Professional Documents
Culture Documents
009 RCC Job Procedure 12
009 RCC Job Procedure 12
1. PURPOSE
2. SCOPE
3. SPECIFICATIONS / REFRENCE DOCUMENTS
4. RESPONSIBILITY OF THE DESIGNATED IN CHARGE
5. MATERIALS
6. GRADE OF CONCRETE
7. TYPE OF CONCRETE MIX
7.1. DESIGN MIX CONCRETE
8. CONCRETE PRODUCTION
9. PLAIN CEMENT CONCRETE
10.REINFORCED CEMENT CONCRETE
11.TRANSPORTING, PLACING, COMPACTION & CURING
11.1. TRANSPORTING & HANDLING
11.2. PLACING
11.3. COMPACTION
11.4. CURING
12.PROTECTION OF FRESHLY LAID CONCRETE
13.FIELD TEST
14.CONCRETE REPAIRS
15.FORM WORK
16.REINFORCEMENT WORKS
17.SAFETY PRECAUTIONS
1. PURPOSE:
The purpose of procedure is to carry out concreting works at site and to ensure
that proper quality control assurance is achieved at HPCL-VRMP Project –
Visakhapatnam.
2. SCOPE:
This procedure covers the various steps involved in executing plain &
reinforced concreting works for various structures like pile cap, foundation,
column, slabs, precast elements etc. including curing, testing, finishing and
repairing of concreting.
Lead Civil Engineer /Construction Manager: Responsible for monitor the daily
construction activities at site.
Safety Engineer: Safety Engineer shall be responsible for safety of all persons
involved in the job.
Lead Quality Engineer: Quality Manager shall be responsible for overall Quality
activities at site.
5. MATERIALS:
5.3. CEMENT
Cement will be as per mix Design for super structure and sub structure
concrete work. Cement will be stored in ready go-downs batching plant to
protect from dampness and will be made easily accessible for proper
inspection and accounting.
Cement shall be procured from primary manufacture as mentioned in
contract documents.
5.4. STEEL
Tor steel reinforcement shall be procured from approved manufacture for
cement concrete works confirming to high yield strength deformed steel
bars of GR. Fe 500D of IS 1786-2008 and co related with MTC [Manufactures
test certificate] and challan issued by manufacture.
Material shall be accepted based on manufactures test certificate and review
of certificates /test reports and other documents like delivery order, delivery
challan, etc.MTC will be produced for all types of reinforcement steel and for
all the consignments coming to site in the case of absence of MTC or
incomplete documentation, the same will be tested in an approved
laboratory as per IS 1786-2008 prior to use.
All reinforcement bars will be clean and free from dirt, oil, paints, grease,
mill scales and loose rust. Bar bending schedule will be prepared before
cutting.
5.5. WATER
The water used for concrete work shall be clean and free from harmful
chemicals and organic material to ascertain the same, a sample of water will
be tested in any of the approved laboratories prior to the commencement of
work and later on in case if any visible change is found. The water shall be in
general conforming to the requirement of IS 456:2016.
It shall be clean and fresh, free from oils, acids, alkalis, or others deleterious
material whether in solution or in suspension.
5.6. ADMIXTURE
Admixture used shall comply with approved manufacture
6. GRADE OF CONCRETE:
Grade of concrete shall be as per drawing:
1. M-10 For PCC work
2. RCC with M-40 grade concrete For Pilling work and Pile Cap Work
8. CONCRETE PRODUCTION:
Availability of all approved ingredients to the required quantity shall be
ensured at Batching plant before start of concrete.
Concrete shall be supplied from Batching plant after confirmation from site.
The concrete shall be mixed at the Batching plant as per the approved mix
design.
Batching of ingredients shall be done in accuracy of +/-2% of cement being
measured &within +/-3% of aggregate, Admixture & water being used as per
IS
The moisture content of the coarse and fine aggregate shall be checked by
the QC Engineer @ Batching plant and suitable adjustment made as per IS
456-2016 on daily basis.
The concrete shall be thoroughly mixed to achieve required workability at
the point of pouring.
Slump requirement at site:
1. For Pilling work – 150mm to 180mm after 3 hours
2. For Pile cap Work – 75mm to 100mm after 3 hours
3. For PCC work – 100mm to 130mm after 3 hours
11.2. PLACING
Pour plan for mass concreting to be submit before 2 days.
The method of placing of concrete shall depend on quantity of concrete,
type of structure, type of formwork etc.
The concrete pour shall be checked for the position, level, proper
reinforcements, embedded parts, and adequacy of shuttering, scaffolding
etc & concreting shall be commenced on approval from engineer in charge.
Concrete shall be laid in layers no greater than 400mm, and each layer shall
be compacted using appropriate vibrators. Concrete shall not be moved
horizontally by vibration and care taken to avoid segregation while pouring.
Placement of concrete shall continue until the completion of the concrete in
one pour to avoid cold joints in concrete unless construction joints are
specified
The maximum permissible free fall of concrete may be taken as 1.5mts.
Mass concrete shall be planned and discussed with clients representative
well in advance, separately with pour sequence, rate of pour, pumping
arrangement and vibrators as required
Concrete shall be placed without segregation,
The concrete shall be placed in its final position and compacted before initial
setting time of concrete commences after first mixing of water, cement and
aggregates
Water for use in mixing concrete and curing shall comply with the
requirements of IS4546
For provision of construction joint at place other than mentioned in drawing
prior approval shall be taken from engineer in charge.
No wet concrete shall be placed in flowing water.
Concreting shall be carried out continuously up to construction joints
Vertical construction joints shall be formed by the insertion of rigid stopping
off forms.
Provision of boom pressure and concrete pump to be available at site as per
instruction of client.
11.3. COMPACTION
Concrete should be thoroughly compacted and fully worked around the
reinforcement, around embedded fixtures and into corners of the formwork.
Concrete shall be compacted using mechanical vibrators complying
IS456.Over vibration and under vibration concrete are harmful and should be
avoided. Vibration of very wet mixes should also be avoided.
60 mm Dia of needle for Vibrator to be used at site.
11.4. CURING
Curing is the process of preventing the loss moisture from the concrete
whilst maintaining a satisfactory temperature regime. The curing regime
shall also prevent the development of high temperature gradients within the
concrete.
Concrete works shall be cured for minimum of 7 days.
Adequate Hessian clothes must be used for curing purposes at site.
17.3. BENDING
All bending shall be done at rebar yard.
All vertical bars shall be joggled at top to accommodate the laps, bars shall
be sent cold.
17.4. FIXING OF BARS
The reinforcement shall be fixed, supported and maintained in position by
adequate use of chairs, cover blocks and binding wire.
Reinforcement shall be fixed with line, level and spacing to be maintained as
per the approved drawing.
The lap length shall be as per drawings or otherwise specified by Field
Engineer.
Laps shall be staggered wherever required or as indicated in the drawing.
Reinforcements may be cut, adjusted and lapped to accommodate
embedded parts in position and add rebar where shifted.
Minimum clear cover shall be as per AFC drawings.
Cover blocks, will be made of same grade of concrete and shall be used to
ensure the required cover for reinforcement.
Cover blocks are generally square or circular in plain with or without binding
wire embedded in them which will be tied to the reinforcement at the time
of placing.
No splices shall be made in the reinforcement other than described or
approved.
Bars crossing each other shall be secured by binding wire, of 16 SWG.