed must be derived so se obavlja rad moraju biti izvedeni tako da se
that through them can navigate employee, kroz njih mogu kretati radnici i vršiti prenos i
transferring and transporting materials. prevoz materijala.

• Leaving materials and other means to • Zabranjeno je ostavljanje materijala


work on approaches and places that are not i drugih sredstava za rad na
designed for it - is forbidden Stacking the prilazima i mjestima koja nisu namijenjena
materials by workplace can be done only in za to. Slaganje materijala na radnom mjestu
amounts that correspond to payload size and može se vršiti samo u količinama koje
available space. Height layer must match the odgovaraju korisnoj nosivosti i raspoloživom
type of material and must not exceed the prostoru. Visina sloja mora da odgovara vrsti
height that would threaten the stability of the materijala i ne smije preći visinu koja bi
material respectively caused the destruction of ugrozila stabilnost materijala, odnosno
complex materials and thus endanger izazvala rušenje kompleksnih materijala i na
employees. taj način ugrozila radnike.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
90
ASSEMBLY WORKS MONTERSKI RADOVI

Assembly construction can be executed only Montažno građenje smije se izvoditi samo na
based on a special programme. osnovu posebno izrađenog programa.

Programme has to contain measures of Program mora sadržati i mjere zaštite na radu
protection at work over all works which form pri svim radovima koji čine montažnu gradnju
part of an assembly construction (over works (pri izradi i opremanju pojedinih montažnih
and equipping of certain assembly parts, load dijelova, utovaru i istovaru montažnih
and discharging of assembly elements, lifting, elemenata, dizanju, namještanju i učvršćivanju
placement and firming of assembly elements, montažnih elemenata, obradi i doradi već
processing of the already implemented ugrađenih montažnih elemenata na objektu i
assembly elements on the structure etc.) drugo).

Assembly construction can be executed only Montažno građenje na gradilištu smije se


under constant supervising of determined izvoditi samo pod neposrednim nadzorom
expert on the site. određene stručne osobe na gradilištu.

Shape and dimensions of the assembly Oblik i dimenzije montažnih elemenata moraju
elements have to be adjusted for an easy and biti podešeni za lako i sigurno prenošenje do
safe transport to the place of implementation mjesta ugrađivanja i za sigurno pričvršćivanje
and for a safe attachment to the structure. na objektu. Prilikom prenosa nekvalitetno
Over transport of a non-quality or cracked or izrađenih kao i napuklih ili na drugi način
somehow damaged element, as well as over oštećenih montažnih elemenata, kao i prilikom
handling with such elements, special rukovanja takvim elementima, moraju se
measures of protection have to be undertaken. poduzeti posebne mjere zaštite na radu.

Assembly construction can be executed only Montažno građenje smije se izvoditi samo uz
with usage of corresponding and for this upotrebu odgovarajućih i za tu svrhu
purpose adjusted mechanized means of podešenih mehanizovanih transportnih
transportation, as well as of devices for lifting, sredstava, kao i uređaja za dizanje,
transport and placing of assembly elements. prenošenje i spuštanje montažnih elemenata.
Assembly and firming of the elements and Sastavljanje i pričvršćivanje montažnih
other assembly works on structures can be elemenata i druge montažne radove na
performed only by healthy persons for works objektu smiju vršiti samo osobe zdravstveno
on height, which are also trained for sposobne za rad na visinama, koje su uz to i
performance of the assembly works. stručno osposobljene za vršenje montažnih
radova.
Every assembly element has to be marked in a
visible way somehow in accordance with the Svaki montažni element mora biti na
programme of the assembly construction. odgovarajući način vidno i podesno obilježen u
Beside this mark, date of execution has to be skladu sa programom montažnog građenja.
put on the element as well as the weight Osim te oznake, na elementu mora biti

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
91
expressed in kilograms. Assembly elements označen i datum izrade i težina elemenata u
on the site have to be neatly placed according kilogramima. Montažni elementi na gradilištu
to the programme of works. moraju biti uredno i prema programu montaže
složeni na određenom mjestu.
Every assembly element has to, beside the
metal parts for implementation and firming to Svaki montažni element mora, osim metalnih
the structure, have auxiliary metal parts which dijelova za ugrađivanje i pričvršćivanje
enable safe transport and implementation of elemenata na objektu, imati pomoćne metalne
the elements on the place of implementation dijelove koji omogućavaju sigurno prenošenje i
(hook etc.). ugrađivanje elemenata na mjestu montaže
(kuku i slično).
Transport of the elements from place of their
production to the site i.e. from place of its Transport elemenata od mjesta njihove izrade
implementation has to be organized in such do gradilišta odnosno mjesta ugrađivanja
way that the assembly elements can be mora biti organizovan tako da se montažni
implemented into structure without stoppages elementi mogu bez zastoja ugrađivati u
and without cluttering of the site. objekat bez zatrpavanja gradilišta.

Loading, transport and discharge of the Utovar, prevoz i istovar montažnih elemenata
assembly elements on the site can be na gradilištu smije se vršiti samo
performed only with corresponding and correct odgovarajućim i ispravnim prevoznim
vehicles, with application of the protection sredstvima, uz primjenu zaštitnih mjera
measure prescribed with Rule book on propisanim Pravilnikom o zaštiti na radu pri
protection at work over load and discharge of utovaru i istovaru tereta («Sl.list SFRJ» br.
cargo («Off. Gazette of SFRJ» no. 17/66) 17/66)

Putting the cargo onto the hook and its Zakačivanje tereta za kuku i njihovo
discharging from the hook of the crane over otkačivanje sa kuke dizalice pri utovaru
loading the assembly elements into vehicles montažnih elemenata u prevozna sredstva
for transport (motor and other vehicles) and (motorna i druga vozila) i istovaru montažnih
discharging of assembly elements from the elemenata iz prevoznih sredstava, treba vršiti
vehicles for transport should be performed bez penjanja zaposlenog na prevozno
without climbing of the employee onto the sredstvo odnosno na elemente.
transport vehicle i.e. to the elements.

