Professional Documents
Culture Documents
2
Engineering Dynamics, Inc. Training Bangkok 2010
This project provides the general information for the SACS training. The material can be
used for basic and advanced SACS training seminar. All the data and drawings included
in this document are for training proposes only, and none of them can be used in any
real design project.
Structure
The training project is a four legged wellhead platform with four conductors and a two-
lever deck located in an unknown area with water depth of 79.5 meters, see drawings
included in this document.
Design codes
Design loads
Equipment loads:
There are four equipment skids on the decks and the locations are shown in Drawing
201. The weights of the equipment are listed in the following table.
Deck loads:
Live loads:
Design specification- 1
Engineering Dynamics, Inc. Training Bangkok 2010
Environmental loads:
Current:
Wind:
Wave:
Design specification- 2
Engineering Dynamics, Inc. Training Bangkok 2010
Earthquake:
Soil data:
The soil data used for this training project are made up data and they are not from any
soil report. The units of the data in the table is detailed as following:
Design specification- 3
Engineering Dynamics, Inc. Training Bangkok 2010
22.5 48.5
Z Q Z Q
0.0 0.0 0.0 0.0
39.37 1 39.37 1.25
0.0 5.47 9.22 11.04 16.00 16.40 19.14 21.87 22.27 48.50
Y P Y P Y P Y P Y P Y P Y P Y P Y P Y P
0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.334 5.02 0.631 16.76 0.331 16.76 0.331 12.57 0.331 12.57 0.323 18.27 0.323 10.27 0.331 25.15 0.673 23.27 0.673 26.27
0.701 5.02 0.796 16.76 0.496 17 0.496 12.57 0.496 12.57 0.484 18.27 0.583 20.26 0.496 25.15 1.012 23.27 1.012 26.27
0.74 5.02 0.894 16.76 0.594 17.33 0.594 12.57 0.594 12.57 0.583 18.27 0.709 20.7 0.594 25.15 1.213 23.27 1.213 26.27
2.16 5.02 2.16 16.76 0.709 17.57 0.709 12.57 0.709 12.57 0.709 18.27 2.16 20.86 2.16 25.15 2.16 23.27 2.16 26.27
2.16 17.57 2.16 12.67 2.16 12.57 2.16 18.27
Design specification- 4
Engineering Dynamics, Inc. Training 2011
In windows file explorer create a directory called “Training Project”, and a subdirectory called
“Structural Modeling”.
Launch SACS Executive and go to “SACS Settings\Units Settings” and set default units to
“Metric KN Force”. Then click on the “OK” button. See picture below.
Set current working directory to “Structural Modeling” and launch Precede program by
clicking on “Modeler”icon in “Interactive” window of Executive (See picture below).
Select “Create New Model” and click ok. Then select “Start Structure Definition Wizard”
and click ok.(See two pictures below).
Elevations:
Keep “Generate Seastate hydrodynamic data” checked to create hydrodynamic data, such as pile
and w.b overrides.
Legs:
Click on the “Legs” Tab to enter the data for the jacket legs.
Number of legs: 4
Leg type: Ungrouted
Leg spacing at working point: X1=15 m, Y1=10 m.
Row Labeling: Define the Row label to match the drawing
Pile/Leg Batter: Row 1 (leg 1 and leg 3, 1st Y Row) is single batter in Y
Row 2 (leg 2 and leg 4, 2nd Y Row) is double batter
(See picture below for the details of the input)
Conductors:
Click on the “Conductors” Tab and then click on “Add/Edit Conductor Data” to enter the data
for the conductors.
(See picture below for the details of the conductor data input)
Click-on “Apply” to create the leg/pile and conductor model as shown below.
Save model:
Go to File/Save As, click “O.K” from prompted window and give file name sacinp.dat_01.
The IDs will be moved to Defined Groups Window after properties are defined.
Click “LG1” from Undefined Groups window and then click on “Add” Tab to define the section
and material properties of LG1.This group is segmented and the data can be found in Drawing
101.
Segment 1: D =48.5in, T = 1.75in, Fy = 34.50 kN/cm2, Segment Length = 1.0 m
Segment 2: D =47.0in, T = 1.0in , Fy = 24.80 kN/cm2
Segment 3: D = 48.5in, T = 1.75in, Fy = 34.50 kN/cm2, Segment Length = 1.0 m
Member is flooded
The unit of each input filed can be modified to use available data. In the pictures below the unit
of Outside Diameter and Thickness are changed to English (in). The segment length will be
designed later. See the pictures below for the details of the LG1 group data input.
Repeat above to define LG2 and LG3 group, the data can be found in Drawing 101.
Define groupLG4,DL6, DL7, CON, PL* and Wishbone groups, find the section dimensions
from Drawing 101.
