You are on page 1of 25

JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

This procedure is to review work steps and their associated hazards to put in place correct solutions to eliminate or minimize the risk.

MANPOWER REQUIRMENTS
Job Type Client: SABIC (HADEED) Area: SPLP II
FOR SPLP-II TA

Estimated
PO # 4801909235 1 WEEK
Duration:
Scope of Works PROVIDING MANPOWER FOR TA WORKS
Document
Mahammad Haneef Date Prepared: 30 May 2021
Prepared By:

Height
Manual Electrical/ Confined Hazardous Forklift Truck/ Mechanical
Work/ Cranes Lay down Area
Handling Instrument Space Substances Mobile Plant Work
Scaffold
Job
Yes No Yes No Yes No Yes No Yes No Yes No Yes No Yes No Yes No
Elements:

 ICMS HSE Plan and safety procedures are always to be followed:

 Minimum PPE to be worn at all times.


General  This JHA to be available at all points of work – operatives must be informed of this JHA and understand the risks involved in the works.
safety condition
requirements  Toolbox talk / pre-job brief to be given at the start of each work shift and before starting a new task or activity.

 Summer and Ramadan working hours changes are to be observed and details posted at worksite.

 Paramedical or ambulance facilities to be available.

Activity / Task Mechanical Technician New Revised


Job Steps (Sub-Task) 1. Mechanical Works
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

2. Site preparation and mobilization of personnel,


materials, and equipment’s.
3. Working Under Extreme Heat Environment, Heat Stress.
4. COVID-19 prevention and protection.
5. Working with hand and power tools, Power & Drill
Machine.
6. Conduct of Housekeeping

Job Step SN Initial Risk Residual Responsibility


Hazard’s Control Measures Risk
Probability Severity Risk Probability Severity Risk Responsible
Person

• Unauthorized commencement of L3 C4 4 • Authorized Work permit holder shall L3 C5 3


works. ensure to obtain and maintain valid
1. • Unavailability of Work permit Work permit (and other required and
required attached certificates for approved documents)
the job. • The supervisor responsible for this
activity must check all required
certificates, photography permit and
other documents are attached and
placed on worksites.
• To comply with all necessary
documentations and permit
requirements prior to commencement
of activities.

• Poor Communication. L3 C4 4 • Discussion of work steps/sequences to L3 C5 3


all work members (with translation-if
possible) before the actual Activity
• Maintain and establish good
coordination and communication
between team members
• Shall have proper approval and
communication from Roots PMT,
Hadeed Focal Point and Station Permit
Authority/Controller for the activity

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

• Exposure to H2S L3 C4 4 • Ensure that no unauthorized personnel L3 C5 3


• Emergency in the working area.
• Personal H2S/Toxic Clip shall always be
worn.
• Ensure that all personnel should have a
valid H2S training ID Card.
• Ensure that gas testing done before
starting the activities.
• Ensure that all personnel fully
understand to raise alarm in event of an
emergency and all personnel are fully
aware the action to be taken in case of
emergency, the nearest muster point,
emergency number and the safe escape
route.

• Emergency response L3 C4 4 • Stop the work L3 C5 3


• Check wind direction
• Locate nearest Assembly point and
emergency exit
• Evacuate upside.
• Use H2S clip
• Inform Hadeed control room
• Use of emergency Hadeed number.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

2. • Heat stroke/Stress • To follow State Law for summer


L3 C4 4 L3 C5 3
• Cramps/ Heat Exhaust working hours, outdoor activities during
• Dehydration summer shall have break down as pe
• Poor ventilation procedure.
• Follow Hadeed HSE Heat Stress
Management Guidelines & OH(D) Heat
Stress Management Plan.
• Rest shelters to be provided.
• Welfare facilities to be provided.
• Cool drinking water igloos to be
provided.
• Toolbox talk to be conducted and
ensure all workers aware to response in
heat stress risks, If any worker feel
dizzy, has a headache, moist, pale skin
or weak.
• Schedule work/rest/drink water as per
heat index
• requirements/ regulations.
• Warning flags to be displayed at
frequent locations.
• Avoid dehydration: rest and drink water
frequently.
• Personal water flask to be provided.
• No plastic (fizzy drink) bottles to be
used, disposable plastic cups for
drinking water to be provided.
• No water no work rule to be
implemented shall implement and
follow up the Heat Stress Prevention
Check List, any failure can lead to
stop/suspend the work activity.
• Heat index to be monitored hourly and
recorded with a calibrated Anemometer
and documented.
• Follow the work ratio as per heat stress
prevention measures.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