During discharge and lifting of the assembly Za vrijeme spuštanja i dizanja montažnih
elements onto the motor vehicle with help of elemenata na motorno vozilo pomoću dizalice,
the crane, the driver must not be in the cabin vozač ne smije biti u kabini vozila.
of the vehicle.

During the lifting, transport and discharge of Za vrijeme dizanja, prenošenja i spuštanja
the assembly elements onto the vehicle, montažnog elementa na vozilo, signalista ne
signalist must not stand on the vehicle. smije stajati na vozilu.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
92
Implementation of every individual element Ugrađivanje svakog pojedinog montažnog
into a construction structure must be elementa mora se vršiti po određenom redu,
performed according to a programme of prema programu montažnog građenja.
assembly construction.

Assembly of an element of the higher floor Montaža elemenata više etaže na objektu ne
cannot commence before ensuring the smije početi prije nego što se osigura prilaz na
approach to his floor (auxiliary pole with tu etažu (pomoćno stubište sa sigurnom
secure fence etc.) ogradom i slično).

Implementation of heavy assembly elements Ugrađivanje teških montažnih elemenata


(panels, beams etc.) can be performed only (ploča, grede i drugo) smije se vršiti samo po
when previously prepared the auxiliary means prethodnoj pripremi pomoćnih sredstava za
of transportation, placement and firming of prenošenje, postavljanje i učvršćivanje tih
those elements to the structure (transportation elemenata na objektu (jarmovi, okviri za
frames etc.). prenos i drugo).

Auxiliary means have to be checked before Pomoćna sredstva se moraju prije upotrebe
usage and examined to load. pregledati a po potrebi i ispitati na opterećenje.

Over transport, placement and firming of each Pri prenošenju, postavljanju i pričvršćivanju
individual assembly element onto a structure, svakog pojedinog montažnog elementa na
person who gives signs to the crane worker objekat, osoba koja daje znakove dizaličaru
(signalist) and crane worker have to monitor (signalista) i dizaličar moraju pažljivo pratiti put
very carefully the path of the assembly montažnog elementa do mjesta ugrađivanja
element to the place of its implementation, as kao i rad montera na postavljanju i
well as works of the assembly worker on učvršćivanju tog elementa. Monter mora javiti
placement and firming this element. Assembly posebnim znakom signalistu odnosno
worker has to announce with a special sign to dizaličaru da je operacija prenošenja i
the signalist i.e. to the crane worker that the ugrađivanja elementa u objekat završena.
operation of transportation and
implementation of the element into the
structure has been finished.

Parts of reinforcement which stick out of the Dijelove armature koji izlaze iz elemenata
elements after performed assembly and which nakon izvršene montaže i koji bi mogli
may cause clothes to stick and injure the prouzrokovati zapinjanje odjeće i ozleđivanje
employees have to be properly removed (with zaposlenih moraju se na podesan način
cutting, bending etc.) otkloniti (odsijecanjem, savijanjem i slično).

Openings in the floors and walls of the floors Ako se pri montaži elemenata koriste ljestve,
on which it is work have to be covered with one moraju odgovarati vrsti radova koja se
firm lids or fenced with protective fences. obavlja kao i biti osigurane od klizanja.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
93
Over execution of assembly works on the Pri izvođenju montažnih radova na objektu
structure where there is a possibility of falling, gdje postoji mogućnost pada zaposlenog,
the responsible person on the site should odgovorna osoba na gradilištu dužna je po
provide, when necessary, tying of the potrebi obezbijediti vezivanje zaposlenog
employee with protective belt and rope. If zaštitnim opasačem i užetom. Ako se spajanje
connecting the reinforcement and other metal armature i drugih metalnih dijelova montažnih
parts of the assembly elements is performed elemenata vrši pomoću plinskog ili električnog
with help of gas or electro welding, protective zavarivanja, primijenit će se zaštitne mjere
measures prescribed with technical measures propisane tehničkim mjerama za razvijače
shall apply for the acetylene developers and acetilena i acetilenske stanice kao i drugi
acetylene stations as well as other existing postojeći tehnički propisi.
technical regulations.

3.5.4 WORK SAFETY MEASURES 3.5.4 MJERE ZAŠTITE PRI RADU NA


FOR WORKING AT HEIGHT VISINI

Protection from fall from height is provided by Zaštita od pada sa visine se obezbjeđuje
construction of regulated working scaffolds, izgradnjom radnih skela, sa sigurnosnom
with safety fence and access entry - exit ogradom i prilaz merdevinama za ulaz - izlaz.
ladders.

During the scaffold montage workers must use Tokom montaže skele radnici moraju nositi
appropriate personal means of protection: odgovarajuća sredstva lične zaštite:

deep shoes with rubber soles, overalls, duboke cipele sa gumenim đonom,
protective gloves, and belt for work at height, kombinezone, zaštitne rukavice i pojas za rad
protective helmet. na visini, zaštitnu kacigu.

Work at height is considered to be the one Radom na visini smatra se rad koji radnik
which worker performs withrelying on supports obavlja oslanjajući se na potporu na visini od
on height of 3.0 m and more than a solid 3.0 m i više od čvrste podloge sa radnim
surface with a working space is not protected prostorom koji nije zaštićen od pada sa visine.
from falling from heights.

Solid surface is considered to be the surface Čvrstom podlogom se smatra površina sa


with deformations under load transferred to it deformacijama pod opterećenjem koje se
in small quantities process and are not prenosi u malim količinama i nije od značaja
significant for the stability of the structures or za stabilnost konstrukcija ili uređaja koje
devices supported by that surface podržava ta površina.