LG4 = 48.5”x1.75”
DL6 = 42”x1.5”
DL7 = 42”x1.5”
CON = 30”x1” flooded
PL* = 42”x1.5”
W.B. = 30”x1” flooded
Member groups defined at this time shall look like the following:
-------------------------------------------------------------------------------------------------------------
GRUP CON 76.200 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP DL6 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP DL7 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP LG1 48.500 1.750 20.007.72234.50 1 1.001.00 0.500F7.84901.00
GRUP LG1 47.000 1.000 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP LG1 48.500 1.750 20.007.72234.50 1 1.001.00 0.500F7.84901.00
GRUP LG2 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.00
GRUP LG2 119.38 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP LG2 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.00
GRUP LG3 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.00
GRUP LG3 119.38 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP LG3 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.00
GRUP LG4 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.8490
GRUP PL1 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP PL2 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP PL3 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP PL4 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP PL5 106.68 3.810 20.007.72224.80 1 1.001.00 0.500 7.8490
GRUP W.B 76.200 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
-------------------------------------------------------------------------------------------------------------
Go to “Display”> “Plan” and pick -79.5 to create the framing at the mudline elevation.The
Structural plan can be found in Drawing 103Plan @ EL (-) 79 500.
The model of the plan after built will be shown in the model plot Plan at EL-79.5
Go to “Display”>“Group Selection” to exclude Pile and Wishbone elements from the current
view. See picture below for details.
You should only see the joints on the jacket legs and conductors in the current view.
Exclude selected
groups from the view
Groups
selected
Uncheck here to
remove unattached
joints
The joint 1100, 1101 and 1102 can be added by divide member by ratio since the joints are at the
mid points of the beams.
You will be getting a new joint and two new elements, the original member 103L-104L has been
replaced by two new created members.
Joint 1103 and 1104 can be defined by using Divide by Distance based on the available
dimensions on Drawing 101.
Add a member connecting Joint 1101-1100, and define group label as “H12”.
Add the members connecting Joint 1101-1102, 1102-1100, 1104-1100 and 1101-1103, and
define group ID as “H13”.
Joint 1105 and 1106can be defined by using Divide by Length based on the available dimensions
on Drawing 101, same as Joint 1103 and 1104.
Use “Member”>“Divide”>“Length” to create Joint 1107, 1108, 1109 and 1110. The distances
can be found in the drawing, see pictures below for adding Joint 1107 and 1110.
Define the group properties to H11, H12, H13 and H14, the dimensions and material can be
found in the drawing. The pictures below show the sample of H11 and H12 definition.
Note that the unit of each input can be changed to match available data. The following pictures
show the diameter and thickness being changed to an English Unit so the data from the drawing
can be input directly. *Make sure units chosen are correct.
Repeat all the steps in Section 3 to create horizontal plans at elevation -50.0m, -21.0m and
2.0m.All the data and dimensions needed to build the model can be found in Drawings 102 and
103.The joint name and group ID can be found in model plots Plan at EL-50, Plan at EL-20 and
Plan at EL+2 PDF files.
Divide members 2107-2109, 2108-2110 by ratios to create joints 2111 and 2112;
Add members 2107-2108, 2109-2110, and 2111-2112 and then divide them by ratios to create
joint 2113, 2114, and 2115.
Use “Property”>“Member Group” to define the group property for the conductor guide frame.
The conductor and frame connection model is shown in the picture below.
Repeat the steps above to build the conductor connections at elevation -21.0 and 2.0.
Step 1:
Open sacinp.dat_03 with Precede and go to “Display”>“Face” and pick “Row A”.
Step 2
Go to “Display”>“Group Selections” to turn off the Pile and Wishbone elements from the
view.
Step 3:
Turn on the Joint and Group label by clicking on the “J” and “G” icon on the toolbar.
Step 4:
Step 5:
Step 6
Repeat Step 5 to build the X-brace between Elevation -21.0m and 2.0m.The new center joint
name should be 301X; group IDs should be BR5 for through members and BR6 for others.
The locations of center joints 101X, 201X and 301X are automatically calculated by the
program.
Step 7
Repeat Step 1 to Step 6 to build X-braces on Row B, Row 1 and Row 2; use same Group IDs and
the center joint ID starts from 102X on Row B, 103X on Row 1 and 104X on Row 2.
Step 8
Define the group properties for the X-brace members. BR1, BR3, and BR5 are through members
which are segmented. BR2, BR4, and BR6 are non-segmented members. The dimensions of all
members can be found in Drawing 101.
Go to “File”>“Structure Definition” and click on the “Deck Girders” Tab. Then click on
“Add/Edit Deck Girder Data”. You should see the following window below.
Deck elevation: select 15.30
Deck extension: input 4.0m at structure North and South
Click “Apply” or “OK” to apply to model. By clicking ok it will apply to the model and also
close out the structure definition box.