3 • Biological Hazards L3 C4 4 • Ensure Temperature Screening for all L3 C4 3


• Cold & Flu Virus personnel involved of the activities.
• Ensure to check flu symptoms, fever,
cough, and shortness of breath
reported to immediate supervisor and
project management team.
• Ensure COVID-19 Mandatory PPE (mask,
disposable gloves, etc.) shall always be
worn.
• Keep working surfaces sanitized
• Avoid touching your face, your eyes and
mouth.
• Catch coughs and sneezes in a tissue.
Disposed of the tissue responsibly in
trash bin.
• Good Hygiene and clean environment
should be maintained. Wash your hands
frequently with soap and water and or
use hand sanitizers-alcohol.
• Maintain Social Distancing, minimum of
1.5 meter apart.
• Avoid direct contacts, no shaking hands
• Avoid spitting and direct contacts with
installation.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

4 • Finger injuries (pinch, nip points) L3 C4 4 • Only experienced and competent L3 C5 3


• Hand and body injuries personnel to do the installation and
witness by Hadeed representative and
to be done in accordance with stated
procedure on approved method
statement.
• Ensure no deviation on procedure
stated on approved method statement.
• Proper manual handling technique
should be observed.
• Ensure that all hand tools used are in
good condition
• Wear appropriate gloves while
installation.
• Inspection of hand tools for damages
before use
• Ensure that all hand tools used are in
good condition
• Defective tools shall be removed from
service

• Dropped objects leading to feet L3 C4 4 • Close supervision while doing the L3 C5 3


injuries installation.
• Ensure that tools are secured, use tools
belt while doing the activity.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

• Improper manual handling L3 C4 4  Use correct manual handling techniques L3 C5 3


 Maintain good coordination and
communication between team
members
 Access routes is clear from all potential
obstacles
 Do not place hands and fingers in trap
points
 Ensure adequate manpower for the job

• Slips/trips/falls L3 C4 4  Conduct walkways and access routes, L3 C5 3


access routes should be clear from all
potential obstacles
 Use appropriate means of accessing
areas which is difficult to reach
 Ensure hand and fingers away from
pinch points, sharp and protruding
objects.
 Good command from the Supervisor
 Ensure that all personnel will avoid
overreaching.
• Hand and finger injury.
L3 C4 4  Ensure De-termination, Removal of L3 C5 3
cables and cable glanding to be
Supervised by Site Supervisor and Site
Engineer
 Keep hand and finger away from trap
points, sharp and protruding objects.
 Wear appropriate type of gloves for the
activity.
• Hand and finger injury.  Inspect hand and power tools prior to
5 • Rotating tools parts – entanglement L3 C4 4 each use L3 C5 3
• Cuts, rush, bruises, electrocution,  All hand power tools shall be physically
• Flying debris/dust inspected and tested by competent
• Hand and eye injuries personnel
• Sharp edges  If using battery drills, ensure to remove
the battery before replacing or
installing new drill bits
 Ensure that only trained and
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

experienced personnel will operate the


drill
 Continuous training/awareness sessions
be conducted to all users and
Supervisors
 Install visual tags/labels for power
toolsas reminders on safe its safe use
 Never remove safety guard from
powers tools
 Do not rush is replacement of drill bits.
Do not take shortcuts
 Do not operate in wet or damp
environments
 User to be familiar with the safety
switch of each power tools
 Before servicing any power tools, such
as changing drill bits, saw blades, or
grinding wheels, you must unplug the
tools
 Damage tools or equipment’s shall be
removed from service and tagged”
Damage”
 Only appropriate tools shall be used for
the job. Do not use makeshift tools
 Ensure hands, feet and loose clothing
are kept clear from moving parts of the
drill.
 Ensure Drill bit is tightened, drill
checked properly
 Always maintain good housekeeping.
 Appropriate PPE for the task must be
used, such as eyeglasses, gloves, face
shields and earplug (as applicabel) shall
be available when using hand and
power tools

