FINAL COMPLETION CERTIFCATE FOR 100% PAYMENT MILESTONE NLD

This is to certify that the following tasks related to Work Order # 161/13026876 Dated: 28.09.2019 has
been successfully completed by M/s kaliyangi construction pvt. ltd. NLDLM-CHAMBA SALUNI
S.
Description Activity UOM Qty Remarks
No
1 T&D Mtr. 3873 3873*2=7746 MTR (Blue-Green)
2 DIT Mtr. 3873
3 CHARGES FOR CIR POLE 7.5M SB NOS 25
4 BLOWING 24F UG Mtr. 4.114 4.114 INCL. Loop
5 24F STRINGING DONE Mtr. 0.655 0.655 INCL. Loop
6 CLOSURE,JOINT,OFC,24F(6LT X 8F) Nos. 2
7 PANEL,DISTRIBUTION,FIBRE,24T,MLT Nos 1
8 NP 2 MANHOLE NOS 7
9 BLOCK TYPE MANHOLE NOS 1
10 EARTHING NOS 25
11 GI Mtr. 18
12 CLAMP,POLE,(50/65/400);PN:PC/H150/65-400 Nos 25
13 CLAMP,LOOP;PN:LC/H150/65-400 Nos 1
14 D-SHACKLE, CS, 0.75T SWL-VK Nos 50
15 THIMBLE, CS, 0.75T SWL-ERT Nos 100
16 TURN BUCKLE,0.75T SWL-VK Nos 50
17 TERMINATING HELIX FOR 11.5MM OFC-ERT Nos 50
18 PROTECTIVE HELIX FOR 11.5MM OFC-ERT Nos 50
TERMINATION ASSEMBLY =4.769
The total continuous Aerial Cable length to be invoiced in for aerial route is 4.828 as detail given below:
(NLDLM-CHAMBA SALUNI) Aerial Cable length 0.655 KM OFC ARM.= 4.114 KM
TOTAL 4.769 METERS
HOTO Done. FAT submitted.
There is no 3rd Party Claim pending on the route
There is no deduction on 3rd party claim which is settled by HFCL
All labor law compliances and other statutory compliances fulfilled
The above route is successfully handover to RJIL and no work is pending on the route.
The above route is successfully handover to RJIL and no work is pending on the route.
(Name of Area Manager/EIC): (Name of CPH):
Signature: Signature:
Date: Date:

Quantity Certification Summary (QCS)


WO No: - 161/13026876 Link/Span IDs:-
WO Date: - 28/09/2019 Span/Route: - NLDLM-CHAMBA SALUNI
Type of Work: ADSSNLD LM SCOPE:- 4.587 KMS
This is to certify that following quantity pertaining to above mentioned Work Order and Link / Span ID of
M/s kaliyangi construction pvt. ltd., being invoiced as per details attached, has been completed.
S.
Description Activity UOM Qty Remarks
No
1 T&D Mtr. 3873 3873*2=7746 MTR (Blue-Green)
2 DIT Mtr. 3873
3 CHARGES FOR CIR POLE 7.5M SB / MID SPAN NOS 25
4 BLOWING 24F UG Mtr. 4.114 4.114 INCL. Loop
5 24F STRINGING DONE Mtr. 0.655 0.655 INCL. Loop
6 CLOSURE,JOINT,OFC,24F(6LT X 8F) Nos. 2
7 PANEL,DISTRIBUTION,FIBRE,24T,MLT Nos 1
8 NP 2 MANHOLE NOS 7
9 BLOCK TYPE MANHOLE NOS 1
10 EARTHING NOS 25
11 GI Mtr. 18
12 CLAMP,POLE,(50/65/400);PN:PC/H150/65-400 Nos 25
13 CLAMP,LOOP;PN:LC/H150/65-400 Nos 1
14 D-SHACKLE, CS, 0.75T SWL-VK Nos 50
15 THIMBLE, CS, 0.75T SWL-ERT Nos 100
16 TURN BUCKLE,0.75T SWL-VK Nos 50
17 TERMINATING HELIX FOR 11.5MM OFC-ERT Nos 50
18 PROTECTIVE HELIX FOR 11.5MM OFC-ERT Nos 50
TERMINATION ASSEMBLY =4828
*Only items applicable under current certification have to be mentioned above and Individual
items/activities for which rates are different, have to be mentioned separately. For.eg. Blowing for 96F &
288F shall be in separate line items.
OTDR Test Report (if Applicable) Submitted & Accepted: Yes
OFC Length as per OTDR: 24F ADSS: = 0.655 KM 24F OFC = 4.114

Certified By:-
Name of CCM/NLD CM: Name of SCH:
Signature Signature
(Name & Contact No.)

*Additional details or line items can be added by adding additional rows in the above table, if required
Final Completion Certificate NLD LM - BLOWING

This is to certify that the BLOWING related to Work Order # 161/13026876


dated 28.09.2019 has been successfully completed by M/s kaliyangi
construction pvt. Ltd. (NLDLM-CHAMBA SALUNI) The total continuous
route length of 2 ducts- BLOWING 24 F ADSS to be invoiced is 0.655 MTR
(K.M. as per MB Sheets) from under mention chain-age:

SN LENGTH INVOICED (MTR)


REMARKS

1 2.020 24F OFC ARM.