Step 3
Step 4
Change the member group ID to W01 and W02 as shown in model plot Plan at 15.3, go to
“Member” > “Details/Modify” and select the elements to change.
Step 5
The Member divide feature can be used to simplify modeling. Joint and group names should be
defined as shown in the model plot Plan at 15.3. The dimensions needed to build the model can
be found in Drawing 202. The functions recommended to build the frame model are:
“Member”>“Divide”>”Distance”
“Member”>“Divide”>”Ratio”
“Member” >“Divide”>”Perpendicular”
The new created joints naming should start from 7100.All the distances and ratios can be found
in the drawing. The conductor guide should be connected to the deck using dummy members.
This is the same as the ones in the jacket.
Step 6
Repeat Step 3 to Step 5 to build the frame in EL 23.00 plan, and the modeling results are
shownin the model plotPlan at 23.0.
Step 7
Define the properties for group W01 and W02; the sections should be selected from the AISC 9th
edition Library.
Click to
select
Section
from the Select wide
Library flange only
The above three pictures is a sample of how to define W01 (From Left to Right).Repeat it to
define the properties for W02.
Deck member groups defined at this time shall look like thefollowing:
-------------------------------------------------------------------------------------------------------------
GRUP W01 W24X162 20.007.72224.80 1 1.001.00 7.8490
GRUP W02 W24X131 20.007.72224.80 1 1.001.00 7.8490
-------------------------------------------------------------------------------------------------------------
Step 1
Include only the jacket in the current active window. Exclude the deck, piles, conductors, and
wishbone element from the current view.
Go to “Display”>“Group Selections” and exclude group PL1-PL5, W01, W02, CON, DL6-
DL7, and W.B. Check off “show unattached joints” and then click on “Apply”. Refer to the
picture below.
Step 2
Go to “Joint”> “Connection” > “Automatic Design”. Check the box “Offset braces to outside
of chord”. For “Gapping option” use “Move Brace”, and for “Brace Move” use “Along Chord”.
Set Gap = 5 cm and Gap size option to “Minimum only”. Select “Use existing offsets if gap
criteria is met”.
Under joint Can/Chord options select “Update segmented groups can lengths” and set “Can
length option” to “API minimum requirements”. Select “Increase joint can lengths only”, seee
above two pictures for the detail options to be selected and click on “Apply” to create the joint
can model.
The leg member’s segment lengths are automatically updated and the member end offsets of
each brace member are created automatically.
Step 3
Create dummy members to connect the guide joint to the framing joint created in last step. The
conductor and frame connection model is shown in the picture below.
Repeat the steps above to build the conductor connection elevation -21.0, 2.0 and 15.3.
The final updated Can length for legs shall look like the following:
-------------------------------------------------------------------------------------------------------------
GRUP LG1 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84902.10
GRUP LG1 119.38 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP LG1 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.76
GRUP LG2 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84902.16
GRUP LG2 119.38 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP LG2 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.63
GRUP LG3 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84902.33
GRUP LG3 119.38 2.540 20.007.72224.80 1 1.001.00 0.500F7.8490
GRUP LG3 123.19 4.445 20.007.72234.50 1 1.001.00 0.500F7.84901.60
GRUP LG4 123.19 4.445 20.007.72234.50 1 1.001.00 0.500 7.8490
-------------------------------------------------------------------------------------------------------------
Step 1
Go to “Display”>“Plan” and select plan at 15.3m. Exclude group DUM, W.B and CON from
current view.
Step 2
Step 3
Repeat above two steps to define the offset for the beams at Plan EL 23.00m.
Use “Property” > “K Factor” > “Ky” to modify Ky factor for H11 members in XY plane Z=-
79.50 m and H21 members in XY plane Z=-50.0 m
Use “Property” > “Effective Length” > “Ly” to modify Ly factor for H31 members in XY
plane Z=-21.0 m and H41 members in XY plane Z=2.0 m
Using “Weight” > “Surface Definition” input “CELLWT1” for Surface ID, pick up joint
71BD, 71ED, and 74BD for local coordinate joints. Input 0.5 for Tolerance, and pick up71BD,
71ED, 74ED and 74BD by holding CTRL key for Boundary joints. Select load direction to
“Members in local Y” and then click Apply to add this surface ID definition.
Using “Weight” > “Surface Definition” input “MAINWT1” for Surface ID. Pick up joint
81BD, 81FD and 84BD for local coordinate joints, input 0.5 for Tolerance, and pick 81BD,
81FD, 84FD and 84BD by holding CTRL key for Boundary joints. Select load direction to
“Local Y” and then click Apply to add this surface ID definition.
