Work Order/NTP
Subcontractor Project Work Instructions Received
1.
Engineer PO
Permit to Work
Accomplish the corresponding
Subcontractor Project Safe Work Permit form Hazards & Control
4. Supervisor (includes personnel assignment)
ASWP
JHA
Subcontractor Project Submit accomplished SWP with JHA &
5. SWMS to the Permit Issuer
Supervisor WMS
(Permit Issuer = GenCon Project
Engineer) Safe Work Permit
JHA
Subcontractor Project Discussion regarding the submitted SWP
and the corresponding JHA and other
6. Supervisor & Permit
attachments.
SWMS
Issuer
Safe Work Permit
SWP
Subcontractor Project Approved SWP and JHA/SWMS
7. Supervisor & Permit JHA / SWMS
Issuer
SWP/JHA/SWMS
8. Subcontractor Project
Coordinate with Site Foreman.
Supervisor/ Site Daily Work Clearance
Foreman