You are on page 1of 43

TUAS WRP

DTSS 2

Programme Speakers
3.00pm Registration
3.35pm Welcome Address Yong Wei Hin
Part A: Overview of Tuas Water Reclamation Plant  DTSS 2 Director, PUB
(TWRP)
3.45pm Part B: TWRP Implementation Updates Scott Trusler
TWRP Project Director, Jacobs
4.45pm Q&As
5.00pm Networking Session

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  1


TUAS WRP
DTSS 2

Industry Briefing
28 November 2018

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 


In case of an Emergency

East Wing

West Wing
(Registration/Security)

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  3


TUAS WRP
DTSS 2

Overview of Tuas Water Reclamation Plant
(part of DTSS Phase 2)
Yong Wei Hin
DTSS 2 Director, PUB

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 


Agenda

Safety Commitment
Overview of Tuas Water Reclamation Plant (TWRP)
Update on Project Progress

Tunnel Section of DTSS Phase 1 Concept Rendering of Tuas WRP

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  5


Safety Commitment

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  6


DTSS Phase 2 Safety Mission

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  7


Tuas WRP Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  8


DTSS Phase 2 Project Timeline

2016 2017 2018 2019 2020 2021 2022 2023 2024


Today

Consultant Tender
LINK
SEWERS Detailed Design

Construction

D&B Tender

TUNNELS
Design & Construction

Consultant Tender
TUAS Detailed Design
WRP
Construction

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  9


Overview of Tuas WRP

Tuas WRP

IWMF

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  10


Project Overview
1. Influent Pumping 
Stations
2. Liquids (Domestic and 
Industrial Used Water) 
Treatment Facilities
3. Biosolids Treatment 
Facility
4. NW and IW Storage 
& Pumping
5. Wet Weather Treatment
6. Admin/O&M with 
Visitor Gallery

Future Expansions

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 11


Preparation Works Status

Soil investigation  Route 2 bridge  Sitewide instrumentation & 


COMPLETED;  monitoring contract AWARDED
COMPLETED
Route 3 bridge
TO BE COMPLETED
by year end
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 12
TUAS WRP
DTSS 2

TWRP Implementation
Scott Trusler
TWRP Project Director, Jacobs

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  13


Agenda

Project Delivery Updates
• Contract Packages (Revised)
• Overall Programme Timeline Changes
• Scope & Tendering Requirements (Revised)
Key Takeaways • Pre‐Tender Qualification for Domestic Liquids
• Upcoming Tenders
• Resources

Raising the Bar – Safety
Project Overview • Safety Update
• Major TWRP Components
• Key Project Challenges

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 14


Ground Rules

NO QUESTIONS
or information 
related to ongoing 
INFORMATION  TWRP tenders.
SHARED Second
in this briefing / 
presentation is only  ACTUAL TENDER 
meant for your  INFORMATION
guidance and  for respective contracts 
planning purposes. shall be issued by the 
Board.

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 15


Raising the Bar – Safety 

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  16


Workplace Safety and Health 
Report: Jul to Sep 2018

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 17


Workplace Safety and Health 
Report: Jul to Sep 2018

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 18


TWRP Safety Requirements

02 ELECTRONIC  03 FALL REDUCTION
PERMIT TO WORK • Drones and laser scans
• Pre fabrication
• On site • Machine platform 
• Overlapping /  railings
conflicting
• Trends

04 SAFETY  05 SELECTION 
TRAINING  OF PPE
FACILITY 01 ACCESS CONTROLS
• Reduced lanyard 
• Who
• Enhanced training length
• Where
• Simulators • Cut‐resistant gloves
• Qualifications

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 19


Project Overview

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  20


Major TWRP Components
An illustration of the 
process flow

Industrial Water Plant

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 21


Key Project Challenges

03
06 Multiple 
overlapping 
Tight 
programme contracts

04 05 02
Constrained 
01 site Limited 
access
Safety
07
Manpower /  Interfaces
supply chain 
competition

