Report on BBD test and Roughness Survey for Consultancy Services for preparation of

Detailed Project Report for formation of Radial Road No. 20 in Hyderabad


.

PHOTOGRAPHS

Photograph-1: BBD Test under Progress – Nagole to Korremula, Radial Road No. 20, Left Carriageway

Photograph-2: BBD Test under Progress, Nagole to Korremula, Radial Road No. 20, Left Carriageway
Report on BBD test, Roughness Survey and preparation of overlay thickness along with crust design
from km.493/0 to km.524/0 on Pune - Hyderabad section of NH-65.

Photograph-3: BBD Test under Progress – Nagole to Korremula, Radial Road No. 20, Right Carriageway

Photograph-4: BBD Test under Progress, Nagole to Korremula, Radial Road No. 20, Right Carriageway
Report on BBD test, Roughness Survey and preparation of overlay thickness along with crust design
from km.493/0 to km.524/0 on Pune - Hyderabad section of NH-65.

Photogrpah-5: BBD Test Pit at km. 0.400 (Nagole to Korremula, Radial Road No. 20, Left Carriageway)
for Pavement Layer Thickness and Subgrade soil sample collection

Photogrpah-6: BBD Test Pit at km. 1.400 (Nagole to Korremula, Radial Road No. 20, Left Carriageway)
for Pavement Layer Thickness and Subgrade soil sample collection
Report on BBD test, Roughness Survey and preparation of overlay thickness along with crust design
from km.493/0 to km.524/0 on Pune - Hyderabad section of NH-65.

Photogrpah-7: BBD Test Pit at km. 1.000 (Nagole to Korremula, Radial Road No. 20, Right Carriageway)
for Pavement Layer Thickness and Subgrade soil sample collection

Photogrpah-8: BBD Test Pit at km. 2.000 (Nagole to Korremula, Radial Road No. 20, Right Carriageway)
for Pavement Layer Thickness and Subgrade soil sample collection
Report on BBD test, Roughness Survey and preparation of overlay thickness along with crust design
from km.493/0 to km.524/0 on Pune - Hyderabad section of NH-65.

Photogrpah-9: Preparation for Bump Integrator Test under Progress

Photogrpah-10: Bump Integrator Test under Progress


Report on BBD test, Roughness Survey and preparation of overlay thickness along with crust design
from km.493/0 to km.524/0 on Pune - Hyderabad section of NH-65.

Photogrpah-11: Bump Integrator Test under Progress

Photogrpah-12: Bump Integrator Test under Progress