PT.

TIMUR SATRIA PERKASA


MINING & GENERAL CONTRACTOR
PT. DUTADHARMA UTAMA COAL MINE PROJECT
JOB SITE Ds.SUMBERJAYA, KINTAP, TANAH LAUT, KALIMANTAN SELATAN

Daily Report
14 Desember 2018

3. Daily Oil Consumption

SHELL KGO SCANIA TOTAL GREASE WATER COOLANT


Description Engine HYD Engine HYD Engine Axle Gear RUBIA TIR AZOLLA RUBIA FLEET TRANSTEC 5 TOTAL Allmakes Pertamina
AF-NAC
15W-40 R2-30 T S2 M68 15W-40 EO-30 VG 46 15W-40 80W-140 15W40 ZS 68 HD200 SAE30W 85W 140 MULTI EP2 AM SLG D180 EPX NL2
Begin Stock - - - 2,315 213 2,365 - 470 30 65 - 155 - - 2 5

In 200

Consumption - - - 280 10 30 45 - - - 1

End Stock - - - 2,035 203 2,365 - 470 - 220 - 155 - - 2 4

4. Unit Break Down / Service & Trouble Time

UNIT FAILURE MRO PO


UNIT MODEL HM DAYS STATUS PROBLEM ETA PLAN RFU REMARKS
CODE DATE TIME NO DATE NO DATE
Prepare Install Part Engine Inner Part (Part Ready) - - - - PARTS READY -

Prepare Install Part Differintial Front + Rear (Part Ready) - - - - PARTS READY -

SCANIA P380 DT.325 20-Jul-18 123870 147 Waiting PO Transmission Assy 1328 1-Oct-18 - - JAN.19 -

Prepare Install Part AC System (Part Ready) - - - - PARTS READY -

General Check Request Additional Part - - - - -


Eta selesai Panca 18
R480LC-9S EX.350 30-Apr-18 9041 228 Recondisi Panca Cylinder ARM Assy Brocken 1619 9-Dec-18 1278 11-Dec-18
dec
Des.18
perbaikan dari CV
R480LC-9S EX.354 9-Dec-18 13881.6 5 Waiting Mech. Vendor AC System - - - -
Kahayan
` R480LC-9S E.357 26-Oct-18 8265 49 Waiting Mech Uniquip Main Pump (Part Ready) - - - - Des.18 -

Progress UT Low power Hydraulic system 1415 13-Nov-18 1102 16-Nov-18 -


Eta selesai Panca 18
Repair Panca Recoil spring Assy - - - -
Dec
PC800 EX.353 10-Sep-18 13907 95 Des'18 Eta selesai Panca 24
Repair Panca Cylinder ARM Assy RH-LH 1622 9-Dec-18 1273 11-Dec-18
Dec
Eta selesai Panca 24
Repair Panca Swiple Joint Assy - - - -
Dec
SCANIA P380 DT.330 21-Nov-18 17461 23 Prosses repair vessel vessel dump brocken - Plate Ready 1496 22-Nov-18 1207 30-Nov-18 Des.18 -

Install Part Rear axle crack (Part Ready) - - - - -

SCANIA P380 DT.331 22-Oct-18 17244 53 Install Part Outer Part Engine (Part Ready) - - - - Des.18 -

Waiting Parts Electrical Part 1345 1-Nov-18 1118 19-Nov-18 Eta masuk 30 Dec

SCANIA P380 DT.334 5-Nov-18 17194 39 Prosses repair vessel vessel dump brocken - Plate Ready 1496 22-Nov-18 1207 30-Nov-18 Des'18 -

SCANIA P410 CT.436 23-Nov-18 6906 21 Wating Parts Liner, Con Rod Bearing, Gasket Head 1535 28-Nov-18 1226 4-Dec-18 Des.18 Eta masuk 30 Dec
Eta selesai Panca 22
D85ESS-2 D.365 22-Nov-18 3735 22 Proses Repair Recondition Arm Blade Assy 1623 9-Dec-18 1274 11-Dec-18 Des'18
Dec

Total Break Down Time 682 Days

5. Support Equipment

MRO PO
NO. SUBJECT DESCRIPTION DAYS STATUS REPONSIBLE ETA REMARKS
NO. DATE NO. DATE
1 PC 800SE-7 (E-351) Glass & Weather Strip 1451 17-Nov-18 1239 5-Dec-18 27 Waiting part UT Eta part masuk 08 Dec - Unit Operasi (Part Very Urgent)
2 BULLDOZER D155A (D-364) Repair Autolube System 1480 19-Nov-18 25 Waiting QUOT UT HO Unit Operasi (Part Urgent)
3 BULLDOZER D155A (D-368) Repair Autolube System 1481 19-Nov-18 25 Waiting QUOT UT HO Unit Operasi (Part Urgent)
4 PC 1250-8 (E-458) Shroud & bolt assembly 1469 19-Nov-18 1281 10-Dec-18 25 Waiting part UT Eta part Masuk 02 Jan '19 - Unit Operasi (Part Urgent)
5 GRADER GD705-5 (MG-490) Stud 1393 8-Nov-18 1270 10-Des-18 36 Waiting Part UT Eta part masuk 30 Dec - Unit Operasi (Part Urgent)
Plate 1594 6-Dec-18 1262 10-Des-18 8 Waiting Part UT Eta part masuk 20 Dec - Unit Operasi (Part Urgent)
6 SCANIA P360 (DT-451) Pneumatic Knock-off valve 1580 3-Dec-18 1265 10-Dec-18 11 Waiting part UT Eta part masuk 18 Dec - Unit Operasi (Part Urgent)
7 SCANIA P380 (DT-332) Torsion Bar 1613 9-Dec-18 1294 13-Dec-18 5 Waiting part UT Eta part masuk 20 Dec - Unit Operasi (Part Urgent)
8 SCANIA P380 (DT-335) Torsion Bar 1613 9-Dec-18 1294 13-Dec-18 5 Waiting part UT Eta part masuk 20 Dec - Unit Operasi (Part Urgent)

6. OTHER ISSUE

NO. SUBJECT PROBLEM CORRECTIVE NEED SUPPORT CURRENT STATUS

1 Radio Kekurangan Radio RIG Radio yang rusak sudah dikirim ke Jakarta Segera radio yang sudah diperbaiki dikirim ke Surat Jalan : TSP-MAINT-181009-043 (Waiting Radio Rig)
site atau di belikan unit yang baru

14 Desember 2018

Prepared Checked Re-Checked

M. Dicky Febrianto Musa Al-Habsi