METHOD STATEMENT

FOR
INSTALLATION OF GENERATORS

 TABLE OF CONTENTS

1. INTRODUCTION AND SCOPE

2. APPLICABLE PROJECT SPECIFICATION

3. LOCATION OF ACTIVITY

4. HEALTH AND SAFETY

5. HEALTH AND SAFETY HAZARDS

6. OPERATION

7. INSTALLATION
8. FIXATION

9. RESPONSIBILITIES

10. MANPOWER REQUIRED

11. MATERIALS REQUIREMENTS

12. EQUIPMENTS REQUIREMENTS


13. WASTE MANAGEMENT
14. SPECIAL CONTROL MEASURES

15. SUPPORTING DOCUMENTATION

16. DISTRIBUTION
1. INTRODUCTION AND SCOPE
 This method of statement covers the off loading, storage and installation of
Generator Sets as defined in the General Specification.
 This procedure will define the method used to ensure that the Generator
Sets installation are correct and acceptable and shall conform to the
Contract Documents and Specification.

2. APPLICABLE PROJECT SPECIFICATION

 Section: GENERATORS

 Division: Installation

 Sub Division: Subdivision

3. LOCATION OF ACTIVITY
 Generator for the whole building .

4. HEALTH AND SAFETY


 Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials. Ensure all
involved personnel shall be aware of the same.

5. HEALTH AND SAFETY HAZARDS


 Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.

6. OPERATION
 Material: Material used will be as approved by the Engineer. The sizes
and routes routing will be as per the approved Shop Drawings.

 Storage and Protection: Deliver components parts to site, completely


identified in accordance with shop and certified CAD Drawings prepared
for this work. Store in accordance with the manufacturer’s instructions,
above ground, properly protected from the weather and construction
activities.

7. INSTALLATION
 Off-loading:
1. Use Mobile Crane to off-load the Generator Sets. Capacity of crane
shall be capable to carry the weight of the generator set. All safety
precaution shall be adhered during off loading.
2. Ensure the safety of equipments and workers.
3. Off load the Generator sets on the designated off loading area. Make
sure that the Generator Set will seat on pipe rollers or wooden flanks.
4. If the Generator Room is not ready for generator set installation, proper
protection of Generator set shall be provided and cover it with
tarpaulin.
 Pre-Installation
1. All materials and documentation relevant to this particular section of
works shall be checked prior to the installation.
2. Make sure that the plinth is completed and painted and ready for final
installation of equipment.
3. Make sure that the generator room is clear and free of debris and
foreign materials.
4. Ensure that the access for generator set installation is free from
obstructions.
5. Make sure that supporting flanks, pipe rollers, chain blocks, hydraulic
jacks and other tools required for installation are in place.
 Installation
 It has been presumed that the Generator Rooms are ready for
permanent installation of the Generator Set.
1. Lift the Generator using mobile crane or portable hydraulic crocodile
jack. Place pipe rollers under the generator skid. Make sure that the
pipe rollers are properly set.
2. Once the generator set will sit on the pipe rollers, push in / pull in the
generator set inside the room. If required, use chain block to pull the
generator set. Make sure that the chain block is properly anchored and
properly set to the direction of generator position.
3. Where in a generator set crosses a trench or unequal elevation, use
steel channels or I- beams to support the pipe rollers. Make sure that
the steel channels or I-beams are properly supported to carry the
weight of the Generator set.
4. Set the Generator set in proper location. Lift the Generator set using
portable crocodile hydraulic jack and let it sit on elevated flanks or I-
beams.
5. Fix the spring vibration isolator. Ensure that it is fixed and aligned
properly.
6. Lift the Generator set and install the spring vibration isolator. Bolt and
tight properly the Generator base on to the spring vibration isolators.
7. Associated work related to the Generator set such as generator
exhaust system, fuel system, acoustic lining etc, will commence.
8. After completing all associated works related to the Generator set,
raise a Request for Inspection for Generator Installation.
8. FIXATION
 Inspection, testing and commissioning:
1. Test the Generator in accordance to specification and manufacturer
recommendation.
2. All testing will be carried out in the presence of Consultant.
3. Test shall be carried out by the manufacturer’s testing engineers.
4. All test sheet shall be certified by the manufacturer representative.

9. RESPONSIBILITIES

 PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.

2. To ensure that the progressing of works is carried out according


to the planned program and as per the approved method of
statement.

3. To ensure that all the equipment and material required


executing the work are available according to the planned
construction program.

4. To co-ordinate with the Main contractor, MEP coordinator,


Safety Officer for a safe and proper execution of the works.

 SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.

2. To provide all necessary information and distribute


responsibilities to his construction.

3. To monitor the progress of work in relation with the work


program and to report to the Project Manager.

4. To co-ordinate with the safety officer and to ensure that the


works are carried out in safe practicing method.

 FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.

2. To ensure that his assistant foreman/ charge hand are aware of


the job requirements and they have enough information to carry
out their duties properly.

3. To ensure that the daily work is progressing as planned and


advice the site engineer of any requirement for additional
resources.

4. To ensure in consultation with the site engineer that the


manpower involved in the works are moving as agreed and
planned for the work.

5. To control disposal of waste materials according to the


instructions received from the site engineer.

6. To ensure full coordination with the safety officer to maintain


safe working and proper house keeping of the site, following the
proved safety measures and further ensure that all his working
team are aware of the same to prevent accident and losses.

7. To inform the site engineer regarding areas ready for inspection.

8. Foreman and the storekeeper are responsible for the distribution


and control of materials.

 SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.

2. Ensure all the implemented safety measures are adequate to


maintain safe working on the site.

3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.

10. MANPOWER REQUIRED


 Charge hand and Experienced Technicians
11. MATERIALS REQUIREMENTS
 Generator and its accessories.

12. EQUIPMENTS REQUIREMENTS


 The equipments that will be engaged for Generator Installation will be as
follows:

1. Hand Tools

2. Power Tools (if required)

3. Diagonal-Cutting Pliers

4. Wire Stripper/Cutter with Spring

5. Side-Cutting Pliers

6. Shank Screwdriver/Flat screw driver

7. Compression lug crimp tool

8. Necessary conduit for System Cabling

9. Knock out set (for conduit)

10. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves


& safety vest )

13. WASTE MANAGEMENT


 The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.

14. SPECIAL CONTROL MEASURES


 The following general control measures against Safety, Environment and
Quality shall be required for our scope of work and special control
measures are not applicable for us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made
available to site.
 All workers doing the work shall be briefed on this method statement
and risk assessment.

15. SUPPORTING DOCUMENTATION


 This method Statement should be read in conjunction with the below
referenced documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.

16. DISTRIBUTION
 Copy of this method statement shall be issued to the following for
information/ action/ comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer