You are on page 1of 8

Unbalanced forces develop in pipelines and occur at

elbows, tees, wyes, reducers, valves, and dead ends.


Unbalanced thrust forces that exist in pressure piping
systems must have adequate physical restraint in the
form of reactive forces for stabilizing the system.
Reactive forces can be provided by (1) introducing
external forces, such as blockings, (2) transmitting
forces to the pipe wall by restrained, harnessed,
flanged, or welded joints, and (3) by an interaction of
physical external forces and partial transmission of
forces to the pipe wall, such as in the case of buried
pipe with tied joints or a combination of tied joints and
blocks. The first method applies to piping systems,
either buried or exposed; the second covers only
exposed pipe installations; and the third is pertinent
only to buried piping systems.
An adequate restraint must limit and control move
Practical ment of the pipe segments within allowable limits,
thereby ensuring water tightness of joints and the
integrity of the entire piping system. For pump-station
Applications piping, particularly pump stations with large-size pipe,
control of movement is crucial to prevent structural or
mechanical failures, such as cracking of valve castings
for Design of and pipe and pump-shaft misalignments.
Theoretical Analysis
Thrust Blocks Thrust forces in a pipe occur whenever the direction
or velocity of the confined water changes. Forces are
and Tied Joints developed from internal static pressure and dynamic
action of water contained in the system. In most cases
dynamic forces are relatively small in comparison with
static forces resulting from internal pressure. However,
George E. Neher and Y. T. Lin for large diameter pipe operating under low head, high
velocity conditions, the velocity head should be given
Piping systems are prone to forces that must somehow due consideration in design.
be absorbed and balanced if they are to retain their The magnitude of the hydraulic forces generated in
integrity. Various factors contributing to pipe movement closed circuits is governed by (1) pipe size, (2) angle of
are examined and countermeasures explained. deflection, (3) operating pressure and velocity head, (4)
MARCH 1978 0003-150X/78/0300-0131 $01.00 G. E. NEHER & Y. T. LIN 131
1978 American Water Works Association
2000

+ — AV2
9

500
400
300
R = Resultant Force 200
F = Thrust
100
A = Cross Sectional Area of Pipe
Tee and Plug R = F
W = Weight of Water
Tied Joints g = Gravitational Acceleration 12 16 20 24 30 36 42 48
Bend: FT = F cos I) h = Pressure Head
Pipe Diameter in.
T = F - Fi P = Pressure
T = Restraining Force Required for Tied Joints
= F-1-cos II
V = Velocity Fig. 2 . Thrust Blocking Design Criteria for Various Pipe Bends
Tee and Plug T = F
Internal pressure 0.69 MPa (100 psi): allowable soil-bearing pres
Fig. 1. Hydraulic Force Diagram for Pressure Conduit sure, 96 kPa (2 kip/sq ft)

TABLE 1
Requirements for Thrust Blocks or Tied Joints*

Blocking
Tied Lengthf
Length Height each way
Pipe Size
Bend Type in. m ft m ft m ft

90deg 12 1.0 4 0.60 2 15.5 51


16 2.0 7 0.60 2 18.0 60
20 2.0 7.5 0.9 3 22.0 72
24 3.5 11 0.9 3 25.5 84
30 4.0 12.5 1.0 4 31.0 102
36 4.5 15 1.5 5 34.5 113
Tee and plug 12 1.0 3 0.6 2 15.5 51
16 1.5 5 .6 2 18.5 60
20 1.5 5.5 0.9 3 22.0 72
24 2.0 7.5 0.9 3 25.5 84
30 3.0 9 1.0 4 31.0 102
'Note,: Mate all hori$. brnd$ ia
36 3.5 11.5 1.5 4.5 36.5 119 sing cofiiinationaf ffa deflection
60 deg 12 1.0 3 0.6 2 7.6 25 angles one/ thrust blocks shoHfi in
Schedule above.
16 1.5 5 0.6 2 9.1 30 Use counter ~*yht crs skw
20 1.5 5.5 0.9 3 11.0 36 a* -fop of !{ verticaltends afar
5'ond use blocking epnaf to
24 2.5 7.5 0.9 3 13.0 42
30 2.5 9 1.0 4 15.5 51
LT a.-fcW. floriy.bcrid kfocking af&ottein
of all vertical bends.

