PROPOSED OT SLUICE ON BHEEMGHANPUR APPROACH CHANNEL

DESIGN AT OT 330.000 M. FROM MAIN ROAD ON RIGHT SIDE OF APPROACH C

1) HYDRAULIC PARTICULARS Duty : 150 Ac / Cusec


Sl.No Description Units Parent Canal O.T
1 Ayacut Acres 1964 0
2 Discharge (Req) Cum 24.0000 0.119
3 Discharge ( Des) Cum 26.0000 0.119
4 Bed Width m 12.000 0.450
5 Full Supply Depth m 5.866 0.450
6 Free Board m 0.450 0.000
7 Side Slopes I/O 11/2:1 / 2:1 0 / 0
8 Bed Fall 1 in 3000 1 in 1000
9 Velocity m/sec 0.428 0.75
10 Value of 'n' 0.025 0.018
11 Top width of Banks L/R 30.0 / 30.0 0.00 / 0.00
12 C.B.L 161.070 161.040
13 F.S.L 166.936 161.490
14 T.B.L 168.000 168.000
15 G.L 167.000 167.000
16 Depth of Cutting m 5.930 5.960

2) DRIVING HEAD:

Driving head 3.979 m


Provide 1 No circular pipe as diameter of
Dia of Pipe 0.151 mm
So provide 1 vent pipe of 450 mm dia NP2 class for OT

Therefore vent provided = 0.159 >= 0.018 HENCE O.K


5) LENGTH OF BARREL

To reduce the Barrel Length of D/S Head wall to be Raised 0.000 m

7) UPSTREAM TRANSITION:

The length of U/s transition (or) The Horizontal length of U/s sloped wing
= 8.273 m
say 8.280 m
Outer width of transition
= 5.970 m
say 6.000 m

7) DOWNSTREAM TRANSITION:

D/S Transition = 5.000 m

DESIGN OF HEAD WALL (U/S)

Top Width = 0.600 STRESS TABLE Base


Foundation Offset = 0.300 Max Min Width
Foundation Thickness = 0.600 Concrete 34.17 -2.753 2.91
Batter. = 2.310 Soil 28.727 2.861 3.51

DESIGN OF WING WALL (U/S)

Top Width = 0.500 STRESS TABLE Base


Width
Base
Foundation Offset = 0.300 Max Min Width
Foundation Thickness = 0.600 Concrete 15.961 10.174 6.02
Batter. = 5.516 Soil 15.407 12.474 6.62

DESIGN OF HEAD WALL (D/S)

Top Width = 0.600 STRESS TABLE Base


Foundation Offset = 0.300 Max Min Width
Foundation Thickness = 0.600 Concrete 1.95 1.712 2.58
Batter. = 1.980 Soil 3.203 2.871 3.18

Drawing
T SIDE OF APPROACH CHANNEL
DHARMASAGAR TANK
8274 1200 0.0 30000 13020 600 SOUTH CANAL
0 Duty : 150 Ac / Cusec
SL.NO Description Units Parent Canal O.T

1 Ayacut Acres 1964 0


+167.386 T.B.L +168.000 2 Discharge (Required). Cumecs 24.000 0.119
2 G.L +167.000 3 Discharge (Designed). Cumecs 26.000 0.119
:1
+166.586 4 Bed Width m 12.000 0.450
5 F.S.D m 5.866 0.450
Groove150mm Width 6 Free Board. m 0.450 0.000
6316

+161.490 7 Value of ' n ' - 0.025 0.018


75 mm Thick W.C 8 Bed Fall. - 1 in 3000 1 in 1000
in CC M-15 9 Velocity. m/sec 0.428 0.750
C.B.L +161.070 450mm Dia NP3 Class Pipe +161.04 10 Side Slope (Inner / Outer). 11/2 : 1 / 2 : 1 11/2 : 1 / 2 : 1

300
0 11 Top Width of Banks.(R/L) m 30 / 30 0/ 0
+160.995 2910 1980 600 12 G.L m + 167.000 + 167.000
+160.395 150 mm Thick Bed 13 C.B.L m + 161.070 + 161.040
+160.095 300 Cone Under Pipe 14 F.S.L m + 166.936 + 161.490
8874 44220 -14220 15 T.B.L m + 168.000 + 168.000
16 Depth of Cutting. m 5.930 5.960
Provide 30000 mm Length Pipe 2500 mm Length 12 No's
NOTE
1 All the Dimensions are in Millimeters and Levels are in Merters.
G.L 2 Do Not Scale the Drawing.
300
600 SPECIFICATIONS

1980
300

300
600
300

1 Foundations : CCM10 Using 40 MSA.


300 1.5 : 1 2 Under Pier. : 150mm Thick in CCM-15.
500 3210 3 Head Walls, Wings & Returns. : In CCM-15 Using MSA.