2 2.048 24F OFC ARM.
3 0.046 24F OFC ARM.
TOTAL 4.114

4 0.655 24F ADSS

TOTAL 4.769

 24 F ADSS OFC has been consumed for blowing as well as stringing

____________________________ _________________________________
(Name of Area Manager/EIC): (Name of CPH):

Signature: Signature:

Data: Date
Final Completion Certificate- DIT

This is to certify that the DIT related to Work Order # Work Order #
161/13026876 Dated: 28.09.2019 has been successfully completed by
M/s kaliyangi construction pvt. ltd. (NLDLM-CHAMBA SALUNI)
The total continuous route length of 2 ducts- DIT to be invoiced is 3.873
MTR (K.M. as per MB Sheets) from under mention chain-age:

Length
Chain age Invoiced
Sr. No From To (Meter) Remark
1 0 66 66
2 66 326 260
3 326 1176 850
4 1176 1917 741
5 1917 2975 1058
6 2975 3870 895
7 3870 3873 3
TOTAL 3873
Above mentioned gap has been excluded from invoice quantity.

_________________________________ _________________________________
(Name of Area Manager/EIC): (Name of CPH):

Signature: Signature:

Data: Date
Final Completion Certificate
This is to certify that OFC Splicing pertaining to Work Order
#161/13026876 Dated: 28.09.201 has been successfully completed by M/s
kaliyangi construction pvt. Ltd.(NLDLM-CHAMBA SALUNI)

Splicing
Splicing /
Termination Nos. of Earthling
Sr.No Chain age splice OFC Chain age Remarks
1 1 24 24 F NR FDP
2 2 24 24 F NR JC
3 3 24 24 F NR JC

TOTAL 24F * 3 NO ‘S= 72

Joint Closure: 2 Nos.

FDP: 01 Nos.
_______________________ _______________
(Name of Area Manager/EIC): (Name of CPH):

Signature: Signature:
Data: Date
Final Completion Certificate NLD Last Mile (Supply of NON FIM Material)

This is to certify that the following tasks related to Work Order #


161/13026876 Dated: 28.09.2019 has been successfully completed by M/s
kaliyangi construction pvt. ltd. (NLDLM-CHAMBA SALUNI). The following
NON FIM material has been supplied by M/s kaliyangi construction pvt. Ltd.

 “B” CLASS GI (ISI Mark GI Pipe 100 mm): 18 MTR


 PCC AS PER SPECIFICATIONS: 130 MTR
 DWC AS PER SPECIFICATIONS: 567 MTR

 POLE CLAMPS: 25 NOS (Including Pole Clamps; Loop


Clamps 1 & Joint Closure Clamps)

________________________ ______________________
(Name of Area Manager/EIC): (Name of CPH):

Signature: Signature:

Date: Date:

Signature:
Circle commercial lead
Date:-
Final Acceptance Certificate for OTDR NLD

This is to certify that the OTDR related to Work Order # 161/13026876


Dated: 28.09.2019 Route NLDLM-CHAMBA SALUNI has been successfully
completed in all respect by M/S kaliyangi construction pvt. Ltd. and
accepted.

Length of OFC as per the OTDR reading is as below

24F OFC : 4.114KM

24F STRINGING : 0.655KM

Name of Area Manager /Engineer-in-charge: Name of CPH:

Signature: Signature:
Date : Date :
FINAL ACCEPTANCE TEST CERTIFICATE

It is certified that the Route/Link Name: (NLDLM-CHAMBA SALUNI), HP for scope


3.873 KM (0.655 KM 24F ADSS) (4.114 KM 24F OFC ARM) wide WO Number
#161/13026876 Dated: 28.09.2019 issued to M/S kaliyangi construction pvt. Ltd. has
been completed in all respects and the Final Acceptance Test Certificate carried out
and completed successfully.

_________________________________ _________________________________
(Name of Area Manager / EIC): (Name of CPH):
Signature: Signature:

Date: Date:

_________________________________
(Name of Spread Construction Head):
Signature:
Date:
Final Completion Certificate NLD LM – STRINGING
This is to certify that the OFC STRINGING pertaining to Work Order # 161/13026876
Dated: 28.09.2019 has been successfully completed by M/s kaliyangi construction pvt.
ltd. (NLDLM-CHAMBA SALUNI)
POLE AERIAL
MB STRINGING NO OF
INSTALLATION LOOP
S. No. Sheet DISTANCE AERIAL REMARKS
LENGTH
No. FROM TO (MTR) LOOPS
(MTR)
1 HP1 MH P1 0 24F
2 HP1 P1 P2 27 24F
3 HP1 P2 P3 23.3 24F
4 HP1 P3 P4 22.5 24F
5 HP1 P4 P5 20.5 24F
6 HP1 P5 P6 22.3 24F
7 HP1 P6 P7 34.4 24F
8 HP1 P7 P8 20.5 24F
9 HP1 P8 P9 16 24F
10 HP1 P9 P10 21.3 24F
11 HP1 P10 P11 21.6 24F
12 HP1 P11 P12 18.8 24F
13 HP1 P12 P13 19.6 24F
14 HP1 P13 P14 14.3 24F
15 HP1 P14 P15 34.3 24F
16 HP1 P15 P16 20.5 47 47 24F
17 HP1 P16 P17 19.1 24F
18 HP1 P17 P18 22.3 24F
19 HP1 P18 P19 32 24F
20 HP1 P19 P20 16.4 24F
21 HP1 P20 P21 17 24F
22 HP1 P21 P22 28.3 24F
23 HP1 P22 P23 19 24F
24 HP1 P23 P24 30.5 24F
25 HP1 P24 P25 21.3 24F
26 HP1 P25 MH 65 24F
TOTAL 608 47 47
OFC Stringing
The total route length of 48 F ADSS STRINGING to be invoiced 0.655 KM. as per MB Sheets against under
mentioned chain-age:-

TOTAL STRINGING 24F =0.655 KM