36 3.5 11.5 1.5 4.5 18.0 59


45 deg or wye 12 1.0 3 0.5 1.5 4.6 15
16 1.0 4 0.6 2 5.5 18
20 1.0 4 0.9 3 6.4 21 EL ZVATtON EL EV4 T1ON'.
24 2.0 6 0.9 3 7.6 25 TEE OR PLUG BENDS
30 2.0 7 1.0 4 9.1 30 TEE & BEND BLOCKING IN SOfL
36 3.0 10 1.0 4 10.7 35
30deg 12 0.6 2 0.5 1.5 2.1 7
16 0.8 2.5 0.6 2 2.4 8
20 1.0 3.5 0.8 25 3.0 10
24 1.0 4 0.9 3 3.4 11
30 1.5 5.5 1.0 3.5 4.3 14
36 2.0 6.5 1.0 4 4.9 16
22K deg 12 0.6 2 0.3 1 1.2 4
16 0.8 2.5 0.5 1.5 1.5 5 ELEVATION SECTION
20 0.9 3 0.6 2 1.8 6
24 0.9 3 0.9 3 1.8 . 6 ffftfffen ir"*" e r c ft c
A A
30 1.0 4 1.0 3.5 2.4 8 Iff TV 43* ff a r-c 10' II' II' n' II'
UfTOSo' 8' a' 8 to 1 S-C'
36 1.5 5 1.0 4 3.0 10 (. to' 7
11M deg 12 0.3 1 0.3 1 0.3 1 T f'-f f >' n' <?
uf-me* T V
16 0.5 1.5 0.5 1.5 0.3 1 £>zi PIPS JYfrv f r evu /a.-o
20 0.5 1.5 0.6 2 0.3 1
24 0.6 2 0.8 2.5 0.6 2 CONCRETE COUNTER-WEIGHT FOR VERTICAL BENDS IN PIPELINE
30 0.8 2.5 0.9 3 0.6 2
36 1.0 4 0.9 3 0.6 2

*For internal pressure of 0.69 MPa (100 psi) and an allowable soil-bearing pressure of 96 kPa Fig. 3. Typical Blocking Schedule
(2 kip/sq ft)
fTied length = 0.3T /(2 (soil weight) + pipe weight + water weight] where the pipe weight Internal pressure, 0.85 MPa (125 psi); allowable soil-bearing pres
is that for ductile iron, class 522. Soil weight = 100 Ib/cu ft. sure, 96 kPa (2 kip/sq ft)

132 OPERATIONS JOURNAL AWWA


SECTIONA-A
•Scale '/*'" I'-O'

12 16 20 24 30 36 42
Pipe Diameter in.

Fig. 4. Volume Requirements for Thrust Blocks


Pressure conditions as for Fig. 2
SECTION B-B so,h:&••?•<>•
Fig. 5. Dead-End Redesigned for Add-On Connection
Internal pressure 0.85 MPa (125 psi)

water-hammer pressure, and (5) thermal expansion or


contraction. c- a£
Of these five factors, 1 through 4 must be given Figure 1, a hydraulic force diagram for pressurized
proper design consideration for both exposed and conduits, shows a typical pipe bend with a deflection
buried pipe. The thermal expansion and contraction for angle 9. In this pipe of constant diameter under steady-
buried pipe are of minor importance and can usually be flow conditions, the two unbalanced forces F may be
neglected without practical effect. However, for some combined with R, the equilibrant required for blocking.
cases of exposed piping systems, thermal expansion Resolved into components, F and T can be obtained as
and contraction do become important factors. the required balance for tying or harnessing pipe joints.
For a restrained piping system, thermal stress due to For tees and dead-end pipe, T = F = PA, which means
temperature change is that the entire force comes into play.
In the specific case of 90 deg bends, the thrust for
S = Eel
Also blocking purposes R is ^/ 2 PA, whereas for tying of
F = aEet pipe joints, F equals T, which equals PA.
where E is the modulus of elasticity of the pipe mate
rial, Practical Considerations
e is the coefficient of linear expansion, Pipelines buried in earth become a part of an envi
t is the change in temperature, ronment in which the physical characteristics can
S is the unit stress, change abruptly in short distances. Although pipe is
F is the total force developed, and normally laid to varying shallow depths in unconsoli-
a is the area of the pipe's cross section. dated materials by cut and cover methods, many
For an unrestrained piping system, of length J, kilometers of pipe are laid in rock, in tunnels, and
thermal expansion or contraction can be computed as under marine conditions.
Ai = etl When engineers design buried piping systems, the
Stress elongation due to operational pressure head or trenching conditions in the installation are for all
water hammer can be estimated as practical purposes usually unknown. If rock or highly
MARCH 1978 G. E. NEHER & Y. T. LIN 133
160 /SB ise
A *\ PROFIL.E.
a-o\_'
•f'O' £ '1*1 -Tfinbtr Pi'/ct
= j- -- H /under ffn Soufhaide of ftalf