0
Canal Flow

2910 4 Wearing Coat. : In CCM-20 75 mm Thick.


1200 5 Protection : 100 mm Thick Lining on
450mm Dia NP2 Class Pipe D/S Side.
7600

6000

150mm Thick in RCC M-20


450

450
450
6 Platform : Using 20MSA with 10mm
1200 dia Bars @ 150 C/C Both
Ways.
500 2250 850 m

0
300 150 0
1650
600
450

850 m
450
300 +0.000 150 150
600 +167.386 3180 STRESS TABLE
Description Concrete Soil
600 +161.490 500 +166.586 150 Max Min Max Min
Head wall U/S 34.170 -2.753 28.727 2.861
PIPE C/S Wing Wall U/S 15.961 10.174 15.407 12.474
6391

Head wall D/S 1.950 1.712 3.203 2.871


5591
450

GOVERNMENT OF ANDHARA PRADESH


IRRIGATION & CAD DEPARTMENT
2310

1980

5516
300

300

300

300

300

600 +160.995 600 +161.040 500 +160.995 PROJECT:


600 600 600
CPWS SCHEME TO BHUPALPALLY AND OTHER HABITATIONS FROM
BHEEMGHANPUR APPROACH CHANNEL, GOLLABUDDARAM (v),
BHUPALPALLY (M), WARANGAL DISTRICT
+160.395 +160.440 +160.395
3210 3180 6616 PROPOSED OT SLUICE ON BHEEMGHANPUR APPROACH CHANNEL
TITLE
GENERAL PLAN & SECTIONAL ELEVATION OF OT AT 330 M. FROM
U/S HEAD WALL D/S HEAD WALL U/S WING WALL MAIN ROAD ON RIGHT SIDE OF APPROACH CHANNEL
Submitted Checked Checked Recommonded Approved By
OFFICE OF EXECUTIVE
ENGINEER, DIVISION NO.
1,JCR- DLIS, WGL. Astt.E.E/Asst.Eng. Dy.Executive Engineer. Executive Engineer Superintending Engineer
Sub Div No. Sub Div No. Div No.1 - JCR - DLIP -JCR-DLIP
PROPOSED OT SLUICE ON BHEEMGHANPUR APPROACH CHANNEL
DESIGN AT OT At Km. 330.000 M. FROM MAIN ROAD ON RIGHT SIDE OF APPROACH C
0
1) HYDRAULIC PARTICULARS Duty : 150 Ac / Cusec
Sl.No Description Units Parent Canal O.T
1 Ayacut. Acres 0 0
2 Discharge (Req). Cum 24.0000 0.1190
3 Discharge ( Des). Cum 26.0000 0.1190
4 Bed Width. m 12.000 0.450
5 Full Supply Depth. m 5.866 0.450
6 Free Board. m 0.450 0.000
7 Side Slopes I/O. 11/2:1 / 2:1 11/2:1 / 2:1
8 Bed Fall. 1 in 3000 1 in 1000
9 Velocity m/sec 0.428 0.75
10 Value of 'n' 0.025 0.018
11 Top width of Banks L/R 30.00 / 30.00 0.00 / 0.00
12 C.B.L. 161.070 161.040
13 F.S.L. 166.936 161.490
14 T.B.L. 167.386 161.490
15 G.L. 167.000 167.000
16 Depth of Cutting. m 5.930 5.960

2) DRIVING HEAD:
F.S.L in parent canal = 166.936 m
3/4 of F.S.D + CBL = 165.469 m
F.S.L. in offtake canal = 161.490 m
Driving head = 165.469 - 161.490
= 3.979 m
3) AREA OF VENTWAY:
Q = Cd A sqrt (2gh) for circular vent Cd = 0.75

Q = Cd A sqrt (2gh) for square or rectangle vent Cd = 0.62

where Q = OT Discharge = 0.119 Cumecs


h = Driving head considered = 3.979 m
A =
Cd = Coefficient of Discharge = 0.75

It is proposed to provide Circular vent


0.119 = 0.75 x A x sqrt 2x 9.81 x 3.979
A = 0.018

Provide 1 No circular pipe as diameter of


A = p/4 D2
D = Sqrt 0.018 / 0.7853982
= 0.151

So provide 1 vent pipe of 450 mm dia NP2 class for OT

Therefore vent provided = 0.159 >= 0.018 HENCE O.K

4) HOIST PLATFORM LEVEL (HPL) :