6 • Trips and falls/Sharp Objects L3 C4 4  All waste generated shall be contained L3 C5 4


and disposed off in designated waste
areas
 All materials shall be removed from the
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

site to a safe storage location


immediately after the work

Activity / Task Electrician New Revised


Job Steps (Sub-Task) 1. Electrician Works site preparation and mobilization of
personnel, materials, and equipment’s.
2. Working Under Extreme Heat Environment, Heat
Stress.
3. COVID-19 prevention and protection.
4. Installation of barricades around working area.
5. Working with Electrical Equipment’s Using Hand
tools, Testing equipment’s.
6. Conduct of Housekeeping

Job Step SN Initial Risk Residual Responsibility


Hazard’s Control Measures Risk
Probability Severity Risk Probability Severity Risk Responsible
Person

• Unauthorized commencement of L3 C4 4 • Authorized Work permit holder shall L3 C5 3


works. ensure to obtain and maintain valid
1. • Unavailability of Work permit Work permit (and other required and
required attached certificates for approved documents)
the job. • The supervisor responsible for this
activity must check all required
certificates, photography permit and
other documents are attached and
placed on worksites.
• To comply with all necessary
documentations and permit
requirements prior to commencement
of activities.

• Poor Communication. L3 C4 4 • Discussion of work steps/sequences to L3 C5 3


all work members (with translation-if
possible) before the actual Activity
• Maintain and establish good
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

coordination and communication


between team members
• Shall have proper approval and
communication from Roots PMT,
Hadeed Focal Point and Station Permit
Authority/Controller for the activity

• Exposure to H2S L3 C4 4 • Ensure that no unauthorized personnel L3 C5 3


• Emergency in the working area.
• Personal H2S/Toxic Clip shall always be
worn.
• Ensure that all personnel should have a
valid H2S training ID Card.
• Ensure that gas testing done before
starting the activities.
• Ensure that all personnel fully
understand to raise alarm in event of an
emergency and all personnel are fully
aware the action to be taken in case of
emergency, the nearest muster point,
emergency number and the safe escape
route.

• Emergency response L3 C4 4 • Stop the work L3 C5 3


• Check wind direction
• Locate nearest Assembly point and
emergency exit
• Evacuate upside.
• Use H2S clip
• Inform Hadeed control room
• Use of emergency Hadeed number.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

2. • Heat stroke/Stress • To follow State Law for summer


L3 C4 4 L3 C5 3
• Cramps/ Heat Exhaust working hours, outdoor activities during
• Dehydration summer shall have break down as pe
• Poor ventilation procedure.
• Follow Hadeed HSE Heat Stress
Management Guidelines & OH(D) Heat
Stress Management Plan.
• Rest shelters to be provided.
• Welfare facilities to be provided.
• Cool drinking water igloos to be
provided.
• Toolbox talk to be conducted and
ensure all workers aware to response in
heat stress risks, If any worker feel
dizzy, has a headache, moist, pale skin
or weak.
• Schedule work/rest/drink water as per
heat index
• requirements/ regulations.
• Warning flags to be displayed at
frequent locations.
• Avoid dehydration: rest and drink water
frequently.
• Personal water flask to be provided.
• No plastic (fizzy drink) bottles to be
used, disposable plastic cups for
drinking water to be provided.
• No water no work rule to be
implemented shall implement and
follow up the Heat Stress Prevention
Check List, any failure can lead to
stop/suspend the work activity.
• Heat index to be monitored hourly and
recorded with a calibrated Anemometer
and documented.
• Follow the work ratio as per heat stress
prevention measures.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

3 • Biological Hazards L3 C4 4 • Ensure Temperature Screening for all L3 C4 3


• Cold & Flu Virus personnel involved of the activities.
• Ensure to check flu symptoms, fever,
cough, and shortness of breath
reported to immediate supervisor and
project management team.
• Ensure COVID-19 Mandatory PPE (mask,
disposable gloves, etc.) shall always be
worn.
• Keep working surfaces sanitized
• Avoid touching your face, your eyes and
mouth.
• Catch coughs and sneezes in a tissue.
Disposed of the tissue responsibly in
trash bin.
• Good Hygiene and clean environment
should be maintained. Wash your hands
frequently with soap and water and or
use hand sanitizers-alcohol.
• Maintain Social Distancing, minimum of
1.5 meter apart.
• Avoid direct contacts, no shaking hands
• Avoid spitting and direct contacts with
installation.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

