MONITORING SHOP DRAWING

MVAC
HOTEL INDIGO SEMINYAK - BALI
TANGGAL 20-01-2015

DRAWING STATUS

NO. DRAWING NO. DRAWING TITLE Isued Rev-1 Rev-2 Rev-3 Keterangan

No.Surat Kirim Kembali Status No.Surat Kirim Kembali Status No.Surat Kirim Kembali Status No.Surat Kirim Kembali Status

1 SD/FAF.01/A Building A1 Ground Floor Fresh Air Fan Installation Plan OPS/003/IDG. 12.11.2014 14.11.2014 AWN
2 SD/FAF.01.1/A Building A1 Ground Floor Fresh Air Fan Installation Section-A SD.AC/11/14 12.11.2014 14.11.2014 APP
3 SD/FAF.01.2/A Building A1 Ground Floor Fresh Air Fan Installation Section-B 12.11.2014 14.11.2014 APP

4 SD/AC.01/SK Typical Superior King MVAC Installation Plan OPS/001/IDG. 10.11.2014 18.11.2014 Revisi OPS/005/IDG. 15.11.2014 18.11.2014 Revisi OPS/006/IDG. 27.11.2014 06.12.2014 AWN
5 SD/AC.01.1/SK Typical Superior King MVAC Installation Detail SD.AC/11/14 10.11.2014 18.11.2014 Revisi SD.AC/11/14 15.11.2014 18.11.2014 Revisi SD.AC/11/14 27.11.2014 06.12.2014 AWN
6 SD/AC.01.2/SK Typical Superior King MVAC Installation Section-A 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 AWN
7 SD/AC.01.3/SK Typical Superior King MVAC Installation Section-B 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 AWN
8 SD/P.AC.01/SK Typical Superior King Piping AC Installation Plan 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 Revisi OPS/018/HI 03.12.201406.12.2014 APP
S.SD.AC/12/
9 SD/P.AC.01.1/SK Typical Superior King Piping AC Installation Detail 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 Revisi 14 03.12.2014
06.12.2014 APP

10 SD/PAC.01/A Building A Ground Floor Piping AC Installation Plan (Typical For 1st Floor - 3rd Floo OPS/007/IDG. 20.11.2014 24.11.2014 AWN
11 SD/PAC.02/A Building A Roof Top Piping AC Installation Plan SD.AC/11/14 20.11.2014 24.11.2014 AWN

12 SD/GR.01/TR Typical Room Grille OPS/009/HIS.S 21.11.2014 26.11.2014 APP


D.AC/11/14

13 SD/MVAC.05/A Buiding A1 Roof Top Exhaust Fan Installation Plan OPS/004/HIS.S 13.11.2014 17.11.2014 Revisi OPS/006/HIS. 19.11.2014 21.11.2014 Revisi OPS/010/HIS. 22.11.2014 25.11.2014 APP
12 SD/MVAC.05.1/A Buiding A1 Roof Top Exhaust Fan Installation Section-A D.AC/11/14 13.11.2014 17.11.2014 Revisi SD.AC/11/14 19.11.2014 21.11.2014 APP SD.AC/11/14

13 SD/MVAC.05.2/A Buiding A1 Roof Top Exhaust Fan Installation Section- B 13.11.2014 17.11.2014 Revisi 19.11.2014 21.11.2014 APP

16 SD/MEP.04/C Roof Top Building C MEP Installation Plan OPS/013/HIS.S 01.12.2014 08.12.2014 AWN
17 SD/MEP.04.1/C Roof Top Building C MEP Installation Section-A D.AC/11/14 01.12.2014 08.12.2014 APP
18 SD/MEP.04.2/C Roof Top Building C MEP Installation Section-B 01.12.2014 08.12.2014 APP
19 SD/MEP.04.3/C Opeining Roof Top Building C Plan