(A) Hoist platform level = Sill level + twice the height of gate + 0.3 + 0.15
Height of gate = 0.450 m
Hoist platform level = 161.040 + 2 x 0.45 + 0.3 + 0.15
= 162.390 m

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 20


FSL in parent canal = 166.936 m

(B) Hoist platform level = FSL + 0.30 1.200


= 166.936 + 0.30
= 167.236 m

C) Hoist platform level = TBL of main canal


167.386 m 0.45 0.60

Therefore provide hoist platform level(HPL) = 167.386 m 0.15

Provide width of platform = 1.050 m

Hoist platform level


5) LENGTH OF BARREL:
Length of pipe = 0.60 + 1.5 ( TBL/GL - U/S T.B.L ) + T.W.B.(L).
+ 2 x ( TBL/GL - D/S T.B.L. ) + 0.5
Assume Level of D/S head wall
= 161.490 m
To reduce the Barrel Length of D/S Head wall to be Raised 0.000 m
Length of pipe = 0.60 + 1.5 167.000 - 167.386 + 30.00
+ 2 167.000 - 161.490 + 0.5
Total Length of Pipe = 41.541 m
Providing 450 mm dia NP2 class pipes 2.50 m length
Err:509

6) PROTECTION WORK:
Provide 10m length of lining in CCM10 on D/ s of structure in the OT canal.
and the same for 5m length on either side of U/s transition to the sides of parent canal.

7) UPSTREAM TRANSITION:

The U/s platform Level = 167.386 m


The U/s wing wall top level = 167.386 - 0.800
= 166.586 m
The length of U/s transition (or) The Horizontal length of U/s sloped wing
= 1.5 ( U/S wing wall top Level - C.B.L )
= 1.5 166.586 - 161.070
= 8.273 say 8.28 m
Barrel width = 0.450 m
Providing length of transition 1 in 3 splay
Outer width of transition = Barrel width + 2 x horizontal length of U/s splay/3
= 0.450 + 2x 8.280 / 3
= 5.97 Say 6.00 m

8) DOWNS TREAM TRANSITION:

Barrel width = 0.450 m


Bed width of OT canal = 0.450 m
Providing length of transition 1 in 5 splay
The length of D/s transition(Abs) = 5 x 0.450 - 0.450
2
= 0.000 m

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 21


DESIGN OF HEAD WALL (U/S)
+ 167.386
Top Width. 0.60 m: W3 0.60
Height. 6.39 m:
Density of Concrete. :
2.40 T/Cum W4 W1
Density of Soil. :
2.10 T/Cum
Width of Rear Batter. 2.31 m: 6.391
Offset. 0.30 m: W2
Bottom Width. 2.91 m:
Foundation Thickness. 0.60 m:
Total Height. :
6.991 m
+ 160.995 0.30 2.31 0.60 0.30
Active Earth Pressure Coeff. 0.6 A 2.91
Pv : 0.0384 m + 160.395
Ph : 0.134 m B 3.51

STRESS TABLE
Max Min
Concrete 34.17 -2.753
Soil 28.727 2.861

Moment About "A"

Force(Tones)
Sl.No Description. L.A(m) L.A(m)
1 W1 = 0.60 X 6.39 X 2.4 9.203 - 2.61 24.019
2 W2 = 2.31 X 6.39 X 0.5 X 2.4 17.72 - 1.54 27.281
3 W3 = 2.31 X 6.39 X 0.5 X 2.1 15.5 - 0.77 11.935
4 Pv = 0.0384 X 6.39 X 6.39 X 2.1 3.293 - - -
5 Ph = 0.1340 X 6.39 X 6.39 X 2.1 - 11.49 2.556 29.376
∑Force. 45.712 ∑Moment. 92.611

∑Moment.
Leaver Arm. = ∑Force.

92.611
= 45.712
= 2.025 m

Base = 2.91 m

Base/2 = 1.46 m

Eccentricity (e). = Leaver Arm + Base / 2


= 0.57 m

Permissible Eccentricity(Base/6). = 0.485 m

Max.Comp.Stress. = (∑Force/Base Width)*( 1+ 6e/b)

45.712 6x 0.57
Max.Comp.Stress. = 2.910 x 1 + 2.91
= 34.17 t/Sqm.

45.712 6x 0.57
Min.Comp.Stress. = 2.910 x 1 - 2.91
= -2.753 t/Sqm.