4 • Hand and body injuries L3 C4 4 • Maintain proper distances when L3 C5 3


installing barricade using safety cones.
• Close supervision by the Site Supervisor

• Keep hand and fingers away from trap


points. Ensure activity to be Supervised
by Site Supervisor and Site Engineer
• Keep hand and finger away from trap
points, sharp and protruding objects.
• Wear appropriate type of gloves for the
activity.

• Electric Shock – (Possible contact  Give emphasis on precautions with


5 with energized system) L3 C4 4 respect to inherent hazards nearby at L3 C5 3
the energized installation, panels and
equipment’s particularly on high
voltage hazards
 Never allow any team member to touch
or get near any energized, live/running
equipment and all personnel involved in
Verification & Energization and should
be aware of nearby running system.
 Close supervision from the Site
Supervisor and Site Engineers at all
times.
 Establish close communication to all
members.

• Working without PTW  To comply with all necessary


L3 C4 4 documentations and permit L3 C5 3
requirements prior to commencement
of activities

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

• Failure or Accidental System  Ensure that activities should be done by


Shutdown L3 C4 4 competent trained personnel with L3 C5 3
appropriate authorization involved in
the task and to the Batteries testing and
Verification & Engergization activities.
 Ensure that no unauthorized personnel
in the working area.
 Ensure that Equipment calibrated and
in good condition
 Ensure to use correct tools for the task.
 Verification & Engergization activities
on Batteries should be done as per
stated on approved method statement.
 Shall have proper approval by Permit
Authority/Controller for the Verification
& Engergization activities
 Follow battery manufacturer’s
recommended Verification &
Engergization procedure.
 Measure and record the voltage of each
battery cells before charging (also total
voltage and ambient & battery cell
temperature)
 Measure and record the voltage of each
battery cells during charging, as well as
total dc, current, AC ripple, ambient
temperature and battery temperature.
 Perform battery discharge test
according to battery manufacturer’s
discharge data.
• Electric shock  Check insulation of all electrical cords.
L3 C4 4 No exposed wires. L3 C5 3
 Remove any body accessories which
can be a conductor of electricity
 Only competent and authorized
Electricians to do the job under
supervision of Electrical
Supervisor/Engineer and in accordance
with approved method statement.
 Shall have proper approval by Permit
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

Authority/Controller for the testing and


Verification & Engergization activities
and Ensure that all electrical cabling
works are completed and inspected by
authorized QP personnel and QA/QC
Engineers
• Fire Explosion.  Suitable fire extinguisher (co2/dry
L3 C4 4 powder) & blanket should be available L3 C5 3
prior to carrying out testing works.

6 • Trips and falls/Sharp Objects L3 C4 4  All waste generated shall be contained L3 C5 3


and disposed off in designated waste
areas
 All materials shall be removed from the
site to a safe storage location
immediately after the work

Activity / Task Hydraulic Fitter New Revised


Job Steps (Sub-Task) 1. Hydraulic Works site preparation and mobilization of
personnel, materials, and equipment’s.
2. Working Under Extreme Heat Environment, Heat
Stress.
3. COVID-19 prevention and protection.
4. Working with hand and power tools, Power & Drill
Machine.
5. Conduct of Housekeeping

Job Step SN Initial Risk Residual Responsibility


Hazard’s Control Measures Risk
Probability Severity Risk Probability Severity Risk Responsible

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

Person

• Unauthorized commencement of L3 C4 4 • Authorized Work permit holder shall L3 C5 3


works. ensure to obtain and maintain valid
1. • Unavailability of Work permit Work permit (and other required and
required attached certificates for approved documents)
the job. • The supervisor responsible for this
activity must check all required
certificates, photography permit and
other documents are attached and
placed on worksites.
• To comply with all necessary
documentations and permit
requirements prior to commencement
of activities.