Workspace safe from the fall from heights is Radnim prostorom bezbjednim od pada sa
considered to be the space which visine smatra se prostor koji istovremeno ima:
simultaneously has:

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
94
1. safety fence according to regulations 1. sigurnosnu ogradu, u skladu sa propisima
mounted along the free edges of the scaffold montiranja, duž slobodnih ivica skele (ivica je
board (edge is separated more than 20 cm odvojena više od 20 cm od vertikalnog zida
from the vertical wall of the structure or similar konstrukcije ili slične prepreke koja u
obstacle which completely protects worker potpunosti štiti radnika od pada preko ivice u
from falling over the edge in surrounding area) okolinu)

2. Scaffold board constructed in accordance 2. Ploča skele je izgrađena u skladu sa


with regulations and drawing done based on propisima i crteži su urađeni na osnovu
structural analysis. That structural analysis strukturne analize. Ta strukturna analiza je
proved its stability and showed the connection pokazala svoju stabilnost i pokazala vezu
of the scaffold board and scaffold. između ploče skele i skele.

3. Scaffold on which is scaffold board with 3. skela gdje se nalazi ploča sa sigurnosnom
safety fence to be mounted, constructed In ogradom koja se montira je izgrađena u skladu
accordance with scaffold design. The sa projektom skele. Korišćenje skele se
utilization of the scaffold is approved by report odobrava izveštajem komisije koja vrši
of the committee, which performed the ispitivanje i prijem pre početka korišćenja.
inspection and reception before the start of the
utilization.

4. Access to the scaffold floors, on which the 4. Pristup spratovima skele, na kojima radnici
workers work, is provided by staircase rade, obezbeđuje se stepeništem izgrađenim
constructed in accordance with regulations u skladu sa propisima iz tačke 1) do 3 ). Za
from the clause 1) to 3). For smaller heights manje visine pristup se jednostavnije
the access is provided by simpler regulated obezbjeđuje (penjalicama sa zadnjom
accesses (step irons with back guard, skew stranom, kosim trajektnim rampama,
ferry ramps, staircases, etc.). Worker performs stepeništa, itd). Radnik obavlja rad na visini
work at height using the means of protection. koristeći sredstva zaštite.

Only experienced workers who, in their Samo iskusni radnici koji su u svom
previous work, starting from small to greater dosadašnjem radu, počevši od malih do većih
heights, gained the experience and checked visina, stekli iskustvo i proverjene lične
personal capabilities for executing these works sposobnosti za izvršavanje ovih radova mogu
can perform work at heights. da vrše rad na visinama.

Works at heights are executed based on Radovi na visini se izvode na


documentation and technology for execution osnovu dokumentacije i tehnologije za
with safety measures, which are provided by izvođenje sa mjerama zaštite, koje
the contractor. obezbjeđuje izvođač radova.

Working at height can be done only with the Rad na visini može se vršiti samo uz direktan i
direct and constant supervision of the stalan nadzor stručnog radnika kojeg imenuje

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
95
professional worker appointed by the manager rukovodilac za nadzor.
for supervision.

During the working at heights, the worker must Tokom rada na visinama, radnik mora da radi
do the following: sljedeće:

1. always have security belt tied above his 1. da uvijek ima sigurnosni pojas vezan iznad
head, if possible, to a place security of which glave, ako je moguće, na postavi zaštitu koju
he checks before stepping to the next support; proverava neposredno prije zakoračivanja na
sljedeći oslonac;

2. step onto a next support and rely on it only 2. zakorači na sljedeći oslonac i oslanj se na
after he has checked if it is safe; njega tek nakon što je proverio da li je
bezbedno;

3. Do not load his new temporary support with 3. Ne opterećuje svoj novi privremeni oslonac
additional cargo (material, tools, etc.) if he is sa dodatnim teretom (materijal, alata , itd.) ako
not sure that support can endure the additional nije siguran da oslonac može da izdrži
load. dodatno opterećenje.

4. do not use the temporary support 4. da ne koristi privremeni oslonac


simultaneously with other worker; istovremeno sa drugim radnikom;

5. Keep tools and other accessories 5. Drži alat i ostali pribor neophodan za
necessary for work execution at hand, on vršenje rada pri ruci, na mestima sa kojih neće
places from which they will not fall. Tools and pasti. Alati i pribor se mogu, ako je potrebno,
accessories could, if necessary, also be tied. takođe vezati.

6. Do not bend into unstable body balance 6. Ne smije se savijati u nestabilan položaj
position or unstable body balance with an ravnoteže ili nestabilnu ravnotežu sa
object holding in his hands or carrying on him. predmetom koji drži u rukama ili koji nosi na
sebi.

7. Perform untying of the safety belt rope from 7. Odvezuje sigurnosni pojas sa jednog mesta
one place and tying it on the other place in the i vezuje ga za drugo mjesto u položaj u kom se
position in which he is firmly supported on čvrsto oslanja na privremene i sigurne oslonce
temporary and safe supports or, in case he ili, u slučaju da ima još jedan konopac, kada je
has another rope, when he is tied with it to vezan s njim za siguran oslonac.
safe support.

8. Do not step above empty space and make 8. Ne zakoračuje iznad praznog prostora i ne
sudden moves. čini nagle pokrete.

9. Constantly keep an eye on the prefabricated 9. Stalno pazi na montažne elementa

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
96
element when approaching and keep him kada se približava i drži ih dalje od
away from the trajectory of the element. putanje elementa.