12 18 24 30 36 42 48 54 60 66 72 78 84 90 96

PLAN SECTIONA-A SECTION B-& Fig. 7. Balancing Forces Required for Tied Joints
Rg. 6. Pipe Deflection Incurred for a Particular Project Because of Internal pressure 0.69 MPa (100 psi)
Unforeseen Trench Conditions

unstable soils are expected, borings are made to esti fill, the failure of a mechanic to tighten all the bolts on a
mate to what extent these conditions prevail. But for restrained joint (in particular the ones not easily reach
the great majority of projects, some quite extensive, no ed), the fluctuation in groundwater conditions, the
knowledge of trenching conditions exists until the heterogeneous characteristics of soils, the shifting of
backhoe takes its bite. loads, the overly opened joints, the failure of passive
Since safe bearing pressures of soils can vary as soil pressure to react in time, and other factors of lesser
widely as the soil types, it is prudent to take a conser magnitude should not be glossed over without due
vative approach to the design of restraints for unbal regard to the consequences. Diligent, thorough inspec
anced hydraulic forces. Based upon judgments made tion during installation can aid in lessening the impact
after many years of experience, it has been determined of these indeterminate factors but cannot be fully
that an allowable soil pressure of about 96 kPa (2000 lb/ counted upon.
sq ft) is a safe figure for trench wall bearing, which will For small-sized pipe, 12 in. and less, there is a line of
suffice for almost all trenching conditions except for options for controlling runaway pipe deflections. Each
previously excavated areas, quicksand, muck, and very is good, has its advocates, and through experience has
soft clays. Fortunately, such formations are fairly rare, proved its worth. Some swear by hardwood-block
but when they are encountered special provisions must supports; others by concrete; whereas many in recent
be made. years have extolled the virtures of tie rods, clamping
In areas of previously excavated trenches or where devices, retainer glands, and anchored fittings. The
there is the likelihood of additional underground main concern is that the pipe stay in place: hardwood
activity in the future, the use of thrust blocking is often blocks should be driven to compress the trench wall;
precluded. In such situations the analysis and subse concrete should be placed against native soil; and
quent design for tying of joints should be based, as in ferrous metal tying systems must be protected with
the case of blocking, upon conservative parameters, ample coatings of bitumastic or other protective envel
particularly with regard to large feeder mains. opes to prevent deterioration.
Experience has demonstrated that safety factors for Flexible tied jointing systems from different manu
indeterminates such as the improper tamping of back- facturers vary considerably as to method of restraint,
134 OPERATIONS JOURNAL AWWA
degree of flexibility, and materials of construction. It should be noted that the incidences where reaction
Special joints are expensive and, for sizes 16-in. and blocking and counterweighting are necessary on a
upward, can increase the per-foot material cost of full project some 64 km long are quite minimal and add
lengths of pipe from 15 to 50 per cent. Where both very little to the total cost.
methods of restraint i.e., blocks or tied joints are Large-degree top-vertical bends are to be avoided if
applicable to a given situation, a cost analysis should possible. The vertical transitions are better and of more
be made to determine the most economical solution. economical design if accomplished gently. The same
holds true for large horizontal deflections if sufficient
Thrust Blocks
right-of-way is available to accommodate them.
Figure 2 displays the resultant forces created in The geometric configuration of the blocks (for esti
closed conduits under a 0.69-MPa (100-psi) head for mating and general construction purposes) may be
pipe up to 72-in. in diameter for various degrees of altered somewhat as long as the minimum bearing area
angular deflection. Also shown is the reaction blocking H X L is provided where H and L are the height and
area required for a 96 kPa (2000 Ib/sq ft) trench-wall length, respectively, of the bearing area.