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 22


Project Delivery Updates

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  23


Overall Programme Changes
2017 | 2018

Milestone 1 – September 2023


» Industrial used water influent pumping station and only industrial liquids 
modules commissioned and operational
Milestone 2 – August 2024
» Domestic used water influent pumping station and one‐half of liquids treatment 
stream commissioned and into production
» NEWater plant commissioned and into production
Milestone 3 – December 2025
» Completion and commissioning of whole of Tuas WRP (Phase 1)
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 24
Contract Packages (11 nos.)
No. Name Description Remarks
C1A Site Development Works • Temporary site wide support infrastructures and services • Award pending
• Permanent yard piping, utilities, 22 kV, port sewer, near‐shore 
outfall
C2A Influent Pumping Stations • Two coarse screen shafts, three pumping stations, rising mains • Tendering
• Two 66 kV substations
C3A Industrial Liquids Modules • Headworks, primary treatment and secondary treatment including  • Scope reduced
MBR
C3B Industrial Water Treatment • Tertiary treatment to produce Industrial Water • New contract

C3C Domestic Liquids Modules and  • Primary and secondary treatment including MBR, and NEWater  • Prior C3B added to 


NEWater production C3C
• Pre‐tender 
qualification added
• No scope change
C3D Product Water Storage and  • Storage and pumping of NEWater and Industrial Water • Schedule shifted
Pumping
C4A Biosolids and Digesters • THP, digestion, thickening, dewatering, solids conveyance • OCFs added

C5A Plant Monitoring and Control  • SCADA/PLC system with progressive buildout


System
C6A Administration and Operations  • Two separate buildings
Buildings
C6B Site Completion • Scope to be defined, includes roads, CCTV, main entrance and etc.

C6C Wet Weather Treatment Facility • Domestic used water overflow treatment and discharge


SAFETY ● SCHEDULE ● BUDGET ● QUALITY 25
Tendering and Construction  Milestone 1
Industrial Used 
Water 
Milestone 2
Domestic Used 
Water & 
Milestone 3
Completion of 
Testing and 

Timelines Commissioned NEWater 


Commissioned
Commissioning of 
TWRP

Today

May 2018 C1A – Site Development Works 

Sep / Oct 2018 C2A – Influent Pumping Stations Construct/Operate

Dec 2018 / Jan 2019 C3A – Industrial Liquids Modules Extended Commissioning

C3B – Domestic Liquids Module  ‐ Primary Construct/Operate

C3C – Domestic Liquids Module  ‐ Secondary and NEWater Construct/Operate

C3D – Product Water Storage and Pumping Construct/Operate

C4A – Biosolids and Digesters Construct/Operate

C5A – Plant Monitoring and Control System

C6A – Administration and Operations Bldgs

C6B – Site Completion
NOTE:
The dates are indicative. C6C –Wet Weather Treatment Facility

SAFETY ● SCHEDULE ● BUDGET ● QUALITY  26


Tendering and Construction Milestone 1 Milestone 2
Industrial Used 
Water 
Domestic Used 
Milestone 3
Completion of 
Water & NEWater  Testing and 

Timeline Commissioned Commissioned Commissioning of 


TWRP

2018
Today
May 2018 C1A – Site Development Works 

Oct 2018 C2A – Influent Pumping Stations Construct/Operate

Feb 2019 C3A – Industrial Liquids Modules Operate

Pre‐tender  C3B – Industrial Water Treatment Operate


qualification
Jan 2019 to Apr 2019 C3C – Domestic Liquids Modules and NEWater Construct/Operate

Q4 2019 C3D – Product Water Storage and Pumping Construct/Operate

Apr 2019 C4A – Biosolids and Digesters Construct/Operate

Q4 2019 C5A – Plant Monitoring and Control System

C6A – Administration and Operations Bldgs

NOTE: C6B – Site Completion

The dates are indicative.
C6C –Wet Weather Treatment Facility

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 27


Contract 3A:
Industrial Liquids Modules

Industrial Liquids 
Modules

Scope includes:
» Two liquids treatment modules
» Headworks, primary treatment tanks, 
secondary bioreactor and membrane tanks
» Ceramic and polymeric membranes
» Industrial water treatment – now tendered 
separately (C3B)
» Odour control facility

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 28


Contract 4A: 
Biosolids and Digesters

Scope includes:
» Biosolids building with space for future 
equipment
Biosolids  » Thermal hydrolysis pre‐digestion, centrifuges 
for pre‐dewatering and thickening
Facilities
» 10 silo digesters – potential construction with 
post‐tensioned precast panels
» Majority of the IWMF interfaces
» Food waste and greasy waste receiving and 
treatment
» Odour control facilities