10. If it is not possible to perform an operation 10. Ako nije moguće izvršiti rad na način ili
in a way or in a sequence regulated by raspored regulisan projektom podizanja ili u
erection design or in agreement with assembly dogovoru sa menadžerom za montažu, radnik
manager, worker shall not continue with work neće nastaviti sa radom, već će zauzeti
but take a safe position and wait to receive sigurnu poziciju i sačekati da primi nove
new instructions from the responsible instrukcije od strane odgovornog radnika.
employee.
Radnik ne sme započeti rad, ili rad na
Worker must not commence the work, or work visinama, ako se oseća umorno, pospano, ako
at heights if he feels tired, sleepy, mentally ima psihičkih smetnji, ako je pod dejstvom
disordered, if he is under medication or he ljekova ili ako koristi sedative.
uses sedatives.
U dijelu gradilišta gdje se vrši
In the construction site part where mounting montaža i demontiranje, sve druge
and demounting is performed, all other aktivnosti se zaustavljaju kao što je
activities stop as the circulation of motor cirkulisanje motornih vozila i radnika.
vehicles and workers.

3.5.5 SPECIAL PROTECTIVE 3.5.5 POSEBNE MJERE ZAŠTITE PRI


MEASURES DURING BLASTING MINIRANJU

(1)During execution of blasting works following (1)Prilikom izvođenja minerskih radova moraju
measures of health and safety at work defined se ispoštovati i sledeće mjere zaštite
by relevant laws, regulations and standards definisane odgovarajućim zakonima,
must be respected: propisima i standardima:

-For organization of the work with explosive -Za organizaciju rada sa eksplozivnim
materials and organization of the expert sredstvima i organizovanje stručne kontrole
control of that work Manager of the drilling and toga rada odgovoran je rukovodilac radova na
blasting works is responsible. bušenju i miniranju.

-For conduction of the works related to -Za sprovođenje rada u vezi rukovanja sa
handling with explosives and blasting material eksplozivom i sredstvima za miniranje
Manager of the drilling and blasting works is odgovoran je rukovodilac radova na bušenju i
responsible. miniranju.

-For organization and conduction of the health -Za organizovanje i kontrolu sprovođenja
and safety at work with explosives and zaštitnih mjera pri radu sa eksplozivom i
blasting materials manager of the drilling and eksplozivnim sredstvima odgovoran je
blasting works is responsible. rukovodilac radova na bušenju i miniranju.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
97
-For the execution of protective measures -Za izvršavanje zaštitnih mjera pri radu sa
during work with explosives and blasting eksplozivom i eksplozivnim sredstvima
materials responsible is blaster. odgovoran je palioc mina.

-To supervise the implementation of -Za vršenje nadzora nad sprovođenjem


regulations related to explosives and blasting propisa koji se odnose na eksplozivna
Manager of the drilling and blasting works is sredstva i miniranje odgovoran je rukovodilac
responsible. radova na bušenju i miniranju.

- The Manager of the drilling and blasting -Rukovodilac radova na bušenju i miniranju
works is obliged to issue instructions for dužan je da izda uputstva za primanje,
receiving, transporting, placing, storing, transportovanje, smještanje, čuvanje,
issuing, usage and destruction of explosives to izdavanje, upotrebu i uništavanje eksplozivnih
persons working and handling with those sredstava licima koja rade i rukuju i sa tim
funds by his signature, and those persons sredstvima uz potpis, a koja su svojim
should by their signature acknowledge receipt potpisom dužna da potvrde prijem ovih
of the instructions. uputstava.

- Works on blasting are done by blasters, -Poslove miniranja vrše palioci mina,
which are trained to independently carry out osposobljeni za samostalno vršenje poslova
mining operations. These persons once during miniranja. Ova lica jednom u toku godine idu
a year have to go to medical examinations, na kontrolni ljekarski preged, a posle
and after 55 years old 2 times a year in order 55.godine starosti 2 puta godišnje u cilju
to determine whether they are physically and utvrđivanja da li su fizički i duševno zdravi i
mentally healthy and capable of performing sposobni za vršenje poslova miniranja.
blasting works.

- If the new types of explosives are introduce -Ako se uvodi nova vrsta eksploziva ili se
in works or the procedure of blasting is mijenja način miniranja, palioci mina se moraju
changed, blasters must be trained for usage of obučiti za upotrebu novog sredstva ili načina
new materials or the way of usage and get upotrebe i dobiti saglasnost Projektanta.
consent from designer.

- During works with explosive materials, and -Pri radu sa eksplozivnim sredstvima, a
especially with explosive lighters, clothing of naročito sa eksolozivnim upaljačima, odjeća
the staff shall not be made of materials which osoblja ne smije da bude od materije koja
are causing static electricity (Nylon, xylon, prouzrokuje statički elektricitet (najlon, ksilon,
synthetics, etc.). sintetika i sl.).

-Blasters must not do the blasting works by the -Palioci mina ne smiju vršiti poslove miniranja
norm. po normi.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
98
-During blasting works and work with explosive -Pri poslovima miniranja i rada sa
materials, as help can be used qualified eksplozivnim sredstvima, kao pomoć se mogu
workers who are trained in this type of works, koristiti kvalifikovani radnici koji su obučeni u
and have work at least one year in the plant tim poslovima, a radili su najmanje jednu
with smaller or greater dangerousness. They godinu u pogonu sa istom ili većom
may not equip firing cartridges and connect opasnošću. Oni ne smiju opremati udarne
them with the initiators of explosion, or perform patrone i spajati ih sa inicijatorima eksplozija,
mines detonating by usage of machines. niti pomoću mašine vršiti paljenje mina.

- Usage of explosive materials which are not -Zabranjena je upotreba eksplozivnih


reported to the relevant institution of sredstava koja nisu prijavljena nadležnom
Municipality Safety Centre on which territory organu CB Skupštine opštine na čijom se
works are performed is forbidden. teritoriji izvode radovi.