loading as previously mentioned. From this graph other Forming for the concrete blocks is usually
resultant forces and reaction-blocking areas may be accomplished by sand bags backed up by trench fill. A
calculated by multiplying the ratio of greater or lesser four-bag concrete mix with a water cement ratio of
internal pressures and safe bearing values by appro about 30 1 (8 gal) per sack is more than adequate to
priate ratios. transmit the thrust loads to the undistributed portion of
It is of interest to note that for thrust-block solutions the trench wall.
a tee, plug, and 60-deg bend generate the same resultant An estimate of the quantity of concrete in cubic
forces and require like reaction areas. Although full yards needed for various-sized concrete blocks is
lengths of bevel pipe would not require restraint for a shown in Fig. 4. The curves show the volume of
96-kPa (2000-lb/sq ft) soil, under certain conditions blocking for pipelines 12- through 72-in. under a 0.69-
bevel adaptors of short laying lengths could. MPa (100-psi) internal pressure, assuming a safe
Figure 3 was developed for a previously installed bearing value of 96 kPa (2 kip/sq ft) for the side walls of
transmission main project, some 64 km (40 mi) in the excavation. The approximate yardage is calculated
length. The internal design pressure 0.85 MPa (125 psi) by the equation: 'A H (L -1).
and an allowable soil-bearing value of 96 kPa (2 kip/sq Figure 4 may be conveniently reworked for costs by
ft) were selected to cover whatever material might be substituting current prices for ready-mix concrete.
encountered in the entire length of trench excavation. Under circumstances where design indicates that
The schedule shows the size of the thrust blocks for 48-, blocks, or tied joints, or both are applicable for
60-, and 72-in. pipe. Also shown is a table for counter restraint, the decision on which to use will logically be
weights for vertical top bends. The counterweights are based on cost.
nothing more than gravity blocks of concrete that
balance the upward hydraulic forces of vertical pipe Special Applications
line deflections. At the bottom of the vertical bends, Complex interconnections. Figure 5 shows the design
concrete pads, in the same proportion as required for for a dead end, with provision for future extension and
horizontal bends, are used. a five-valve connection and crossover between a new
MARCH 1978 G. E NEHER & Y T. LIN 135
60-in. main and an existing 48-in. main. (The latter unbalanced forces of the gradual horizontal deflection
could be taken out of service for a time to allow a cut- of 27 deg were absorbed by concrete blocking tied
in.) It is seen that many unbalanced hydraulic forces of integrally with the concrete cradle atop the piling
various magnitudes are in play. section and by the natural physical forces in that
The main force to be reckoned with for the 0.85-MPa portion of the segmental curve where average trenching
(125-psi) pressure criteria is the thrust on the 60-in. conditions were encountered.
blank flange. This force, some 1.6 X 106 N (350 kip), has The pipeline has been in service many years and is a
been overcome by two sets of interlocking steel sheets part of a single water-supply transmission main serving
tied into an unexcavated sandy soil formation. The son some 100 000 people.
loading on the two sets of sheets, about 23 m 2 (250 sq ft),
is about 67 kPa (1400 Ib/sq ft). The concrete placed Tied Joints
ahead of the sheeting transmits the thrust from the As previously shown, the force generated by
under and over 24 WF 120# sections (designed for hydraulic pressures to be balanced by a tied system is
minimum deflection), which take the hydraulic thrust given by the expression
from the two load-transfer stubs. T = F = PA (1 - cos 6)
Other unresolved forces in this piping system are The curves plotted in Fig. 7 for pipe diameters of 12-96
those in the 60- by 36-in. tee looking up; the 36-in., 90- in. are convenient for estimating the total force to be
deg vertical bend; the 36-in., 30-deg horizontal bend; restrained for various pipeline deflections from 11 %-90
and the 48- by 36-in. tee. The downward thrust of the deg.
60- by 36-in. tee is nullified by a concrete pad, and the These curves, based on calculations for a design head