• Poor Communication. L3 C4 4 • Discussion of work steps/sequences to L3 C5 3


all work members (with translation-if
possible) before the actual Activity
• Maintain and establish good
coordination and communication
between team members
• Shall have proper approval and
communication from Roots PMT,
Hadeed Focal Point and Station Permit
Authority/Controller for the activity

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

• Exposure to H2S L3 C4 4 • Ensure that no unauthorized personnel L3 C5 3


• Emergency in the working area.
• Personal H2S/Toxic Clip shall always be
worn.
• Ensure that all personnel should have a
valid H2S training ID Card.
• Ensure that gas testing done before
starting the activities.
• Ensure that all personnel fully
understand to raise alarm in event of an
emergency and all personnel are fully
aware the action to be taken in case of
emergency, the nearest muster point,
emergency number and the safe escape
route.

• Emergency response L3 C4 4 • Stop the work L3 C5 3


• Check wind direction
• Locate nearest Assembly point and
emergency exit
• Evacuate upside.
• Use H2S clip
• Inform Hadeed control room
• Use of emergency Hadeed number.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

2. • Heat stroke/Stress • To follow State Law for summer


L3 C4 4 L3 C5 3
• Cramps/ Heat Exhaust working hours, outdoor activities during
• Dehydration summer shall have break down as pe
• Poor ventilation procedure.
• Follow Hadeed HSE Heat Stress
Management Guidelines & OH(D) Heat
Stress Management Plan.
• Rest shelters to be provided.
• Welfare facilities to be provided.
• Cool drinking water igloos to be
provided.
• Toolbox talk to be conducted and
ensure all workers aware to response in
heat stress risks, If any worker feel
dizzy, has a headache, moist, pale skin
or weak.
• Schedule work/rest/drink water as per
heat index
• requirements/ regulations.
• Warning flags to be displayed at
frequent locations.
• Avoid dehydration: rest and drink water
frequently.
• Personal water flask to be provided.
• No plastic (fizzy drink) bottles to be
used, disposable plastic cups for
drinking water to be provided.
• No water no work rule to be
implemented shall implement and
follow up the Heat Stress Prevention
Check List, any failure can lead to
stop/suspend the work activity.
• Heat index to be monitored hourly and
recorded with a calibrated Anemometer
and documented.
• Follow the work ratio as per heat stress
prevention measures.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

3 • Biological Hazards L3 C4 4 • Ensure Temperature Screening for all L3 C4 3


• Cold & Flu Virus personnel involved of the activities.
• Ensure to check flu symptoms, fever,
cough, and shortness of breath
reported to immediate supervisor and
project management team.
• Ensure COVID-19 Mandatory PPE (mask,
disposable gloves, etc.) shall always be
worn.
• Keep working surfaces sanitized
• Avoid touching your face, your eyes and
mouth.
• Catch coughs and sneezes in a tissue.
Disposed of the tissue responsibly in
trash bin.
• Good Hygiene and clean environment
should be maintained. Wash your hands
frequently with soap and water and or
use hand sanitizers-alcohol.
• Maintain Social Distancing, minimum of
1.5 meter apart.
• Avoid direct contacts, no shaking hands
• Avoid spitting and direct contacts with
installation.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

4 • Finger injuries (pinch, nip points) L3 C4 4 • Only experienced and competent L3 C5 3


• Hand and body injuries personnel to do the installation and
witness by Hadeed representative and
to be done in accordance with stated
procedure on approved method
statement.
• Perform preoperational inspection
• Connect the wrench to the hydraulic
pump
• Plug in the hydraulic pump
• Start the pump
• Test the function of the wrench and
pump
• Setting the Reaction Arm
• Setting Torque
• Setting the appropriate pressure on the
Pump
• Ensure no deviation on procedure
stated on approved method statement.
• Proper manual handling technique
should be observed.
• Ensure that all hand tools used are in
good condition
• Wear appropriate gloves while
installation.
• Inspection of hand tools for damages
before use
• Ensure that all hand tools used are in
good condition
• Defective tools shall be removed from
service

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

• Dropped objects leading to feet L3 C4 4 • Close supervision while doing the L3 C5 3


injuries installation.
• Ensure that tools are secured, use tools
belt while doing the activity.