Step 3 Add weight group AREA by adding surface weight for deck
Using “Weight” > “Surface Weight” input AREA as Weight Group and AREAWT as Weight
ID, input weight pressure of 0.5 kN/m2 for the cellar deck and move CELLWT1 to “Included
Surface IDs” and click “Apply”. Then input a weight pressure of 0.75 kN/m2 for the main deck
and move MAINWT1 to “Included Surface IDs” and click “Apply”.
Add weight group LIVE by using surface weight feature as in step 3. Weight ID MAINLIVE
includes the main deck weight pressure of 5.0 kN/m2and ID CELLLIVE includes the cellar
deck weight pressure = 2.5kN/m2.
The added surface IDs and surface weights shall look like following:
-------------------------------------------------------------------------------------------------------------
SURFID CELLWT1 LY 71BD 71ED 74BD 0.500
SURFDR 71BD 71ED 74ED 74BD
SURFID MAINWT1 LY 81BD 81FD 84BD 0.152
SURFDR 81BD 81FD 84FD 84BD
SURFWTAREA 0.500AREAWT 1.001.001.00CELLWT1
SURFWTAREA 0.750AREAWT 1.001.001.00MAINWT1
SURFWTLIVE 2.500CELLLIVE 1.001.001.00CELLWT1
SURFWTLIVE 5.000MAINLIVE 1.001.001.00MAINWT1
-------------------------------------------------------------------------------------------------
Click Apply and the summation of forces will be shown on a pop-up window. To save the input
footprint weight select Keep.
Go to “Weight” > “Member Weight” and hold control key to select all members on the east
side of the decks, and enter the following data:
Go to “Weight” > “Member weight” and select the following members: 703L-74BD, 7102-
7103, 7106-7107, and then enter the following data:
Go to “Weight” > “Joint Weight” and pick up joint 501L, 502L, 503L and 504L, and enter the
following data:
Weight group: LPAD
Weight ID: PADEYE
Weight: 2.0kN
Check on “Include
buoyancy
Density: 7.849 ton/m^3
Step 5 Enter the walkway weight at boat landing elevation (EL 2.0m)
Go to “Weight” > “Member Weight” and pick all the members at EL 2.0 plan except the
wellbay members and then enter the data as following:
Go to “Display” > “Volumes” and select Type of volume to “Volumes to include”. Select joint
101L to get the min. Z-coordinate and select joint 301X to get the max. Z-coordinate, and then
click Apply. This will display only the part of jacket with anode protection.
Go to “Display” > “Group selection” to exclude group DUM, PL1-PL5, W.B, CON, H13-H14,
H23-H24 and H32-H33.This will exclude the wishbone, conductor, pile, and horizontal elements
from the current view.
Go to “Weight” > “Anode Weight” and drag a window to select all the members in the current
view and enter the data as following:
To create inertia loads from various weights defined on deck structure three steps need to be
performed:
Step 1
Step 2
Step 3
Weights defined on the jacket will be added to the environmental load conditions to account
forthe possible buoyancy and possible wave loads.
LOADCNEQPT
INCWGT EQPT
ACCEL 1.00000 N CEN1
LOADCNLIVE
INCWGT LIVE
ACCEL 1.00000 N CEN1
LOADCNMISC
INCWGT MISC
ACCEL 1.00000 N CEN1
-------------------------------------------------------------------------------------------------------------
Go to “Environment”>“Global
Parameters”>“Marine growth” to enter
the data shown in the picture on the right.
The added marine growth override lines shall look like following:
-------------------------------------------------------------------------------------------------------------
MGROV
MGROV 0.000 60.000 2.500 1.400
MGROV 60.000 79.500 5.000 1.400
------------------------------------------------------------------------------------------------------------
Go to “Environment”>“Global
Parameters”>“Member Group
Overrides”
Operating Storm (three directions considered: 0.00, 45.00, 90.00): load case P000, P045, P090
Jacket weight groups ANOD and WKWY should be included in all three load cases by using
“Environment” > “Loading” > “Weight” > “Include Weight Group” to account for weight,
buoyancy and wave/current loads.
The 3 operating storm load case lines shall look like following:
-------------------------------------------------------------------------------------------------------------
LOADCNP000
INCWGT ANODWKWY
WAVE
WAVE1.00STRE 6.10 12.00 0.00 D 20.00 18MS10 1
WIND
WIND D 25.720 0.00 AP08
CURR
CURR 0.000 0.514 0.000 -5.000BC LN
CURR 79.500 1.029
DEAD
DEAD -Z M BML
LOADCNP045
INCWGT ANODWKWY
WAVE
WAVE1.00STRE 6.10 12.00 45.00 D 20.00 18MS10 1
WIND
WIND D 25.720 45.00 AP08
CURR
CURR 0.000 0.514 45.000 -5.000BC LN
CURR 79.500 1.029
DEAD
DEAD -Z M BML
LOADCNP090
INCWGT ANODWKWY
WAVE
WAVE1.00STRE 6.10 12.00 90.00 D 20.00 18MS10 1
WIND
WIND D 25.720 90.00 AP08
CURR
CURR 0.000 0.514 90.000 -5.000BC LN
CURR 79.500 1.029
DEAD
DEAD -Z M BML
-------------------------------------------------------------------------------------------------------------
Extreme Storm (three directions considered: 0.00, 45.00, 90.00): load case S000, S045 andS090
Extreme storm load cases can be defined similar as the operating storm load cases, except 100-
year storm criteria are used to generate the environmental forces. Jacket weight groups ANOD
and WKWY should be included in all three load cases. The water depth should be overridden to
consider the high tide. The following pictures show the detailed input data from the
Specification.