20 SD/AC.01.1/C Office Ground Floor Building C MVAC Installation Plan OPS/014/HIS.S 03.12.2014 11.12.2014 AWN
D.AC/12/14

21 SD/OP.01/A Opening Roof u/ Installation MEP Plan OPS/008/HIS.S 21.11.2014 25.11.2014 AWN OPS/011/HIS. 27.11.2014 08.12.2014 AWN
22 SD/OP.01.1/A Opening Roof u/ Installation MEP Section-A D.AC/11/14 21.11.2014 25.11.2014 AWN SD.AC/11/14 27.11.2014 08.12.2014 APP
23 SD/OP.01.2/A Opening Roof u/ Installation MEP Section-B 21.11.2014 25.11.2014 AWN 27.11.2014 08.12.2014 APP
24 SD/MEP.01/A Roof Top Building A MEP Installation Plan 27.11.2014 08.12.2014 AWN

25 SD/PAC.01/C Building C Ground Floor Piping AC Installation Plan OPS/016/HIS.S 04.12.2014 13.12.2014 AWN
26 SD/PAC.02/C Building C 1st Floor Piping AC Installation Plan (Typical for 2nd & 3rd Floor) D.AC/12/14 04.12.2014 13.12.2014 APP
27 SD/PAC.03/C Building C Roof Top Piping AC Installation Plan 04.12.2014 13.12.2014 APP

28 SD/AC.01/DR.B Dinning Room Buidong B Ground Floor AC Installation Plan OPS/019/HIS.S 09.01.2015
29 SD/AC.01.1/DR.B Dinning Room Buidong B Ground Floor AC Installation Section-A D.AC/01/15 09.01.2015

30 SD/AC.01/DR.NS Deluxe Room Non Standart AC Installation Plan OPS/020/HIS.S 12.01.2015 15.01.2015 AWN
31 SD/AC.01.1/DR.NS Deluxe Room Non Standart AC Installation Section-A D.AC/01/15 12.01.2015 15.01.2015 AWN
32 SD/AC.01.2/DR.NS Deluxe Room Non Standart AC Installation Section-B 12.01.2015 15.01.2015 AWN
MONITORING SHOP DRAWING
MVAC
HOTEL INDIGO SEMINYAK - BALI
TANGGAL 20-12-2014

DRAWING STATUS

NO. DRAWING NO. DRAWING TITLE Isued Rev-1 Rev-2 Rev-3 Keterangan

No.Surat Kirim Kembali Status No.Surat Kirim Kembali Status No.Surat Kirim Kembali Status No.Surat Kirim Kembali Status

1 SD/FAF.01/A Building A1 Ground Floor Fresh Air Fan Installation Plan OPS/003/IDG. 12.11.2014 14.11.2014 AWN
2 SD/FAF.01.1/A Building A1 Ground Floor Fresh Air Fan Installation Section-A SD.AC/11/14 12.11.2014 14.11.2014 APP
3 SD/FAF.01.2/A Building A1 Ground Floor Fresh Air Fan Installation Section-B 12.11.2014 14.11.2014 APP

4 SD/AC.01/SK Typical Superior King MVAC Installation Plan OPS/001/IDG. 10.11.2014 18.11.2014 Revisi OPS/005/IDG. 15.11.2014 18.11.2014 Revisi OPS/006/IDG. 27.11.2014 06.12.2014 AWN
5 SD/AC.01.1/SK Typical Superior King MVAC Installation Detail SD.AC/11/14 10.11.2014 18.11.2014 Revisi SD.AC/11/14 15.11.2014 18.11.2014 Revisi SD.AC/11/14 27.11.2014 06.12.2014 AWN
6 SD/AC.01.2/SK Typical Superior King MVAC Installation Section-A 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 AWN
7 SD/AC.01.3/SK Typical Superior King MVAC Installation Section-B 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 AWN
8 SD/P.AC.01/SK Typical Superior King Piping AC Installation Plan 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 Revisi OPS/018/HI 03.12.201406.12.2014 APP
S.SD.AC/12/
9 SD/P.AC.01.1/SK Typical Superior King Piping AC Installation Detail 10.11.2014 18.11.2014 Revisi 15.11.2014 18.11.2014 Revisi 27.11.2014 06.12.2014 Revisi 14 03.12.2014
06.12.2014 APP

