FOR
EPC Project
Iskandar N. /
A 13-02-2020 For Information F. Adi Putra Budi S. M. Hayama
T. Fujita
~ Revision History ~
CONTENTS
PAGE
I. GENERAL ....................................................................................... 4
II.SCOPE ............................................................................................ 5
I. GENERAL
I.1 Purpose
The purpose of this Work Method Statement as guide for NSI i-III Project and explaining the
details of Heavy Duty Polymer Flooring System.
I.2 Definition
NSI PT. NIPPON SHOKUBAI INDONESIA
EPC Engineering, Procurement and Construction work
i-III Project NSI Acrylic Acid Plant Phase 3 Project
Project No. 18123
Site Location Kawasan lndustri Panca Puri,JI.Raya Anyer Km.122 Ciwandan
Cilegon 42447 Banten, Indonesia
CLIENT NSI
CONTRACTOR IKPT and SMCC consortium
TOYO Toyo Engineering Corporation.
IKPT PT. INTI KARYA PERSADA TEHNIK
SMCC PT. SMCC Utama Indonesia
JSA Job Safety Analysis
PTW Permite to Work
EDMS Electronic Document Management System
SHOKA TOYO’s Standard Document Management System
LMS Letter Management System as a sub-system of SHOKA
LAE Lead Assigned Engineers
AE Assigned Engineers
Approval Action of officially agreeing to EPC Deliverables or accepting them as
satisfactory
Review Formal assessment or examination of EPC Deliverables with the
possibility or intention of instituting change if necessary
WORK METHOD STATEMENT
HEAVY DUTY POLYMER FLOORING SYSTEM
FOR
i-III Project
Issued 13-02-2020 Project Document No: ED-000-CST-WMS-0021 Rev.A Page 5 of 9
I.3 Reference
NSI’s and contractor’s HSE regulation.
II.SCOPE
This method statement cover general requirement for heavy duty polymer flooring system of
contractor in area i-III Project at PT. Nippon Shokubai Indonesia which requires the heavy duty
polymer flooring system.
IV.WORK SEQUENCE
This method statement prior to work has to be briefed to all member of work team as a guide to
them and be able to do heavy duty polymer flooring system within quality and safety
requirements.
IV.1 Preparation
1. Submit work method statement and JSA for review prior to work implementation;
2. All machine and equipment to be used in the work should be checked and certified during
entry (driver’s licence or specialist certificate if required);
3. All worker to attend induction with safety personnel;
WORK METHOD STATEMENT
HEAVY DUTY POLYMER FLOORING SYSTEM
FOR
i-III Project
Issued 13-02-2020 Project Document No: ED-000-CST-WMS-0021 Rev.A Page 6 of 9
4. Work permits before start to work shall be approved by safety team and placed in the
location put base cover ground;
5. Barricade working area and place warning signs (if required);
b. Apply the mixture using a spatula. The function as an epoxy filler for repair or patching.
3. Wait for it to dry completely at least 24 hours before proceeding to the next application
stage.
V.SAFETY PRECAUTION
Safety will be the first consideration and the highest priority. The heavy duty polymer flooring
system will follow safety viewpoints, following :
1. Make sure the necessary document prior to work is being approved by authorized
personnel;
WORK METHOD STATEMENT
HEAVY DUTY POLYMER FLOORING SYSTEM
FOR
i-III Project
Issued 13-02-2020 Project Document No: ED-000-CST-WMS-0021 Rev.A Page 8 of 9
2. Ensure the risk of work to be performed, prior to start have been assessed and the
countermeasures have been determined. Make sure JSA are cascaded to the workers and
clearly understood before working starts;
3. Make sure “Tool Box Meeting” in working place is conducted before starting work;
4. Ensure all workers are wearing proper PPE during doing their job;
5. Make sure all tools and equipment are checked prior to use and regular checking shall be
done;
6. Safety sign and hard barricade should be placed surrounding the location and as per
directed by contractor. Clear and safety for access go to heavy duty polymer flooring
system area;
7. Proper lighting will be prepared before over time night work.
WORK METHOD STATEMENT
HEAVY DUTY POLYMER FLOORING SYSTEM
FOR
i-III Project
Issued 13-02-2020 Project Document No: ED-000-CST-WMS-0021 Rev.A Page 9 of 9
Start
Work prepation
Finish