The 3 extreme storm load case lines shall look like following:
-------------------------------------------------------------------------------------------------------------
LOADCNS000
INCWGT ANODWKWY
WAVE
WAVE1.00STRE 12.19 81.00 15.00 0.00 D 20.00 18MS10 1
WIND
WIND D 45.170 0.00 AP08
CURR
CURR 0.000 0.514 0.000 -5.000BC LN
CURR 81.000 1.801
DEAD
DEAD -Z 81.000 M BML
LOADCNS045
INCWGT ANODWKWY
WAVE
WAVE1.00STRE 12.19 81.00 15.00 45.00 D 20.00 18MS10 1
WIND
WIND D 45.170 45.00 AP08
DEAD
DEAD -Z 81.000 M BML
CURR
CURR 0.000 0.514 45.000 -5.000BC LN
CURR 81.000 1.801 45.000
LOADCNS090
INCWGT ANODWKWY
WAVE
WAVE1.00STRE 12.19 81.00 15.00 90.00 D 20.00 18MS10 1
WIND
WIND D 45.170 90.00 AP08
CURR
CURR 0.000 0.514 90.000 -5.000BC LN
CURR 81.000 1.801 90.000
DEAD
DEAD -Z 81.000 M BML
-------------------------------------------------------------------------------------------------------------
Six load combinations OPR1, OPR2, OPR3, STM1, STM2 and STM3 will be added into the
model. Three of them are corresponding to operating storms and the other three are
corresponding to extreme storms. Load factor of 1.1 will be used for environmental loads. The
live load will be included with a factor of 0.75 in extreme storm load combinations.
Go to “Load”>“Combine load conditions” to define the load combinations. The following two
pictures show the combinations of operating and extreme storm conditions.
Allowables can be increased by 1/3 based on API code, and this should be entered using the
AMOD line. Go to “Options” > “Allowable stress/Mat Factor” and enter the data as shown in
the picture below.
Add unity check partition line (UCPART). Go to “Options”>“Unity Check Ranges” and enter
the data as shown in the picture below.
The LCSEL, UCPART and AMOD lines shall look like following:
-------------------------------------------------------------------------------------------------------------
LCSEL ST OPR1 ORP2 ORP3 STM1 STM2 STM3
UCPART 0.5000.5001.0001.000300.0
AMOD
AMOD STM1 1.330STM2 1.330STM3 1.330
-------------------------------------------------------------------------------------------------------------
Section 1 Create the static analysis directory and separate the model file.
Under “Training Project”, create “Static” subdirectory; copy sacinp.dat_09 to the directory, and
make this directory current.
Open sacinp.dat_09 with Precede and then go to File/Save As and select “Model data only”, and
click-on “OK” to save the model file to sacinp.dat. See picture below.
Go to File/Save As and select “Seastate data only”, click-on “OK” to save the separated seastate
input file to seainp.dat. See picture below.
Click on “Analysis Generator” from the Executive window and select “Statics” for Type and “Static
analysis” for Subtype. See below picture for details.
Check and click on “Edit Environmental Loading Options” to active the Seastate program and get
the Seastate Analysis Options shown as below.
Select the option to match the definition in the picture below. Click on “O.K” to save the option.
Click on “Edit Element Check Options” to get the code check option window and set the options
Detailed as following:
Step 2 Select model input file, the model file is saved in step 2 of Section 1.
