Professional Documents
Culture Documents
Content:
1) Objective
2) Machine startup procedure.
3) During running.
4) Machine shutdown procedure.
5) Hazard and control measure
6) Environment aspect impact and controls
7) Safety procedures
8) Safety rules and regulation
9) Emergency Contact Number
1. Objective:
This work instruction purpose is to provide information on how to promote proper
operating procedure, maintain the cleanliness of the factory, to provide information of
the hazard, control measure and environmental aspect, impact and control that are
associated in the production of stretch film. This document is generated to give warning to
the employee what are the safety procedure and safety rules and regulation to promote
positive health and safety culture.
Doc Ref. Issue No./Date Revision No./ Date Doc Prepared by: Authorized by:
na na 00 / NA Soumya OP
WORK INSTRUCTION Page 2 of 5
For Stretch Film Machine
DEPARTMENT PRODUCTION (STRETCH FILM) LOCATION FACTORY 1
NAME OF MACHINE COLLINES COUNTRY OF ORIGIN ITALY
3. During running:
Always checking raw material available in raw material container.
Always careful about machine parameters as well as water & air presser and
cooling temp. of water goes into different sections.
Always checking film thickness physically by thickness gauge and checking film
not fold or wrinkle and any puncture.
Checking always paper core available in core store draw in both winders.
Put proper core according to product running in winder like 2” &3” core diameter.
Doc Ref. Issue No./Date Revision No./ Date Doc Prepared by: Authorized by:
na na 00 / NA Soumya OP
WORK INSTRUCTION Page 3 of 5
For Stretch Film Machine
DEPARTMENT PRODUCTION (STRETCH FILM) LOCATION FACTORY 1
NAME OF MACHINE COLLINES COUNTRY OF ORIGIN ITALY
Doc Ref. Issue No./Date Revision No./ Date Doc Prepared by: Authorized by:
na na 00 / NA Soumya OP
WORK INSTRUCTION Page 4 of 5
For Stretch Film Machine
DEPARTMENT PRODUCTION (STRETCH FILM) LOCATION FACTORY 1
NAME OF MACHINE COLLINES COUNTRY OF ORIGIN ITALY
Environmental
Sl.# Environmental Impact Control Measures
Aspect
Depletion on natural
1 Use of electricity 1. Monitoring of electricity consumption
resources
Depletion on natural
2 Use of water 1. Monitoring of electricity consumption
resources
Spillage of 1. Emergency response procedure for spillage /
Contamination of land
3 materials (solid leakage implemented
and water
materials) 2. air drawing machine with filter provided.
Spillage of Contamination of land
1. Emergency response procedure for spillage /
4 materials (liquid and water cause of
leakage implemented
materials) leakage
7. Safety procedure:
1. always wear you uniform and personal protective equipment
2. always read production schedule, memo, manuals, work instruction and signage for your
information and safety.
3. Report any dangerous activity or dangerous situation to avoid any accident
4. Report to you immediate superior before and after shift
5. know the location of the emergency exits, fire extinguisher, manual call point, fire hose
reel, first aid box and emergency contact number.
Doc Ref. Issue No./Date Revision No./ Date Doc Prepared by: Authorized by:
na na 00 / NA Soumya OP
WORK INSTRUCTION Page 5 of 5
For Stretch Film Machine
DEPARTMENT PRODUCTION (STRETCH FILM) LOCATION FACTORY 1
NAME OF MACHINE COLLINES COUNTRY OF ORIGIN ITALY
Anyone violated the mention above and proven, employee will be evaluated subjected for
disciplinary action or dismissal
Local
Name Position Department Mobile Number
Number
Facility Control Maintenance &
Dirkie Decir 50313476 106
Engineer Service
Maintenance &
Mohammad Irshad Electrical Engineer 66878685 101
Service
Jed Ruthven F
HSE Officer HSE & Security 77983445 107
Briones
Mohammed First aider / Fire
Production 70799721 108
Shareef R.K. Warden
Soumya Ranjan First aider / Fire
Production 30997371 108
Dhupal Warden
Security 50612369 N/A
Doc Ref. Issue No./Date Revision No./ Date Doc Prepared by: Authorized by:
na na 00 / NA Soumya OP