I EXCAVATION
1 SITE CLEARANCE
2 GENERAL EXCAVATION
3 FILLING
3.1 Backfilling
Page 1/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
4 DISPOSAL
Page 2/30
Unit Rates - Concrete Work
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
II CONCRETE WORK
1 IN-SITU CONCRETE
2 REINFORCEMENT
Page 3/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
3 FORMWORK
5 EXPANSION JOINTS
Page 4/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
6 WATERPROOFING
7 INTEGRATED FINISH
Page 5/30
Unit Rates - Brickwork and Blockwork
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
1 CLAY BRICKS
2 CONCRETE BLOCKS
3 GLASS BLOCKS
Page 6/30
Unit Rates - Roofing
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
IV ROOFING
1 TILE ROOFING
2 BUILT-UP ROOFING
Page 7/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
A Concrete grade 20 to roof slabs; finished to falls m2 30.33 30.27 30.27 30.27
B Concrete grade 25 to roof slabs; finished to falls m2 34.93 34.87 34.87 34.87
3 METAL ROOFING
4 RAINWATER GOODS
4.1 Flashings
Page 8/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
5 SUNDRIES
5.1 Insulation
Page 9/30
Unit Rates - Carpentry and Joinery
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
1 CARCASSING
2 FRAMING
3 LININGS
3.4 Plywoods
Page 10/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
4 WALL INSULATION
5 PANELLING
Page 11/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
6 FLOORING
A 12mm thick x 70mm wide x 400-1200mm randon length m2 86.57 86.57 86.57 86.57
Indonesia teak
B 12mm thick x 70mm wide x 400-1200mm randon length m2 98.93 98.93 98.93 98.93
Burmese teak
C Extra over for 9mm thick WBP plywood to underside of m2 16.17 16.17 16.17 16.17
teak strip flooring (m/s) laid on prepared screed (m/s)
D Extra over for 9mm thick MR plywood to underside of teak m2 18.50 18.50 18.50 18.50
strip flooring (m/s) laid on prepared screed (m/s)
7 TIMBER DOORS
Hollow core flush door panel faced both sides with timber
veneer; complete with hardwood lipping all round
(including supply and installation of sub-frame, frame /
architrave and installation of ironmongery)
*C overall size: 900 x 2100 x 38mm thick; single leaf No 440.00 440.00 440.00 436.67
*D overall size: 900 x 2100 x 45mm thick; single leaf No 491.67 491.67 491.67 488.33
Page 12/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
INTERNAL WALLS
8 PARTITIONS
A 75mm thick walls with gypsum plasterboard on both sides m2 63.50 63.50 63.50 63.50
B 75mm thick walls with fibrous plasterboard on both sides m2 71.67 71.67 71.67 71.67
C 75mm thick walls with calcium silicate board on both sides m2 80.00 80.00 80.00 80.00
F 100mm thick walls with calcium silicate board on both m2 99.33 99.33 99.33 99.33
sides
Page 13/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
I 100mm thick walls with calcium silicate board on both m2 118.33 118.33 118.33 118.33
sides
Page 14/30
Unit Rates - Structural Steelwork
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
VI STRUCTURAL STEELWORK
1 Structural Steel
Page 15/30
Unit Rates - Metal Work
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
Page 16/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
2 Metal Cladding
2.1 Aluminium
3 Metal Doors
Page 17/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
4 RAILINGS
Page 18/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
Page 19/30
Unit Rates - Floor Finishes
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
1 IN-SITU FINISHES
Page 20/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
2 CARPET FINISHES
2.1 Labour
3 VINYL FINISHES
3.1 Labour
4 STONE FINISHES
4.1 Labour
5 TILE FINISHES
5.1 Labour
Page 21/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
A 80mm thick brick paver to floor; generally m2 44.92 44.93 44.93 45.60
B 80mm thick concrete paver to floor; generally m2 54.08 54.10 54.10 54.77
7 GLASS BLOCKS
8 RAISED FLOORING
9 SUNDRIES
Page 22/30
Unit Rates - Wall Finishes
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
IX WALL FINISHES
1 IN-SITU FINISHES
2 TILE FINISHES
2.1 Labour
3 STONE FINISHES
3.1 Labour
Page 23/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
4 SHEET FINISHES
4.1 Labour
Page 24/30
Unit Rates - Ceiling Finishes
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
X CEILING FINISHES
1 IN-SITU FINISHES
2 SUSPENDED CEILINGS
C 600 x 600 x 20mm thick Acoustical mineral fibreboard, pre- m2 34.83 34.83 34.83 34.83
finished face pattern panels with a white paint finish
D 600 x 600 x 9mm thick calcium silicate board m2 35.00 35.00 35.00 35.00
E 600 x 600 x 13mm thick calcium silicate board m2 39.67 38.67 38.67 38.67
F 600 x 600 x 9mm thick cement board m2 35.10 34.77 34.77 34.77
G 600 x 600 x 12mm thick cement board m2 41.33 40.67 40.67 40.67
H 600 x 600 x 9mm thick fibrous gypsum board m2 31.50 31.50 31.50 31.50
I 600 x 600 x 13mm thick fibrous gypsum board m2 34.60 34.60 34.60 34.60
J Extra over for every 1.5m high m2 2.00 2.00 2.00 2.00
Page 25/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
Page 26/30
Unit Rates - Glazing
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
XI GLAZING
1 STANDARD GLASS
1.1 In Panes
1.2 In Louvres
Page 27/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
1.3 In Panels/Doors
2 SPECIAL GLASS
2.1 Mirrors
3 SHOWER SCREEN
Page 28/30
Unit Rates - Painting
Last Updated on 04/03/13
[The data will be updated on a quarterly basis]
XII PAINTING
1 INTERNAL PAINTING
Page 29/30
ITEM DESCRIPTION UNIT 2012Q1 2012Q2 2012Q3 2012Q4
MEAN MEAN MEAN MEAN
A two coats of aluminium primer, one undercoat and two m 3.07 3.07 3.07 3.07
finishing coats of synthetic enamel paint
B two coats of zinc chromate primer, one undercoat and two m 3.17 3.17 3.17 3.17
finishing coats of synthetic enamel paint
A one coat of polyvinyl acetate primer, one undercoat and m 2.57 2.57 2.57 2.57
two finishing coats of synthetic enamel paint
2 EXTERNAL PAINTING
3 GENERAL
3.1 Labour
Page 30/30