Type in or select
the file ID here
Click here to run
the analysis
Click here to
apply
GROUP III - UNITY CHECKS GREATER THAN 1.00 AND LESS THAN*****
MAXIMUM LOAD DIST AXIAL BENDING STRESS SHEAR FORCE SECOND-HIGHEST THIRD-HIGHEST
MEMBER GROUP COMBINED COND FROM STRESS Y Z FY FZ KLY/RY KLZ/RZ UNITY LOAD UNITY LOAD
ID UNITY CK NO. END N/MM2 N/MM2 N/MM2 KN KN CHECK COND CHECK COND
803L-8104 W01 1.064 OPR3 0.0 -5.42 -137.45 15.28 -5.12 230.20 18.9 64.6 1.001 OPR2 0.947 OPR1
804L-83FD W01 1.215 OPR3 0.0 0.01 -173.58 8.96 -3.80 241.87 18.9 64.6 1.189 OPR2 1.151 OPR1
8102-8103 W01 1.083 OPR3 5.0 -4.86 146.69 -7.64 0.01 160.96 18.9 64.6 1.077 OPR2 1.076 OPR1
8103-802L W01 1.632 OPR1 5.0 -5.17 -221.12 -14.84 -5.93 -503.48 18.9 64.6 1.556 OPR2 1.486 OPR3
8104-8105 W01 1.327 OPR3 5.0 -5.42 182.97 -7.16 0.09 204.14 18.9 64.6 1.302 OPR2 1.280 OPR1
8105-804L W01 1.903 OPR1 5.0 -5.29 -265.90 -8.30 -3.11 -609.63 18.9 64.6 1.864 OPR2 1.822 OPR3
802L-804L W02 1.760 OPR3 10.0 -2.24 -178.72 -6.53 -1.14 -606.86 38.5 132.5 1.726 OPR2 1.614 OPR1
8109-8111 W02 1.109 OPR1 2.0 0.03 178.92 2.95 -0.22 183.61 15.4 53.0 1.106 OPR2 1.097 OPR3
8111-8105 W02 1.041 OPR3 0.0 0.06 158.34 -9.82 4.71 -201.74 11.6 39.7 1.025 OPR2 1.023 OPR1
81BD-801L W02 1.836 OPR1 4.0 -0.01 -290.32 -9.73 -2.69 -786.05 15.4 53.0 1.824 OPR3 1.795 OPR2
-------------------------------------------------------------------------------------------------------------------
Step 1 Create a new folder and name it ‘Static PSI”, and then make it the current folder.
Copy SACINP.DAT and SEAINP.DAT files from ‘Static” directory to current folder.
Click-on “Data file” icon to launch Datagen program, and select “Create new data file” and
click-on OK to get the second window pop-up, as shown below; select “Pile Soil Interaction” as
the analysis type and make sure the unit is Metric KN. Click-on Select and skip the “Title” and
get next step to define the analysis options..
Leave default options for both “General” and “Output Options”, and click “Next”.
Engineering Dynamics, Inc. Training 2011
Click-on “No” to LCSEL and PILSUP cards. Click on “Yes” to PLTRQ card to get Plot Option
window and select the options shown below.
Click-on “Next” and select “Include all piles in plot”, select all load cases to be plotted. Do not
define plot size and specify pile section data until get Pile Group definition.
Define two pile groups and one conductor group, the pile group ID =”PL1” and “PL2”;
conductor group ID =”CND”. The first pile group segment length is 10m and second segment
has length of 30m with available end bearing area of 0.656m^2.
Engineering Dynamics, Inc. Training 2011
Click-on “More” to add the segments or groups, and click-on “Next” to finish the pile group
definition.
Click here to add more groups
Click here to get to next
Define the pile head joint, batter joint, pile group ID and soil ID as shown in following picture
for the four piles, and repeat to define conductors.
Click-on “More” to add a pile and click-on “Next” to finish the pile definition and get to next
step.
Engineering Dynamics, Inc. Training 2011
The header data defines the total number of soil strata, Z-factor, Soil ID and the maximum data
point of any T-Z curves. The data should be got from the Design Specification for this training,
and is shown in following picture.
Engineering Dynamics, Inc. Training 2011
This step defines the soil stratum information followed by soil data of each stratum (Step 10), the
data needs to be defined is number of point of the curve, stratum location and T factors;
following picture shows the stratum definition of the top soil.
The picture below will show up when finish the step 10. Click-on “Yes” to enter the Q-Z axial
header data.
Engineering Dynamics, Inc. Training 2011
Define the Q-T axial header data shown in below picture, click-on “Next” to accept the data and
get to soil stratum data.
Define the soil stratum data as shown in following two pictures and repeat it for all the stratums.
The torsional stiffness of the soil can be defined as linear spring, following two pictures gives the
detail of the input.
Engineering Dynamics, Inc. Training 2011
The P-Y data input is similar to Axial T-Z data, follow the direction of Step 7 to 10 and get the
data from the soil report to finish the input.
Following two pictures show the soil type selection and P-Y header definition.
Following two pictures show the stratum and soil data definition at 0.0m location, repeat the
input to define all the P-Y soils at rest locations.
Your current directory should have three input files: SEAINP.DAT containing the loading
condition, SACINP.DAT containing the model information includes the weight definition and
PSIINP.DAT containing the pile model information.
Engineering Dynamics, Inc. Training 2011
Click-on <Edit Environmental Loading Options> to get the window shown below and make
selections as shown in the window, click-on “OK” when finish; Click-on <Member code check
options> to define the code option shown in below window on right:
Override the report to include Joint deflection, Joint reaction, Member end forces and the UC
range report.