other unrestrained forces are negated by the gravita of 0.69 MPa [(100 psi) (230 ft approximately)], can be
tional weight of pipe, water, and earth. The flanged readily adapted for greater or less design pressures by
gasket joints are adequately protected from corrosion multiplying the curve data for any particular pipe size
by protective coatings. by the appropriate ratio.
The 60-in. blind flange is to be removed in the future For buried service, when determining which lengths
for installation of a 72-in. transmission-main extension of pipe are to be restrained to counteract hydraulic
without shutdown of either pipeline that is presently in forces, conservative parameters should be used as
service. Connections such as these should be of very elaborated earlier. Simply stated, the major force in a
conservative design and based upon sound engineering tied system restricting the thrust T is frictional
judgment. The slight additional cost between a safe-or- resistance to movement occasioned by the dead loads
sorry design for a few such connections on multimillion of pipe, water, and trench backfill.
dollar transmission-main projects is well justified. The magnitude of these dead loads is readily calcu
Pipe bend on piling. Problems almost always arise in lated once the size, material, and the minimum depth of
the field after designs are complete, bids taken, cover is established. The one unknown in the analysis,
contracts let, pipe purchased, and pipe installed. Often the one with the greatest impact, is the earth: hetero
solutions must be found at the site. The appearance of geneous, and complex to an extreme.
the topography, for example, can effectively hide Prudent designs for buried tied-piping arrangements
mysteries beneath the earth as encountered in the more should embody a conservative approach to cover the
than 40-km-(25-mi-)long transmission-main project de whole gamut of soil characteristics, trench wall condi
picted in Fig. 6. The contractor's crew on that section of tions, compaction of backfill, and all the other
the work was laying an average of about 120 m (400 ft) unknown variables.
of 42-in. pipe per day. At the end of each day, a cap was Table 1 shows the conditions of pressure, depth of
installed. One morning it was found that the last pipe cover, and unit weight of backfill indicated for pipe
laid the previous day had settled and come completely sizes 12- through 36-in. The coefficient of friction is
out of the bell. The logical solution was tried: stabilize taken as 0.30 according to best engineering judgment to
the bottom by replacing unsuitable material with gran cover all cases except those encountered in unstable
ular bedding. In a short time it became apparent that ground.
this was not the answer. Soon the excavation was such For comparison, the blocking necessary to ac
that it took several days to remove the backhoe, which complish an equivalent restraint is shown. Although
had been operating on mats. A muck deposit of the pipe weight for Table 1 is based on class 522 ductile
substantial size had been encountered. iron, the tied lengths are equally applicable for
The depth of the deposit was probed with a re-bar, concrete pipe. Where the tied lengths are indicated as
which delineated the depths as shown on the profile. It less than the laying length for small deflections, only
was prudent to skip this area until the frost of winter the bend needs to be tied.
could allow heavy track-mounted equipment sufficient
support. Meanwhile, field solutions were worked out. Yard and Plant Applications
Local timber was cut, stripped, and peeled for piling, In the vicinity and at the site of water-treatment
and the engineer in residence designed the pile bents plants and pump stations, extremes in head conditions
and concrete cradle after conferences with the pipe are normally encountered. These heads may vary from
manufacturer and the installation contractor. the low of open-channel flow to those in excess of 1.38
Later, with conditions right (frost line well below the MPa (200 psi) without allowance for water hammer. In
surface), the construction within the muck area was such locales it is of utmost importance that reliability
accomplished at little extra cost to the owner. The and continuity of water supply be maintained. .
136 OPERATIONS JOURNAL AWWA
.Sent,