(2)Transportation and security of explosive (2)Transport i obezbjeđenje eksplozivnog


material from the producer to the user can be materijala od proizvođača do preduzeća može
done by the producer, and if it is done by the da vrši i proizvođač eksplozivnih sredstava, a
contractor of the works, following conditions ukoliko to vrši izvođač radova, moraju se
must be fulfilled: ispuniti sledeći uslovi:

-To get consent from the competent Safety -Da se dobije odobrenje od nadležnog CB-i,
Centre.

-To provide accompaniment of the explosive -Da se od nadležnog CB-i obezbjedi pratnja
materials from the competent Safety Centre. eksplozivnog materijala,

-To provide technically checked and good -Da se obezbijedi tehnički ispravno vozilo sa
vehicle with two drivers, dva vozača,

-To equip vehicle with tarpaulin, two fire -Da vozilo posjeduje ciradu, dva aparata za
extinguishers, two labels that indicate the gašenje požara, dvije oznake koje označavaju
transfer of explosive materials, hack, shovel prenos eksplozivnog materijala, pijuk, lopatu i
and a box with sand, sanduk sa pijeskom,

-To ensure that speed during transport does -Da brzina pri prevozu ne prelazi 50 km/h,
not exceed 50 km / h,

-To fill vehicles with explosive material up to -Da je punjenje vozila sa eksplozivnim
60% of the maximum capacity of the vehicle, materijalom do 60 % maksimalne nosivosti
and at least 20 cm below the site vehicles, vozila, odnosno najmanje 20 cm ispod stranica

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
99
vozila,

-To be aware that it retention and leave the -Da je najstrože zabranjeno zadržavanje i
vehicles transporting explosive materials in ostavljanje vozila koje prevozi eksplozivna
populated areas is strictly forbidden, sredstva u naseljenim mjestima,

-That during transportation of explosive -Da se pri prevozu eksplozivnih sredstava ne


materials is not allowed to receive and drive smiju primati i prevoziti druga lica,
other persons,

-That driver and co-driver who are carrying -Da vozač i suvozač koji prevoze eksplozivna
explosive materials must be familiar with sredstva moraju poznavati mjere zaštite pri
safety measures when loading, transporting utovaru, prevozu i istovaru eksplozivnih
and unloading explosives. sredstava.

- That during loading and transfer of -Pri utovaru i uopšte prenosu eksplozivnih
explosives and initiators of the explosion at the sredstava i inicijatora eksplozije na radilište,
site in general, following safety measures must moraju se poštovati sledeće mjere zaštite na
be observed: radu:

-By receipt of explosive materials blasters and -Primajući eksplozivna sredstva palioci mina i
their assistants (skilled workers) should go njihovi pomoćnici (obučeni radnici) moraju ići
directly to the place of explosives transfer direktno na mjesto prenosa eksplozivnih
without retention and communication with sredstava bez zadržavanja i komunikacije sa
groups of people. grupama ljudi.

-Transfer of explosives shall be carried out in -Prenos eksplozivnih sredstava vrši se na


places where the number of workers is mjestima gdje je prisutan najmanji broj
smallest, and those workers during passing by radnika, a ti radnici pri prolazu pored njih,
of explosive have to stop work until explosives moraju prekinuti posao dok se ne prenesu
are transferred and eksplozivna sredstva i

-During the transfer of explosives, the distance -pri prenosu eksplozivnih sredstava,
between individuals shall be at least 10 m. udaljenost između pojedinaca je najmanje 10
m.

(3)On the individual transportation of explosive (3)Na pojedinačnom prenosu eksplozivnih


materials and explosion initiators, from the sredstava i inicijatora eksplozije, bilo sa vozila
vehicle to outside magazine or from outside u spoljni magacin ili iz spoljnjeg magacina na
magazine to construction site, following health radilište, moraju se primijeniti sledeće mjere
and safety measures must be implemented: zaštite:

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
100
-One worker can transfer up to 1000 pieces of - Jedan radnik smije prenositi do 1000 kom.
blasting primers or 500 pieces of electrical kapisli ili 500 kom. električnih upaljača u
lighters in original boxes, or in wrapper placed originalnim kutijama, odnosno u omotima
in the boxes in which blasting primers and smještenim u sanduke u kojima se kapisle i
electrical lighters shall not overlap. upaljači ne mogu preklapati,

-If more workers transfer primers and lighters - Ako više radnika istovremeno prenosi kapisle
at the same time, those workers has to be on ili upaljače, ti radnici moraju ići jedan za
distance of 10 m between each other , and to drugim na međusobnom rastojanju od 10 m,
carry material in special bags or boxes in nose se u specijalnim torbama ili kutijama u
which initiators are prevented from any kojima je onemogućeno kretanje pojedinačnih
movements. -During transport of single inicijatora.pri prenosu kapisli u originalnom
primers in original packages bigger than 100 pakovanju većem od 1000 komada (sanduk od
pieces (5000 piece box), those box has to be 5000 kom.), takav sanduk moraju prenositi 2
carried by 2 workers, holding it for the special radnika držeći ga za posebne ručice, na
handles on the distance at least 20 meters. odstojanju od najmanje 20 m.

-One person can carry most 30 kg of explosive -Jedno lice smije prenositi do 30 kg
and initiators, in original packages, and if that eksploziva, i to u originalnim pakovanjima, a
package is bigger the 30 kg, it must be carried ako je originalno pakovanje veće od 30 kg,
out by 2 persons. onda to pakovanje nose 2 lica.

-Quantities under original explosive package -Količine ispod originalnog pakovanja


shall be carried in bags, closed boxes, or eksploziva, nose se u torbama, zatvorenim
crates. kutijama ili sanducima.