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 3


Moment About "B"

Force(Tones)
Sl.No Description. L.A(m) L.A(m)
1 W1 = 0.60 X 6.39 X 2.4 9.203 - 2.91 26.780
2 W2 = 2.31 X 6.39 X 0.5 X 2.4 17.72 - 1.84 32.595
3 W3 = 2.31 X 6.39 X 0.5 X 2.1 15.5 - 1.07 16.586
4 W4 = 0.30 X 6.39 X 2.1 4.026 - 0.15 0.603
5 W5 = 3.51 X 0.60 X 2.4 5.054 - 1.76 8.869
6 Pv = 0.0384 X 6.99 X 6.99 X 2.1 3.941 - - -
7 Ph = 0.1340 X 6.99 X 6.99 X 2.1 - ### 2.796 38.458
∑Force. 55.440 ∑Moment. 123.891

∑Moment.
Leaver Arm. = ∑Force.

123.891
= 55.440
= 2.234 m

Base = 3.51 m

Base/2 = 1.76 m

Eccentricity (e). = Leaver Arm + Base / 2


= 0.479 m

Permissible Eccentricity(Base/6). = 0.585 m

Max.Comp.Stress. = (∑Force/Base Width)*( 1+ 6e/b)

55.440 6x 0.479
Max.Comp.Stress. = 3.510 x 1 + 3.51
= 28.727 t/Sqm.

55.440 6x 0.479
Min.Comp.Stress. = 3.510 x 1 - 3.51
= 2.861 t/Sqm.

Note: The Ground Level is higher than T.B.L the Canal Protion above T.B.L Should be
excavated to 2:1 Slope & Steps Should be Constructed for easy to Access to its Plotform
for Operation.

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 4


DESIGN OF WING WALL (U/S)
+ 166.586
Top Width. 0.50 m: W3 0.50
Height. 5.59 m:
Density of Concrete. :
2.40 T/Cum W4 W1
Density of Soil. :
2.10 T/Cum
Width of Rear Batter. 5.52 m: 5.591
Offset. 0.30 m: W2
Bottom Width. 6.02 m:
Foundation Thickness. 0.60 m:
Total Height. :
6.191 m
+ 160.995 0.30 5.52 0.50 0.30
Active Earth Pressure Coeff. 0.60 A 6.02
Pv : 0.0384 m + 160.395
Ph : 0.134 m B 6.62

STRESS TABLE
Max Min
Concrete 15.961 10.174
Soil 15.407 12.474

Moment About "A"

Force(Tones)
Sl.No Description. L.A(m) L.A(m)
1 W1 = 0.50 X 5.59 X 2.4 6.709 - 5.77 38.684
2 W2 = 5.52 X 5.59 X 0.5 X 2.4 37.01 - 3.68 136.074
3 W3 = 5.52 X 5.59 X 0.5 X 2.1 32.38 - 1.84 59.516
4 Pv = 0.0384 X 5.59 X 5.59 X 2.1 2.52 - - -
5 Ph = 0.1340 X 5.59 X 5.59 X 2.1 - 8.796 2.236 19.667
∑Force. 78.617 ∑Moment. 253.941

∑Moment.
Leaver Arm. = ∑Force.

253.941
= 78.617
= 3.23 m

Base = 6.02 m

Base/2 = 3.01 m

Eccentricity (e). = Leaver Arm + Base / 2


= 0.222 m

Permissible Eccentricity(Base/6). = 1.002 m

Max.Comp.Stress. = (∑Force/Base Width)*( 1+ 6e/b)

78.617 6x 0.222
Max.Comp.Stress. = 6.016 x 1 + 6.02
= 15.961 t/Sqm.

78.617 6x 0.222
Min.Comp.Stress. = 6.016 x 1 - 6.02
= 10.174 t/Sqm.

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 5


Moment About "B"

Force(Tones)
Sl.No Description. L.A(m) L.A(m)
1 W1 = 0.50 X 5.59 X 2.4 6.709 - 6.07 40.696
2 W2 = 5.52 X 5.59 X 0.5 X 2.4 37.01 - 3.98 147.176
3 W3 = 5.52 X 5.59 X 0.5 X 2.1 32.38 - 2.14 69.230
4 W4 = 0.30 X 5.59 X 2.1 3.522 - 0.15 0.528
5 W5 = 6.62 X 0.60 X 2.4 9.527 - 3.31 31.515
6 Pv = 0.0384 X 6.19 X 6.19 X 2.1 3.09 - - -
7 Ph = 0.1340 X 6.19 X 6.19 X 2.1 - ### 2.476 26.707
∑Force. 92.236 ∑Moment. 315.852

∑Moment.
Leaver Arm. = ∑Force.