24 30 36 42 48 54 60 66 72 78 84 90
Pipe Diameter in

Fig. 10. Tied Lengths for Low-Head Pipe Yard Piping


Conditions as for Fig. 8

12 18 21 30 36 42 48 54 60 66 72 7B 84 90

Fig. 8. Resultant Forces for Blocking for Low-Head Plant Yard


Piping
Internal pressure, 30 kPa (10 ft head); velocity, 0.6 m/s (2 fps)

12 18 24 30 36 42 46 54 60 66 72 7

Fig. 9. Balancing Forces for Tied Joints for Low-Head Plant Yard Fig, 11. Two Tied-Joint Configurations for Suspended Piping
Piping
Conditions as for Fig. 8

MARCH 1978 G. E. NEHER & Y. T. LIN 137


Support for thrusts by blocking buried piping in adequate allowance for expansion and contraction.
constricted plant areas is not possible because of the Joints available for this type application are
existence of previously installed utilities and the need harnessed Dresser-type sleeves, grooved or collared
for future extensions. Under such conditions, tied joints Victualic-type couplings, and flanged coupling adapt
or a combined restraint of tied-blocked joints are in ers. For high heads, the Victualic and flanged-type tied
order. couplings are limited to small sizes. They are available
Figure 8 shows the resultant force R created by low in large diameter for low-head conditions. For use in
head, low velocity conditions, which are often the systems of high pressure and large diameter (36 in. and
average values encountered in water treatment greater), harnessed Dresser-type sleeves offer a reliable
processes. Although the total forces to be restrained are restrained flexible joint.
comparatively small, in pipes entering poured-concrete In Fig. 11 typical design examples of steel-pipe
structures through wall sleeves with fitting bends discharge headers under 0.3 MPa (100-ft) maximum-
located close to the wall, the fittings and pipe entering design head are demonstrated. Hangers are provided at
the structure should be blocked if possible. If not, both sides of the joints to allow movement of the
fittings should be tied integrally with the concrete wall header. In addition, two harness tie bolts are installed
to prevent movement and subsequent leakage. for each joint to transmit thrust forces.
Figure 9 is a graphic presentation of the balancing Figure 11, case A, shows a design example of a 42-m
forces required for restraining yard- and plant-piping (140-ft)-long welded-steel discharge header for eight
systems up to 96-in. diameter. Tees, plugs, and 90-deg pumping units. The header was restrained by blocking
bends for tied joints of the same pipe diameter require at a dead end and by a wall pipe with a water stop
the same balancing-system equilibrium. As stated in collar at the other. The tied joint provides flexibility for
previous examples, the required balancing forces for thermal expansion and contraction and transmission of
design heads other than 30 kPa (10 ft) may be derived thrust forces. It also allows suitable clearances for
by multiplying curve data by the proper head ratio for installations.
the pipe sizes and fittings under consideration. In case B, a 48-in. main is suspended from the floor
Tied lengths of yard-piping systems in plant areas are slab of an existing settling-inlet basin with an offset in
shown in Fig. 10. The lengths were figured for conduit the open space between the two structures.
sizes to 96-in. diameter operating under 30 kPa (10 ft) of The settling basin portion of the 48-in. line is some
head. The calculations for the restrained lengths are on 205 m (680 ft) in length and hung below the interme
the premise that practically all water plants have diate slab of four equal-width two-story settling basins.
expanded in physical size as needs increased at least The header is anchored to the basin floor slab with a
once since their founding. Thus additional, adequate tied joint to restrain the thrust and with sufficient
factors of safety should be introduced. flexibility to prevent a thermal expansion-and-contrac-
Figure 10 does not allow for the dead-load weight of tion movement of the wall pipe, precluding leakage at
trench backfill (as it may not be there) in the frictional- the walls. This tied system must be designed to offset
force's resisting movement. For tied joints in plant thermal length variations of both the pipe and struc
yards, only the frictional resistance to sliding produced tures.
by the combined weight of pipe and water is consid The change in elevation and direction of the 48-in.
ered and the formula for the frictional resisting force pipe between the structures is accomplished by the use
is of steel segmental bends, suspended and tied, to resist
f = (pipe .weight -I- water weight) X 0.3 thrust and allow seasonal temperature-induced move
As expected, the data plot is very flat. Though the ment between the two structures without causing joint
tied lengths of these low-head systems are short, they damage.
are among the most important to be restrained. Summary
Presently, there is a plant expansion under construc Adequate supports of conservative design for
tion where special piling tie-backs must be placed to resisting unbalanced hydraulic forces created by direc
give temporary support to a 60-in. concrete bend laid tional changes in piping systems must be provided to
prior to the development of present-day special-design ensure water tightness and integrity of all piping
tied-joint fittings. In most cases it is sufficient to only systems. Since there is no way to predict the physical
restrain a few lengths of pipe each side of the bends, characteristics of materials in which water mains are
and in the case of minor angular deflections, only the laid in advance of excavating, a conservative basis for
fitting need be tied. design is recommended. The restraints provided for
Flexible Joints-Tied exposed pipe systems and low-head yardage conduits
in water plants should also be of conservative design.
In water-utility practice tied joints with special flex Thrust-restraint problems require practical solutions
ible capabilities are for the most part limited to based on proper evaluation of knowns using common
exposed plant piping installations in pump stations and sense and, above all, sound engineering judgments.
water-treatment installations. These types of joints
must provide thrust resistance while providing suffi
An annual conference paper selected by the JOURNAL, authored by
cient clearances for installation and enough flexibility George E. Neher (Active Member, AWWA), partner, and Y. T. Lin
to accommodate length changes due to temperature (Active Member, AWWA), ch. design engr., both of Alvord, Burdick
and Howson (Consultant Member, AWWA), Chicago, III.
variations. For a long, straight pump discharge header
with restrained ends, a proper design must include 55765 5600

138 OPERATIONS JOURNAL AWWA

You might also like