Engineering Dynamics, Inc. Training 2011
Select the input files as shown in below window and check the output file names, click-on “Run
Analysis” Tab to run the analysis.
Engineering Dynamics, Inc. Training 2011
Member code check results can be checked from post listing file or Postvue database, see below.
---------------------------------------------------------------------------------------------------------------
PSI SAMPLE ANALYSIS DATE 12-FEB-2011 TIME 16:10:54 PST PAGE 158
GROUP III - UNITY CHECKS GREATER THAN 1.00 AND LESS THAN*****
MAXIMUM LOAD DIST AXIAL BENDING STRESS SHEAR FORCE SECOND-HIGHEST THIRD-HIGHEST
MEMBER GROUP COMBINED COND FROM STRESS Y Z FY FZ KLY/RY KLZ/RZ UNITY LOAD UNITY LOAD
ID UNITY CK NO. END N/MM2 N/MM2 N/MM2 KN KN CHECK COND CHECK COND
102P-202P PL1 1.438 STM1 0.0 -77.40 -114.13 111.13 -144.24 165.19 81.9 81.9 0.694 STM2 0.632 STM3
103P-203P PL1 1.396 STM3 0.0 -84.84 -134.10 13.98 -18.21 187.41 81.5 81.5 0.751 STM2 0.733 STM1
104P-204P PL1 1.636 STM2 0.0 -97.92 -140.61 -12.02 15.35 199.60 81.9 81.9 1.454 STM1 1.179 STM3
803L-8104 W01 1.065 OPR3 0.0 -5.42 -137.51 15.34 -5.14 230.24 18.9 64.6 1.002 OPR2 0.948 OPR1
804L-83FD W01 1.215 OPR3 0.0 0.01 -173.57 8.95 -3.79 241.85 18.9 64.6 1.189 OPR2 1.150 OPR1
8102-8103 W01 1.083 OPR3 5.0 -4.86 146.66 -7.75 -0.03 160.83 18.9 64.6 1.078 OPR2 1.077 OPR1
8103-802L W01 1.633 OPR1 5.0 -5.18 -221.15 -14.97 -5.99 -503.52 18.9 64.6 1.557 OPR2 1.489 OPR3
8104-8105 W01 1.327 OPR3 5.0 -5.42 182.97 -7.23 0.08 204.19 18.9 64.6 1.302 OPR2 1.280 OPR1
8105-804L W01 1.902 OPR1 5.0 -5.29 -265.76 -8.28 -3.11 -609.48 18.9 64.6 1.863 OPR2 1.821 OPR3
802L-804L W02 1.758 OPR3 10.0 -2.24 -178.44 -6.55 -1.14 -606.56 38.5 132.5 1.724 OPR2 1.613 OPR1
---------------------------------------------------------------------------------------------------------------
Engineering Dynamics, Inc. Training 2011
---------------------------------------------------------------------------------------------------------------
PSI SAMPLE ANALYSIS DATE 12-FEB-2011 TIME 16:10:51 PSI PAGE 465
* * * P I L E M A X I M U M U N I T Y C H E C K S U M M A R Y * * *
PILE GRUP LOAD ******* PILEHEAD FORCES ******* * PILEHEAD DISPLACEMENTS * *********** STRESSES AT MAX. UNITY CHECK ************
JT. CASE AXIAL LATERAL MOMENT AXIAL LATERAL ROTATION DEPTH AXIAL FBY FBZ SHEAR COMB. UNITY
101P PL1 OPR1 -2045.22 173.63 386.2 0.16 1.90 0.001688 0.0 -25.00 18.47 -1.67 4.22 -43.54 0.268
OPR2 -1233.30 196.10 430.6 0.10 2.18 0.001947 10.4 -9.24 -26.42 -0.09 1.11 -35.66 0.219
OPR3 -2139.58 289.73 730.6 0.16 3.44 0.002927 0.0 -26.15 35.07 1.07 7.13 -61.23 0.365
STM1 3125.92 886.34 4514.2 -0.23 30.98 0.014261 0.0 38.20 216.77 2.46 20.44 254.99 1.071
STM2 5852.36 841.32 3848.9 -0.43 24.92 0.012223 0.0 71.52 184.68 7.58 18.66 256.36 1.110
STM3 2729.80 811.41 3849.2 -0.20 23.74 0.011847 0.0 33.36 184.85 0.85 18.91 218.21 0.917
102P PL2 OPR1 -4660.75 156.22 375.3 0.35 1.70 0.001471 0.0 -56.96 17.99 -1.04 3.89 -74.98 0.480
OPR2 -2774.74 183.64 411.1 0.21 2.04 0.001816 0.0 -33.91 19.71 -1.03 4.51 -53.65 0.334