In the case of the carrying explosive and U slučaju istovremenog nošenja eksploziva i
explosion initiators at the same time, blaster inicijatora ekspplozije, palioc mina može nositi
can carry most 10 kg of explosive and most 40 najviše 10 kg eksploziva, i najviše 40 komada
blasting initiators, in the special boxes and inicijatora eksploziva, i to u zasebnim torbama
bags which are separated one from each ili kutijama, koje su odvojene jedne od drugih
other.

Blasting initiators should be carried out only by Inicijatore eksplozije nosi samo palioc mina.
blaster.

(4)During preparation of the firing cartridges, (4)Prilikom pripreme udarne patrone, punjenja
filling the mine borehole and mines detonation, minske bušotine i paljenja mina, moraju se
following measures must be carried out: sprovoditi i sledeće mjere:

-Preparation of firing cartridge must be done -Pripremanje udarne patrone vrši se

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
101
directly on the site, but only after removal of neposredno na radilištu, ali tek posle
workers and mechanization. The recess in the povlačenja radnika i mehanizacije. Udubljenje
firing cartridge where there comes the trigger u udarnu patronu gdje dolazi kapisla ili
or electric lighter shall be performed using električni upaljač vrši pomoću šiljka koji ne
non-sparking tip. During carrying out of these varniči. Pri izvođenju ovih radova zabranjeno
works smoking is forbidden , je pušenje,

-Before filling blasting boreholes on all -Prije punjenja minskih bušotina na svim
approaches to the location must be set guard prilazima moraju se postaviti straže koje
to prevent access around the mining, onemogućuju prilaz oko mjesta miniranja,

-Firing cartridge must not be pressed before -Udarna patrona prije stavljanja u bušotinu ne
placing in the borehole. Filling the hole with smije se pritiskati. Punjenje bušotine
explosives shall be set out in the order eksplozivom vrši se utvrđenim redosledom
envisaged by the project and construction of predviđenim po projektu i konstrukciji minskog
the mine filling, by carefully placing of each punjenja, uz pažljivo spuštanje svake patrone
cartridge separately, zasebno,

-Each blasting borehole has designed length -Svaka minska bušotina ima projektovanu
of the bung which is filled by inflammable dužinu čepa koji se puni nezapaljivim sipkim
material or loam, clay, or drilled material, materijalom ili ilovačom, glinom, ili nabušenim
materijalom,

-Bringing of ignition - fire needed for -Dovođenje paljenja – vatre potrebne za


detonating mines shall be carried out by: paljenje mina izvodi se preko: Nonel
Nonel system, slow-burning fuse, detonator sistema,sporogorećeg štapina, kapisle br.8 ili
No.8 or electric detonators, which are električnih upaljača koji se aktiviraju preko
activated by electric machines for mines električnih mašina za paljenje mina.
detonation.

(5)While activating of the mines with the (5)Pri paljenju mina sporogorećim štapinom
slow-burning fuse following safety measures moraju se primjenjivati sledeće mjere:
shall be applied:

- The shortest fuse shall be 1m. - Najkraći štapin je 1m,

- Every next fuse is 10 cm longer than the - Svaki naredni štapin je duži 10 cm od
previous one. prethodnog,

- It can be burned mostly 5 blasting - Najviše se smije paliti 5 minskih bušotina


boreholes at the same time, in which case the u isto vrijeme, u kom slučaju najduži štapin

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
102
longest fuse is 1.40m. iznosi 1.40m.

- In special cases it is allowed to the blaster - Izuzetno se odobrava paljenje jednom


to burn 6 mines in the case that the shortest paliocu 6 mina pod uslovom da je najkraći
fuse is 1.30 and the longest is 1.80 m. štapin 1.30 m dužine, odnosno 1.80 m najduži
štapin,

- Burning of the fuse shall be done by - Paljenje štapina se izvodi minerskom


blasting matches or by the fuse. šibicom ili štapinom.

- During burning of the fuses first should be - Pri paljenju štapina uvijek se pali najduži
the longest fuse, and the shortest is last one. štapin prvi, a najkraći poslednji,

- During burning of the fuse, if blasted does - Za vrijeme paljenja štapina, ako palioc
not have blasting match he has to have spare mina nema minersku šibicu mora imati
fuse in his hands which signalize to him time rezervni štapin u ruci koju mu signalizira
when he has to leave the site, and this fuse is vrijeme povlačenje sa radilišta, pri čemu je
0.7 m long. ovaj štapin dugačak 0.7 m,

- Burning of the slow-burning fuse blaster - Paljenje sporogorećeg štapina palioc ne


cannot do by alone, or without presence of the smije vršiti sam, odnosno bez prisustva
Site Manager or the person trained for work rukovodioca radilišta ili lica obučenog za rad
with explosive materials from the reason of the sa eksplozivnim sredstvima iz razloga lične
personal safety (possible loose of bezbjednosti (eventualne nesvjestice i sl.),
consciousness, etc.)

- In the case of the need for burning bigger - U slučaju potrebe paljenja većeg broja
number of blasting boreholes with minskih bušotina sporogorećim štapinom od 5
slow-burning fuse then 5 or 6 pieces, it is odnosno 6 komada, obavezna je primjena
obligatory to use blasting capsule or minerske čaure ili saća.
“honeycomb”

(6)While activating of the mines with the (6)Pri paljenju mina detonirajućim štapinom
detonating fuse following safety measures primjenjuju se sledeće mjere zaštite:
shall be applied:

Detonating fuse is explosive which is very Detonirajući štapin je eksplozivan i jako


sensitive for impact and friction, so it must be osjetljiv na udar i trenje, te se mora odrezati na
cut on the pieces of the preferred length komade potrebne dužine prije nego će se
before it is putted in explosive cartridge, staviti u patronu eksploziva,

Detonating fuse shall be cut by slow Detonirajući štapin reže se laganim kretanjem
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
103
movements of cleaned sharp knife on the čistog oštrog noža na čistoj drvenoj podlozi
clean wooden surface with one move in one jednim potezom u jednom smjeru,
direction.