10 SD/PAC.01/A Building A Ground Floor Piping AC Installation Plan (Typical For 1st Floor - 3rd Floo OPS/007/IDG. 20.11.2014 24.11.2014 AWN
11 SD/PAC.02/A Building A Roof Top Piping AC Installation Plan SD.AC/11/14 20.11.2014 24.11.2014 AWN

12 SD/GR.01/TR Typical Room Grille OPS/009/HIS.S 21.11.2014 26.11.2014 APP


D.AC/11/14

13 SD/MVAC.05/A Buiding A1 Roof Top Exhaust Fan Installation Plan OPS/004/HIS.S 13.11.2014 17.11.2014 Revisi OPS/006/HIS. 19.11.2014 21.11.2014 Revisi OPS/010/HIS. 22.11.2014 25.11.2014 APP
12 SD/MVAC.05.1/A Buiding A1 Roof Top Exhaust Fan Installation Section-A D.AC/11/14 13.11.2014 17.11.2014 Revisi SD.AC/11/14 19.11.2014 21.11.2014 APP SD.AC/11/14

13 SD/MVAC.05.2/A Buiding A1 Roof Top Exhaust Fan Installation Section- B 13.11.2014 17.11.2014 Revisi 19.11.2014 21.11.2014 APP

16 SD/MEP.04/C Roof Top Building C MEP Installation Plan OPS/013/HIS.S 01.12.2014 08.12.2014 AWN
17 SD/MEP.04.1/C Roof Top Building C MEP Installation Section-A D.AC/11/14 01.12.2014 08.12.2014 APP
18 SD/MEP.04.2/C Roof Top Building C MEP Installation Section-B 01.12.2014 08.12.2014 APP
19 SD/MEP.04.3/C Opeining Roof Top Building C Plan

20 SD/AC.01.1/C Office Ground Floor Building C MVAC Installation Plan OPS/014/HIS.S 03.12.2014 11.12.2014 AWN
D.AC/12/14

21 SD/OP.01/A Opening Roof u/ Installation MEP Plan OPS/008/HIS.S 21.11.2014 25.11.2014 AWN OPS/011/HIS. 27.11.2014 08.12.2014 AWN
22 SD/OP.01.1/A Opening Roof u/ Installation MEP Section-A D.AC/11/14 21.11.2014 25.11.2014 AWN SD.AC/11/14 27.11.2014 08.12.2014 APP
23 SD/OP.01.2/A Opening Roof u/ Installation MEP Section-B 21.11.2014 25.11.2014 AWN 27.11.2014 08.12.2014 APP
24 SD/MEP.01/A Roof Top Building A MEP Installation Plan 27.11.2014 08.12.2014 AWN

25 SD/PAC.01/C Building C Ground Floor Piping AC Installation Plan OPS/016/HIS.S 04.12.2014 13.12.2014 AWN
26 SD/PAC.02/C Building C 1st Floor Piping AC Installation Plan (Typical for 2nd & 3rd Floor) D.AC/12/14 04.12.2014 13.12.2014 APP
27 SD/PAC.03/C Building C Roof Top Piping AC Installation Plan 04.12.2014 13.12.2014 APP

28 SD/AC.01/DR.B Dinning Room Buidong B Ground Floor AC Installation Plan OPS/019/HIS.S 09.01.2015
29 SD/AC.01.1/DR.B Dinning Room Buidong B Ground Floor AC Installation Section-A D.AC/01/15 09.01.2015

30 SD/AC.01/DR.NS Deluxe Room Non Standart AC Installation Plan OPS/020/HIS.S 12.01.2015


31 SD/AC.01.1/DR.NS Deluxe Room Non Standart AC Installation Section-A D.AC/01/15 12.01.2015
32 SD/AC.01.2/DR.NS Deluxe Room Non Standart AC Installation Section-B 12.01.2015