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 29


Contract 3C: Entire Domestic 
Liquids Modules & NEWater

Domestic Liquids 
Modules Scope includes:
» Two liquids treatment modules
» Headworks, primary treatment tanks,
secondary bioreactor and membrane 
tanks
» Polymeric MBR membranes
» NEWater production
» Odour control facilities

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 30


Contract 3A:
Tendering Requirements – BCA 
C3A

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 31


Contract 3A, 3C & 4A:
Tendering Requirements – BCA 
Structure
» Prime w/ named ME11‐L5* (or higher) subcontractor 
» Consortium
○ Lead plus 1 or 2 members (3 parties maximum)
○ May require named ME11‐L5* (or higher) subcontractor IF no ME11‐L6* member
ME11‐L5* means ME11‐L5 with min. paid‐up capital and min. net worth of $1.5 million 
(equivalent to Mechanical Engineering L6 financial grade)
ME11‐L6* means ME11‐L6 with min. paid‐up capital and min. net worth of $15 million 
(equivalent to Civil Engineering A1 financial grade)

Prime or Consortium Lead
» CW01‐A1
» CW02‐A1
Consortium
» Members may be CW01‐A1, CW02‐A1, or ME11‐L6*
» Consortium parties must be exclusive
» Joint and Several – all parties
SAFETY ● SCHEDULE ● BUDGET ● QUALITY 32
Examples

CONSORTIUM
PRIME WITH  CONSORTIUM
ME11‐L6* LEAD
SUBCONTRACTOR (No Subcon Req’d)
Not Allowed

CW02 – A1 CW01 – A1 ME11 – L6*

CW02 – A1
CW02 – A1 ME11 – L6*

ME11 – L5* 
ME11 – L6

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 33


Pre‐Tender Qualification (PTQ) 
for Domestic Liquids

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 35


Contract 3C: 
PTQ Requirements – BCA
Structure
» Prime* 
» Consortium*
*Note: Subcontractors must be named and only Applicant(s) shall provide detailed information

Prime or Consortium Lead
» CW01‐A1
» CW02‐A1
Consortium Applicants
» May be CW01‐A1, CW02‐A1, or ME11‐L6*
» Consortium parties must be exclusive

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 36


Contract 3C: PTQ Criteria

CRITICAL CRITERIA
OTHER CRITERIA OTHER CRITERIA OTHER CRITERIA

BCA Registration Track Record Personnel & Organisation Approach & Scope 


of Appreciation
Safety, Debarment Record Certified HSE policy  Staff proposed for the work
and track record Understanding of the 
Performance of the work project and requirements
Safety, ISO Certifications Large, complex WRP
projects and processing  Response to specific 
Necessary resources to support  topics
plants and facilities project

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 37


Contract 3C: 
PTQ and Tendering Timeline
Pre‐Tender 
Pre‐Tender  Qualification 
Qualification  Shortlist 
1 Calling 3 Notification

28 NOV JAN 2019 ‐ MAR ‐


APR 2019
FEB 2019 APR 2019

Industry  2 Pre‐Tender  4
Briefing Qualification 
Evaluation

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 38


Key Takeaways

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 39


Upcoming Tenders and 
Resources

UPCOMING TENDERS
01 C3C Pre‐tender qualification – Jan 2019 to Apr 2019
C3A Tender – Q1 2019
C3C Tender – Q3 2019
C4A Tender – Q2 2019 
C5A Tender – Q3 2019
C3D Tender – Q4 2019
DTSS 2 RESOURCES
02 Visit https://www.pub.gov.sg/dtss/phase2/resources for 
more information related to DTSS 2 projects

FOR ENQUIRIES
03 Use TWRP@jacobs.com mailbox for general 
enquiries

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 40


Q&As

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 41


Reminder: Ground Rules

NO QUESTIONS
or information to 
be asked pertaining 
INFORMATION  to ongoing TWRP 
SHARED Second tenders.
in this briefing / 
presentation is only  ACTUAL CONTRACT 
meant for your  INFORMATION
guidance and  shall derive from 
planning purpose. respective tender 
documents issued by 
the Board.

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 42


Thank you

SAFETY ● SCHEDULE ● BUDGET ● QUALITY 43