OPR3 -703.99 263.77 615.9 0.06 3.11 0.002723 10.4 -5.38 -37.39 -0.04 1.52 -42.77 0.257
STM1 -9529.89 792.77 4871.0 0.71 30.61 0.015049 0.0 -116.47 233.62 -11.84 22.86 -350.39 1.536
STM2 -3152.27 775.31 3967.1 0.24 24.19 0.012492 0.0 -38.53 190.50 -2.44 19.83 -229.04 0.966
STM3 3864.15 793.62 3584.8 -0.28 21.89 0.011275 0.0 47.23 172.13 2.72 18.20 219.38 0.936
103P PL1 OPR1 -1876.81 176.84 395.9 0.14 1.93 0.001709 0.0 -22.94 -18.91 -1.95 4.30 -41.95 0.256
OPR2 -3830.00 198.40 499.9 0.29 2.14 0.001790 0.0 -46.81 -23.97 -1.22 4.91 -70.81 0.444
OPR3 -5919.23 255.29 688.1 0.44 2.95 0.002458 0.0 -72.34 -33.01 1.48 6.50 -105.39 0.664
STM1 3287.87 888.94 4526.0 -0.24 31.12 0.014285 0.0 40.18 -217.34 2.02 20.44 257.54 1.083
STM2 -3354.38 801.30 4291.3 0.25 26.45 0.013078 0.0 -41.00 -206.01 -5.25 20.58 -247.07 1.042
STM3 -10445.87 724.51 4122.7 0.78 23.08 0.012172 0.0 -127.66 -197.98 0.60 20.79 -325.65 1.446
104P PL2 OPR1 -4773.04 159.44 384.3 0.36 1.74 0.001498 0.0 -58.33 -18.43 -0.99 3.97 -76.79 0.491
OPR2 -5510.91 164.94 420.3 0.41 1.76 0.001470 0.0 -67.35 -20.18 0.18 4.13 -87.54 0.561
OPR3 -4560.62 249.15 641.6 0.34 2.89 0.002458 0.0 -55.74 30.72 -2.29 6.26 -86.55 0.540
STM1 -9635.55 793.07 4892.1 0.72 30.75 0.015100 0.0 -117.76 -234.65 -11.59 22.92 -352.69 1.546
Engineering Dynamics, Inc. Training 2011
STM2 -12057.11 724.89 4315.2 0.90 24.80 0.013054 0.0 -147.36 -207.23 -1.10 21.56 -354.59 1.583
STM3 -8787.05 717.25 3853.9 0.66 21.46 0.011596 0.0 -107.39 184.87 -8.78 19.98 -292.47 1.292
…
…
PSI SAMPLE ANALYSIS DATE 12-FEB-2011 TIME 16:10:51 PSI PAGE 480
* * * P I L E M A X I M U M A X I A L C A P A C I T Y S U M M A R Y * * *
PILE GRP ********* PILE ********* ************** COMPRESSION ************* **************** TENSION ***************
JT PILEHEAD WEIGHT PEN. CAPACITY MAX. CRITICAL CONDITION CAPACITY MAX. CRITICAL CONDITION *MAXIMUM*
O.D. THK. (INCL. WT) LOAD LOAD LOAD SAFETY (INCL. WT) LOAD LOAD LOAD SAFETY UNITY LOAD
CM CM KN M KN KN KN CASE FACTOR KN KN KN CASE FACTOR CHECK CASE
101P PL1 106.68 2.50 177.4 40.0 -57792.1 -2139.6 -2139.6 OPR3 27.01 58144.3 5852.4 5852.4 STM2 9.94 0.15 STM2
102P PL2 106.68 2.50 177.4 40.0 -57772.9 -9529.9 -9529.9 STM1 6.06 58125.1 3864.2 3864.2 STM3 15.04 0.25 STM1
103P PL1 106.68 2.50 177.4 40.0 -57792.1 -10445.9 -10445.9 STM3 5.53 58144.3 3287.9 3287.9 STM1 17.68 0.27 STM3
104P PL2 106.68 2.50 177.4 40.0 -57772.9 -12057.1 -12057.1 STM2 4.79 58125.1 0.0 0.0 OPR1 100.00 0.31 STM2
---------------------------------------------------------------------------------------------------------------
Face - ROW 1
Member Label= Group
Face - ROW 2
Member Label= Group
Face - ROW A
Member Label= Group
Face - ROW A
Member Label= Group
Face - ROW B
Member Label= Group
Face - ROW B
Member Label= Group
Plan at 2.000
Member Label= Group
Plan at 15.300
Member Label= Group
Plan at 23.000
Member Label= Group
Plan at -21.000
Member Label= Group
Plan at -50.000
Member Label= Group
Plan at -79.500
Member Label= Group
Plan at Z=-79.500
Member Label= Group