After every cut from the knife and surface Poslije svakog rezanja moraju se sa noža i
leftovers from the fuse must be cleaned. podloge dobro očistiti ostaci od štapina.

The person who performs cutting must turn his Lice koje reže detonirajući štapin mora kalemu
back to the spool. okrenuti leđa,

In the net of detonative fuses it is forbidden to U mreži detonirajućih štapina zabranjeno je


use detonative fuses from different produces upotrebljivati detonirajuće štapine raznih vrsta
and different sizes. Burning of detonative i različitih proizvođača. Paljenje detonirajućeg
fuses is done by blasting primer No.8. štapina se izvodi rudarskom kapislom br.8,

Primer cannot be brought in the area of Kapisla ne smije biti donijeta u područje
blasting, neither placed on the main line of miniranja, niti postavljena na glavni vod
detonative fuse until everything is not detonirajućeg štapina dok nije sve
prepared for the blasting. pripremljeno za paljenje,

During transport of the detonative fuse free Pri prenosu detonirajućeg štapina slobodni
end must be isolated. kraj mora biti izolovan.

(7)Electrically mines are burned through serial, (7)Električnim putem mine se pale preko
parallel or combination connection methods serijskog, paralelnog ili kombinovanog načina
and following precautionary measures shall be povezivanja, a moraju se primjeniti sledeće
applied: mjere zaštite:

Each machine for detonating mines must have Svaka mašina za paljenje mina mora imati
a board on which must be written the value of tabelu na kojoj mora biti ispisana vrijednost
resistance expressed in ohms, otpora izražena u omima,

At least once a month the accuracy of Najmanje jedan put mjesečno provjeravaju se
machines for detonating mines and electrical na ispravnost mašine za paljenje mina i
measuring devices in the workshop must be električni mjerni uređaji u radionici, a ovi se
checked, and this is written in the book of nalazi upisuju u knjigu eksplozivnih sredstava,
explosives,

At least once a year electrical appliances for Najmanje jedanput godišnje električni uređaji
detonating mines are tested by an institution or za paljenje mina se ispituju od strane ustanove
organization specialized in this business, ili organizacije specijalizovane za ovaj posao,

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
104
Electrical line for activation of mines shall be Električni vod za paljenje mina treba da bude
made of copper with section area at least 0.8 od bakra presjeka najmanje 0.8 mm2 sa
mm2 with rubber or PVC isolation. izolacijom od gume ili PVC-a.

During connection of electrical detonators one Pri vezivanju električnih upaljača jednih za
to each other, as well as for detonation line, druge, kao i za vod za paljenje, krajevi se
ends must be cleared well. moraju dobro očistiti,

Connection to the main line cannot be done Vezivanje za glavni dovodni vod ne smije se
until all detonators are not connected among vršiti dok svi upaljači između sebe nisu
themselves povezani,

During laying main supply cable for ignition, Pri razvlačenju glavnog dovodnog voda za
end of the line which is connected on the place paljenje, kraj voda koji se vezuje na mjestima
for mines activation must be shortly za paljenje mina mora biti kratko spojen,
connected.

Machine for mines detonation is carried by Mašina za paljenje mina nalazi se kod palioca
blaster ,and if there is a key, then key is also mina, a ako ima ključ, onda je ključ kod palioca
by blaster, in order to exclude the possibility mina, čime se isključuje mogućnost da
that an unauthorized person could cause neovlašćeno lice može izazvati opaljenje,
accidental firing,

Power line of signalization, lighting should not Električni vodovi signalizacije, osvjetljenja ne
be used as lines for detonating mines. smiju se koristiti kao vodovi za paljenje mina,

Lines for mines detonation are placed on the Vodovi za paljenje mina postavljaju se na
side where are no any electrical lines, pile strani gdje nema električnih vodova,
lines or steel bars cjevovoda, čeličnih užadi i sl.

During connection of the lines on machine for Prije povezivanja vodova za paljenje mina na
mines detonation, end which was shortly mašinu za paljenje, kraj koji je bio kratko
connected should be connected to OM-meter, spojen treba povezati za OM-metar, te ako je
and in case of getting adequate resistance , dobijen odgovarajući otpor, onda se isti
connect the same to the activation machine, povezuje za mašinu za paljenje, a ako nije
and if not find the place of connection treba pronaći mjesto prekida veze,
breakage.

During activation of the burning machine, Pri opaljenju mašinom za paljenje, mašina za
machine for burning must be placed on the paljenje mora se postaviti na drvo, koljeno ili
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
105
wood, knee, or any surface with the goal of drugu podlogu u cilju spriječavanja da mašina
preventing that machine came in touch with za paljenja mina dođe u dodir sa eventualnim
any potentially stray currents. lutajućim strujama,

Temporarily checking of stray currents Povremeno vršiti provjeru provodnika od


conductor shall be done. lutajućih struja,

When construction site is totally prevented, Kada je radilište potpuno obezbijeđeno, ljudi i
people and mechanization removed, guard mehanizacija povučeni, postavljene straže,
placed, tables posted and the others, blasting istaknute table i dr. pristupa se miniranju sa
can be started with the shouting: “FIRE!”, and uzvikom "Vatra !“, a kad je isto obavljeno
when blaster has done his work he claim it palioc objavljuje da je miniranje završeno
with the word “FINISHED!” riječima "Gotovo !“,