315.852
= 92.236
= 3.424 m

Base = 6.62 m

Base/2 = 3.31 m

Eccentricity (e). = Leaver Arm + Base / 2


= 0.116 m

Permissible Eccentricity(Base/6). = 1.102 m

Max.Comp.Stress. = (∑Force/Base Width)*( 1+ 6e/b)

92.236 6x 0.116
Max.Comp.Stress. = 6.616 x 1 + 6.62
= 15.407 t/Sqm.

92.236 6x 0.116
Min.Comp.Stress. = 6.616 x 1 - 6.62
= 12.474 t/Sqm.

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 6


DESIGN OF HEAD WALL (D/S)

W6
0.99 + 161.490
Top Width. 0.60 m: W3 0.60
Height. 0.45 m:
Density of Concrete. :
2.40 T/Cum W4 W1
Density of Soil. :
2.10 T/Cum
Width of Rear Batter. 1.98 m: 0.450
Offset. 0.30 m: W2
Bottom Width. 2.58 m:
Foundation Thickness. 0.60 m:
Total Height. :
1.050 m
+ 161.040 0.30 1.98 0.60 0.30
Active Earth Pressure Coeff. 0.60 A 2.58 W5
Pv : 0.0384 m + 160.440
Ph : 0.134 m B 3.18

STRESS TABLE
Max Min
Concrete 1.950 1.712
Soil 3.203 2.871

Moment About "A"

Force(Tones)
Sl.No Description. L.A(m) L.A(m)
1 W1 = 0.60 X 0.45 X 2.4 0.647 - 2.28 1.475
2 W2 = 1.98 X 0.45 X 0.5 X 2.4 1.069 - 1.32 1.411
3 W3 = 1.98 X 0.45 X 0.5 X 2.1 0.935 - 0.66 0.617
4 W6 = 1.98 X 0.99 X 0.5 X 2.10 2.058 - 1.32 2.716
5 Pv = 0.0384 X 0.45 X 0.45 X 2.1 0.016 - - -
6 Ph = 0.1340 X 0.45 X 0.45 X 2.1 - 0.056 0.179 0.010
∑Force. 4.725 ∑Moment. 6.229

∑Moment.
Leaver Arm. = ∑Force.

6.229
= 4.725
= 1.318 m

Base = 2.58 m

Base/2 = 1.29 m

Eccentricity (e). = Leaver Arm + Base / 2


= 0.028 m

Permissible Eccentricity(Base/6). = 0.43 m

Max.Comp.Stress. = (∑Force/Base Width)*( 1+ 6e/b)

4.725 6x 0.028
Max.Comp.Stress. = 2.580 x 1 + 2.58
= 1.950 t/Sqm.

4.725 6x 0.028
Min.Comp.Stress. = 2.580 x 1 - 2.58

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 7


= 1.712 t/Sqm.

Moment About "B"

Force(Tones)
Sl.No Description. L.A(m) L.A(m)
1 W1 = 0.600 X 0.450 X 2.400 0.647 - 2.580 1.669
2 W2 = 1.980 X 0.450 X 0.500 X 2.4 1.069 - 1.620 1.731
3 W3 = 1.980 X 0.450 X 0.500 X 2.1 0.935 - 0.960 0.897
4 W6 = 1.980 X 0.990 X 0.500 X 2.1 2.058 - 1.620 3.333
5 W4 = 0.300 X 0.450 X 2.100 0.283 - 0.150 0.042
6 W5 = 3.180 X 0.600 X 2.400 4.579 - 1.590 7.280
7 Pv = 0.0384 X 1.050 X 1.050 X 2.1 0.088 - - -
8 Ph = 0.1340 X 1.050 X 1.050 X 2.1 - 0.310 0.420 0.130
∑Force. 9.659 ∑Moment. 15.082

∑Moment.
Leaver Arm. = ∑Force.

15.082
= 9.659
= 1.561 m

Base = 3.18 m

Base/2 = 1.59 m

Eccentricity (e). = Leaver Arm + Base / 2


= 0.029 m

Permissible Eccentricity(Base/6). = 0.53 m

Max.Comp.Stress. = (∑Force/Base Width)*( 1+ 6e/b)

9.659 6x 0.029
Max.Comp.Stress. = 3.180 x 1 + 3.18
= 3.203 t/Sqm.

9.659 6x 0.029
Min.Comp.Stress. = 3.180 x 1 - 3.18
= 2.871 t/Sqm.

OT R4 @ KM. 4.250 OF D1 OF SC Page No. 8