• Improper manual handling L3 C4 4  Use correct manual handling techniques L3 C5 3


 Maintain good coordination and
communication between team
members
 Access routes is clear from all potential
obstacles
 Do not place hands and fingers in trap
points
 Ensure adequate manpower for the job

• Slips/trips/falls L3 C4 4  Conduct walkways and access routes, L3 C5 3


access routes should be clear from all
potential obstacles
 Use appropriate means of accessing
areas which is difficult to reach
 Ensure hand and fingers away from
pinch points, sharp and protruding
objects.
 Good command from the Supervisor
 Ensure that all personnel will avoid
overreaching.
• Hand and finger injury.  Inspect hand and power tools prior to
5 • Rotating tools parts – entanglement L3 C4 4 each use L3 C5 3
• Cuts, rush, bruises, electrocution,  All hand power tools shall be physically
• Flying debris/dust inspected and tested by competent
• Hand and eye injuries personnel
• Sharp edges  If using battery drills, ensure to remove
the battery before replacing or
installing new drill bits
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

 Ensure that only trained and


experienced personnel will operate the
drill
 Continuous training/awareness sessions
be conducted to all users and
Supervisors
 Install visual tags/labels for power
toolsas reminders on safe its safe use
 Never remove safety guard from
powers tools
 Do not rush is replacement of drill bits.
Do not take shortcuts
 Do not operate in wet or damp
environments
 User to be familiar with the safety
switch of each power tools
 Before servicing any power tools, such
as changing drill bits, saw blades, or
grinding wheels, you must unplug the
tools
 Damage tools or equipment’s shall be
removed from service and tagged”
Damage”
 Only appropriate tools shall be used for
the job. Do not use makeshift tools
 Ensure hands, feet and loose clothing
are kept clear from moving parts of the
drill.
 Ensure Drill bit is tightened, drill
checked properly
 Always maintain good housekeeping.
 Appropriate PPE for the task must be
used, such as eyeglasses, gloves, face
shields and earplug (as applicabel) shall
be available when using hand and
power tools

6 • Trips and falls/Sharp Objects L3 C4 4  All waste generated shall be contained L3 C5 4


and disposed off in designated waste
areas
ICMS (International construction & manufacturing services)
JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

 All materials shall be removed from the


site to a safe storage location
immediately after the work

Prepared by: HSE Engineer Acknowledged by Section Manager:

Name:__________________ _________________________Signature:__________________________ Badge:__________

JSA Team Members


Team members include area owner, maintenance, EHSS, Technical supervisor or engineer. if needed, contractor (if job is to be done through
the contractor)
Name: ________________ Signature: _________________ Badge: ______
Name ID Department Signature Date

Note: For risks cannot be reduced or mitigate after formal JSA study,
then approval shall be obtained as per SHEM-02 SAFER requirement.

Approved by Department / Operation Manager:

Name:____________________________________ Signature:______________________________ Badge: ___________

Approved By

SN HOD Department Signature Date


01

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

Note: If Residual Risk is, Significant and above SAFER Approval Required.

ENDORSEMENT SECTION (This section shall be filled incase this document use for same scope of work in future)

Date Section Manager (Signature) Area Manager (Signature) Validity Date

SFM-08.10-SHEM-0

Emergency Procedures

In an emergency, or if a “stop work alarm” sounds.

 Stop work
 Shutdown the equipment
 Evacuate personnel to assembly points
 Account for every man. (Head Count)
 Re-enter work area only with permission from HSE & Security representative after hearing the all clear alarm.

Emergency Response

If Plant emergency should arise, the Emergency Action Plan, approved by ……………………. shall be followed.

Note: The Project In –charge, Safety Officer, Supervisor, or employee shall stop all works in the event of emergency evacuation.

In case of emergency Call: .......................................

Pre-work instruction to all personnel exposed to hazards. Outline precautions. Attendees to sign form which is attached to work permit documents.

ICMS (International construction & manufacturing services)


JOB SAFETY ANALYSIS (JSA) AND HAZARDIDENTIFICATION PLAN (HIP):

ICMS (International construction & manufacturing services)

You might also like