After mine blasting it must be waited at least Poslije otpucavanja mina mora se najmanje
30 minutes, and only after it is noticeable that sačekati 30 minuta, pa pošto se vidi da je
site is freed from the gasses, only that go on radilište oslobođeno gasova, tek onda otići na
the site in the following order: on the site radilište i to sledećim redoslijedom: na
comes the blaster and his assistant, check the otpucano radilište dolazi palioc mina i njegov
site, and after confirming that everything is in pomoćnik, pregledaju radilište, te
order they invite work groups to continue with konstatacijom da je sve u redu pozivaju radne
regular work conduct. grupe na normalno vršenje poslova,

In the case it is noted that some of the mines Ukoliko se konstatuje da neka mina nije
did not blast, removal of it is done right away otpucala, pristupa se njenom otklanjanju
by making new borehole 30 cm left or right bušenjem nove bušotine na 30 cm lijevo ili
from the leftover mine and making evident ion. desno od zaostale mine i vođenjem
After removal of leftover mine work groups are evidencije.Po otklanjanju zatajale mine
invited to continue with regular works.In the pozivaju se radne grupe da nastave normalan
case some explosive, primers or detonators rad, Ukoliko se naidje na eksploziv ili kapisle i
which explosion throw away or have not upaljače koje je eksplozija izbacila ili nijesu
exploded for some reasons are founded, it eksplodirali iz nepoznatih razloga,mora se
must be done as noted in previous paragraph. postupiti kao što je gore navedeno.

(8)During blasting on the surface there must (8)Pri miniranju na površini moraju se
be applied following measures: primjeniti sledeće mjere zaštite:

- Emphasize the boards about time of blasting -istaći table o vremenu miniranja i znacima
and blasting signs-signals, miniranja-signali,

- if the blasting is performed beside public -ukoliko se miniranje izvodi pored javnih
roads and other roads, in another sound of puteva ili drugih puteva,na drugi znak sirene
Design of Bridge for Main Design
Bar – Boljare Highway, section Smokovac – Mateševo
106
siren traffic must be stopped, from guards that se zaustavlja saobraćaj,od straža koje su
have been sent to take care and who handle unaprijed poslate na obezbedjenje i koje imaju
warning flags, u rukama zastavice upozorenja,

- if the mining is done under the power line -ako se miniranje vrši ispod el. voda koji je pod
which is under voltage before any work it is naponom,prije bilo kakvih radova traži se
necessary get approval to turn off the line by saglasnost za isključenje voda od vlasnika i
the owners and shall be dealt according to his postupa se po njegovim zahtjevima,
requirements,

-if the mining is done right near the railway line -ukoliko se miniranje vrši neposredno u blizini
or there is a danger of flying pieces of the rail željezničke pruge ili postoji opasnost da dodje
line, permits and approves for blasting like the do razlijetanja komada na željezničku
time is determined directly by the competent prugu,saglasnost i dozvolu miniranja kao i
authority of the railways, vrijeme odredjuje neposredno nadležni organ
željeznice,

- if blasting is performed in a populated area it -ukoliko se miniranje izvodi u naseljenom


is necessary to report the competent authority mjestu izvještava se organ nadležnog centra
of the Security Centre, which determines bezbjednosti koji odredjuje zaštitne mjere pri
safety measures during blasting to protect miniranju radi zaštite naselja,
settlements,

- If the affected area is not otherwise provided, -ako ugroženo područje nije odredjeno
the responsible manager determines drugačije,odgovorni rukovodilac radilišta
protective measures during blasting in local odredjuje zaštitne mjere pri miniranju u
conditions, mjesnim uslovima,

- During blasting on surface must always be -pri miniranju na površini moraju se uvijek
set up guards and workers must stay on safe postaviti straže, a radnici skloniti na sigurna i
and in particular places. za to odredjena mjesta.

(9)During using explosives it must exist diary (9)Kod upotrebe eksplozivnih sredstava vodi
book for blasting. This diary is filled by the se i čuva dnevnik miniranja.Ovaj dnevnik
Blasting manager, and includes: popunjava rukovodilac miniranja, i sadrži:

- drawing of a minefield on the layout plan, -skicu minskog polja na situacionom planu,

- quantity of explosives in the borehole and the -količine eksploziva po bušotini i ukupne
total quantity of explosives, količine eksploziva,

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
107
- way of initiating and connection scheme, -način iniciranja i šema veze,

-weather conditions of blasting (dry, sunny, -vremenske uslove miniranja


cloudy, rainy weather and etc.) (suvo,sunčano,oblačno,kišovito vrijeme i sl.),

- an overview of the site and its look after -pregled radilišta i njegov izgled poslije
blasting, miniranja,

-important observations, -važnija zapažanja,

- signature of the person who committed and -potpis lica koje je izvršilo i rukovodilo
guided blasting. miniranjem.

This diary is a document of permanent value Ovaj dnevnik je dokument trajne vrijednosti i
and as such must be permanently stored. kao takav mora se trajno čuvati.

(10)Conclusion: (10)Zaključak:

During blasting staff, equipment and Za vrijeme miniranja će se povući


machinery will be withdrawed in accordance zaposleni,oprema i mehanizacija u skladu sa
with the calculation of the safety distance, proračunom sigurnosnih rastojanja, uz
respecting the laws of fire protection. It will be poštovanje zakona protivpožarne
organized guards at all access roads and the zaštite.Organizovat će se straža na svim
blsting during blasting. prilaznim putevima i mjestu miniranja u
trajanju miniranja.

Previously,for all actions will be obtained a Prethodno svim radnjama bit će pribavljena
permit for carrying out mining of Department dozvola za izvodjenje miniranja od CB Sektora
for Emergency Situations. za Vanredne Situacije.

Design of Bridge for Main Design


Bar – Boljare Highway, section Smokovac – Mateševo
108