KONTRUKSI

JASA ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING DAN CERTIFICATION


GAS FLOWLINE FACILITIES FROM TGA 19 to TGA 1/7
MINARAK BRANTAS GAS, INC.
2019

UNIT PRICE
Qty TOTAL PRICE (Rp)
NO DESCRIPTION UNIT (Rp) Keterangan
(a) (b) (c) = (a)+(b)
IV CONSTRUCTION 1.808.041.310
IV.E Underground Flowline 2x 825 m from TGA-19 to TGA-1/7 Lot 1
IV.E.1 JASA PEKERJAAN PENANAMAN FLOWLINE 6"
IV.E.1.1 Pipe hauling, 825 m x 2 Line m 1650 - By ADP
IV.E.1.2 Stringing 825 x 2 Line m 55.000 1650 90.750.000 Man power, alat , consumabel and etc by EKJ
IV.E.1.3 Trenching 1.2 m x 1.8 m x 900 m m 675.000 825 556.875.000 Man power, alat , consumabel and etc by EKJ
Man power, alat , consumabel and etc by EKJ
IV.E.1.4 Lowering m 65.000 1650 107.250.000
( Marker tipe by ADP )
IV.E.1.5 Backfilling m 130.000 825 107.250.000 Man power, alat , consumabel and etc by EKJ
Rekondition & Reinstatement (include material and installation of marker post every Man power, alat , consumabel and etc by EKJ
IV.E.1.6 m 200.000 825 165.000.000
100 m and marker sign every 500 m) ( Marker post dan Marker sign by ADP )
Man power, alat , consumabel and etc by EKJ dan
IV.E.1.4 U-Ditch 30 x 30 x 120 Ea 220.000 412,5 90.750.000
Material Udit by ADP
IV.E.1.5 Boring
Include Casing 10" & Accesories include venting
IV.E.1.5.1 Road Crosing m 2.400.000 56 134.400.000
galvanis pipe 1.5 inc
IV.E.1.5.2 River Crosing m 2.900.000 20 58.000.000 U-ditch by ADP
IV.E.2 MECHANICAL CONSTRUCTION
IV.E.2.1 FIT-up & WELDING (Incl. Consumable, Equipment,Installation & Man Power) Dia.in 242.000 1164 281.688.000 Man power, alat , consumabel and etc by EKJ
IV.E.2.2 Wrapping Elbow (Jasa + Material) Ea 165.000 26 4.290.000 Material by ADP
IV.E.2.3 Field Joint Coating (Jasa + HSS material) Joint 165.000 170 28.050.000 Material by ADP
IV.E.2.4 Holiday test of all underground flowline Lot 7.500.000 1 7.500.000 Holiday test ( alat dan man power by EKJ )
IV.E.5 Civil Work

IV.E.5.1 Control Box 3500 x 3500 x 3000 mm dimensi sesuaikan dengan CB 2 FL TGA 16/17

IV.E.5.1.1 Trenching m3 100.000 81 8.100.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.2 Turap lot 10.000.000 1 10.000.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.3 Strous @4m m 100.000 24 2.400.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.4 Dewatering lot 12.000.000 1 12.000.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.5 Pemasangan Begisting + Casing m2 300.000 96,25 28.875.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.6 rabatan m2 75.000 20,25 1.518.750 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.7 Penulangan/Pembesian m 16 kg 16.000 2327,5 37.240.000 Man power, alat , consumabel and etc by EKJ

IV.E.5.1.8 Concrete K175 m3 1.400.000 13,3 18.620.000 Man power, alat , consumabel and etc by EKJ

IV.E.5.1.9 Pembuatan Rangka Baja Atap Profil Siku 8 dan 6 kg 24.000 317,44 7.618.560 Man power, alat , consumabel and etc by EKJ
KONTRUKSI
JASA ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING DAN CERTIFICATION
GAS FLOWLINE FACILITIES FROM TGA 19 to TGA 1/7
MINARAK BRANTAS GAS, INC.
2019

UNIT PRICE
Qty TOTAL PRICE (Rp)
NO DESCRIPTION UNIT (Rp) Keterangan
(a) (b) (c) = (a)+(b)
IV.E.5.1.10 Kolom Ekstra penguat Dinding (Pembesian RB D16) kg 16.000 756 12.096.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.11 Ladder lot 600.000 1 600.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.12 Pekerjaan Lapisan Kedap (Waterprofing) m2 250.000 66 16.500.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.13 Pekerjaan Plasteran m2 90.000 66,5 5.985.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.14 Pekerjaan Finishing Acian m2 20.000 66,5 1.330.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.15 Benangan m' 20.000 56 1.120.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.16 Pekerjaan Pengecatan m2 60.000 12,25 735.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.17 Pek. Pemasangan Venting lot 1.500.000 1 1.500.000 Man power, alat , consumabel and etc by EKJ
IV.E.5.1.18 Pekerjaan Rekondisi CB lot 10.000.000 1 10.000.000 Man power, alat , consumabel and etc by EKJ

Surabaya, 11 Februari 2020


PT. ESTETIKA KENCANA JAYA

Hardja Gunadibrata
Direktur